Project : Construction of One Storey Building

Location :
Owner :

Item No. Description Quantity Unit Unit Price Cost

A. EARTH WORKS
A.1 Excavation 7.36 cu.m. 35.00 257.60
A.2 Backfill/Compaction 2.18 cu.m. 49.00 106.82
A.3 Embankment 3.28 cu.m. 55.00 180.40

Subtotal (Earthworks) 544.82

B. STRUCTURAL WORKS
B.1 Concrete works
a. Slab 1.45 cu.m. 3,250.00 4,712.50
Cast-In-Place Concrete
b. Materials(columns, footings and Beams) 3.15
Cement 23.00 bags 250.00 5,750.00
Sand 2.25 cu.m. 450.00 1,012.50
Gravel 3.50 cu.m. 920.00 3,220.00

Subtotal 14,695.00

B.2 Reinforced Steel Bars


a. Materials
Reinforced Steel Bars
12mmdia x 6.00m 21.00 pcs 312.50 6,562.50
16mmdia x 6.00m 8.00 pcs 405.25 3,242.00
20mm dia x 6.00m 16.00 pcs 500.40 8,006.40

Subtotal 17,810.90

Subtotal (Structural Works) 32,505.90

C. ROOFING WORKS
C.1 Roof Framing Works
a. Materials
2" x 4" C Purlins 9.00 pcs 605.00 5,445.00
2" x 6" C Purlins 2.00 pcs 695.00 1,390.00
.60mm x 45mm x 5m Metal battens 10.00 pcs 215.00 2,150.00
tekscrew 70.00 pcs. 0.80 56.00

Subtotal 9,041.00

C.2 Roofings & accessories


a. Materials(include insulation) 1.00 lot 23,450.00 23,450.00

Subtotal 23,450.00
Project : Construction of One Storey Building
Location :
Owner :

Sub-Total (Roofing Works) 32,491.00

D. MASONRY
D.1 4" thk. CHB 25.14 sq.m.
a. Materials
4" thk. CHB 326.82 pcs 12.00 3,921.84
Cement 18.00 bags 250.00 4,500.00
Sand 3.50 cu.m. 450.00 1,575.00
RSB (9mm dia x 6.00) 12.00 pcs 85.00 1,020.00

Subtotal 11,016.84

D.3 Plastering
a. Materials
Cement 12.00 bags 250.00 3,000.00
Sand 1.00 cu.m. 450.00 450.00

Subtotal 3,450.00

Subtotal (Masonry Works) 14,466.84

E. ARCHITECTURAL
E.1 Pebble washout
a. Materials
Black Pebble #10 16.00 bags 125.00 2,000.00
Cement 22.00 bags 250.00 5,500.00
40 x 40 Non-Slip Tiles 56.00 pcs 180.00 10,080.00

Subtotal 7,500.00

E.2 Paver
a. Materials
4"x 8"paver 350.00 pcs. 9.00 3,150.00

Subtotal 3,150.00

E.3 Pre cast


a. Materials
4" pre cast 7.00 l.m 125.00 875.00
Cement 6.00 bag 300.00 1,800.00

Subtotal 2,675.00

Subtotal (Architectural) 13,325.00


Project : Construction of One Storey Building
Location :
Owner :

F. CEILING FINISHES
F.1 Flexboard Ceiling - flat ceiling 27.72 sq.m.
a. Materials
Carrying Channel 12.00 pcs 89.00 1,068.00
Furring Channel 10.00 pcs 65.00 650.00
Wall Angle 11.00 pcs 32.00 352.00
Furring Clip 32.00 pcs 4.50 144.00
Blind Rivets 3/4" 1.20 boxes 102.00 122.40
Flexboard 6.0mm 15.00 pcs 575.00 8,625.00

Subtotal (Ceiling Finishes) 10,961.40

G. PLUMBING (DOWNSPOUT) 1.00 lot


a. Materials
3" dia PVC pipe 3.00 pcs. 380.00 1,140.00
3" PVC elbow 5.00 pcs. 36.00 180.00
Solvent Cement 0.75 can 750.00 562.50

Subtotal (Plumbing) 1,882.50

H. Electrical
a. Materials
4" Pinlight 6.00 sets 85.00 510.00
Wall Lamp w/ CFL 9watts 4.00 pcs. 675.00 2,700.00
9W CFL E27 230V Daylight 4.00 pcs. 73.00 292.00
Push Botton Switch 2.00 pcs. 305.00 610.00
Duplex Weatherproof Outlet w/ Cover 1.00 pc. 530.00 530.00

Subtotal (Electrical) 4,642.00

Grand Total 110,819.46