QM for Windows - [Data] Results


Start End Activity Early
Activity Early Start Late Start Late Finish Slack
node node time Finish
Project 19

1 1 2 5 0 5 1 6 1

2 1 3 5 0 5 2 7 2

3 1 4 7 0 7 0 7 0

4 2 5 4 5 9 6 10 1

5 2 8 3 5 8 16 19 11

6 3 5 3 5 8 7 10 2

7 4 5 3 7 10 7 10 0

8 4 6 6 7 13 8 14 1

9 5 7 7 10 17 10 17 0

10 6 8 4 13 17 15 19 2

11 6 9 5 13 18 14 19 1

12 7 8 2 17 19 17 19 0

13 7 9 1 17 18 18 19 1

14 8 10 0 19 19 19 19 0

15 9 10 0 18 18 19 19 1