Invoice CNE Baucau Final
Invoice CNE Baucau Final
Invoice CNE Baucau Final
Adeline Carrier
OIC, Head of Governance Unit
UNDP Timor Leste
Madam, we are pleased to submit to your good office our Progress Accomplishment
Billing 100% according to the contract Amount of US $ 128,016.83 (One Hundred and
Twenty-Eight Thousand and Sixteen Point Eighty-Three United States Dollar Only) with
the amount to be transferred for this payment of US$ 89,611.78 (Eighty-Nine thousand
Six hundred and Eleven American dollars point seventy- Eigh cents only) for the
construction New office building of CNE in Baucau municipality no Contract Contract
Ref. no: UNDP/TLS/CW/2022/043 in the, along with its supporting pertinent documents.
INVOICE NO:
DATE
40A/V/2023/02_NC-CNE
INVOICE
30 May 2023
Baucau
INVOICE TO
UNDP / CORE – TL Project
UNDP Timor Leste
Caicoli, Dili-Timor Leste
Reference to the contract signed between UNDP Timor Leste and the One 4-All Unipessoal Lda
company on October 24, 2022 is numbered UNDP/TLS/CW/2022/043 on article 3 Price and payment 3.3
which contains
Due dates
after %
% of Amount
No Deliverable / Output signature of Disbur
Progress contract In USD
sement
Installment 2:
Column casting up to beam
completed
Roof beam casting completed
Underground water tank
construction completed with all
arrangements
Septic tank construction
completed with all arrangements 50 % 3 month
D2 20% USD 25,603.37
Overhead rainwater facility
construction completed with all
arrangements
Domestic water tank facility
construction completed with all
arrangements
Completion of floor casting and
finishing
D3 Exterior and interior masonry 75% 4.5 month 25% USD 32,004.21
work completed
Tiling work completed
Drywall partitions wall
completed
Plastering work completed
Door and window installation
completed
Plumbing inside of the building
completed
Ceiling work completed
Truss installation work
completed
CGI sheet installation and
insulation completed
Eaves and gutters installation
completed