S-Curve Week-03
S-Curve Week-03
S-Curve Week-03
I PRELIMINERIES 1,00 ls 15,990% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777%
II EXCAVATION WORKS
Excavation; commencing from excavated level and not
exceeding 1.50m deep; to;
A Pile caps 454,88 m3 1,855% 0,265% 0,265% 0,265% 0,265% 0,265% 0,265% 0,265%
B Tie beams 95,30 m3 0,389% 0,056% 0,056% 0,056% 0,056% 0,056% 0,056% 0,056%
C Pad foundation 2,82 m3 0,011% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002%
Progres rencana 100,000% 2,390% 2,559% 13,514% 13,698% 24,494% 24,494% 13,869% 2,667% 2,315%
Komulatif Rencana 2,390% 4,948% 18,463% 32,161% 56,654% 81,148% 95,017% 97,685% 100,000%
Realisasi Progres Kemajuan pekerjaan per Minggu 3,064% 4,715% 18,463%
Realisasi Progres Kemajuan pekerjaan Komulatif 3,064% 8,307% 26,837%
Deviasi 0,674% 3,359% 8,375%
Cepat/Lambat Cepat Cepat
Week 1 2 3 4 5 6 7 8 9