S-Curve Week-03

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

S-CURVE SCHEDULE

THERMAX NEW FACTORY PROJECT


NAMA PEMILIK : P.T. THERMAX INTERNATIONAL INDONESIA
LOKASI PROYEK : KRAKATAU INDUSTRIAL ESTATE CILEGON

QYT SATUAN APRIL MEI JUNI


NO ITEM PEKERJAAN BOBOT ( % )
18 s/d 24 25 s/d 01 2 s/d 08 09 s/d 15 16 s/d 22 23 s/d 29 30 s/d 5 6 s/d 12 13 s/d 19
1 2 3 4 5 6 7 8 9

I PRELIMINERIES 1,00 ls 15,990% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777% 1,777%

II EXCAVATION WORKS
Excavation; commencing from excavated level and not
exceeding 1.50m deep; to;
A Pile caps 454,88 m3 1,855% 0,265% 0,265% 0,265% 0,265% 0,265% 0,265% 0,265%
B Tie beams 95,30 m3 0,389% 0,056% 0,056% 0,056% 0,056% 0,056% 0,056% 0,056%
C Pad foundation 2,82 m3 0,011% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002% 0,002%

Back Filling with excavated material; to:


D Pad foundation 2,43 m3 0,005% 0,001% 0,001% 0,001% 0,001% 0,001%
Disposal
Disposal surplus excavated material from site; to;
E Pile caps 454,88 m3 1,681% 0,240% 0,240% 0,240% 0,240% 0,240% 0,240% 0,240%
F Tie beams 95,30 m3 0,352% 0,050% 0,050% 0,050% 0,050% 0,050% 0,050% 0,050%
G Pad foundation 0,38 m3 0,001% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%
Surface Treatment
Compacted existing soil surfaces to CBR min. 5%; to;
H Pile caps 338,88 m2 0,429% 0,061% 0,061% 0,061% 0,061% 0,061% 0,061% 0,061%
I Tie beams 112,12 m2 0,142% 0,020% 0,020% 0,020% 0,020% 0,020% 0,020% 0,020%
J Pad foundation 2,56 m2 0,003% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000%
Earthworks Support
K Earthwork support to side of all excavations 1,00 ls 0,487% 0,097% 0,097% 0,097% 0,097% 0,097%
Sundries
L Allow for keeping all excavation free from water, 1,00 ls 0,609% 0,087% 0,087% 0,087% 0,087% 0,087% 0,087% 0,087%
mud and the like for the duration of contract by pumping,
bailing or other means including the provision of
all necessary pump, temporary plumbing etc.
III CONCRETE WORK
In-Situ Concrete
Sand Beds, 100mm thick spreading, levelling, and
compacting; to receive :
A Pile caps 338,88 m2 0,685% 0,137% 0,137% 0,137% 0,137% 0,137%
B Tie beams 112,12 m2 0,227% 0,045% 0,045% 0,045% 0,045% 0,045%
C Pad foundation 2,56 m2 0,005% 0,001% 0,001% 0,001% 0,001% 0,001%
Blinding layer, 50mm thick; to receive:
D Pile caps 338,88 m2 1,005% 0,335% 0,335% 0,335%
E Tie beams 112,12 m2 0,333% 0,111% 0,111% 0,111%
F Pad foundation 2,56 m2 0,008% 0,003% 0,003% 0,003%
Reinforced in-situ concrete designed mix Grade 30 Mpa;
20mm aggregate, vibrated as described, in
manufacturer's specification and Engineer's approval to:-
G Pile caps 404,05 m3 22,811% 7,604% 7,604% 7,604%
H Tie beams 78,49 m3 4,431% 1,477% 1,477% 1,477%
I Pad foundation 0,38 m3 0,022% 0,007% 0,007% 0,007%
J Pedestal 14,55 m3 0,821% 0,274% 0,274% 0,274%
Reinforcement bar to deformedv bars BjTd 40 (fy = 400 Mpa);
as described in
Pilecap
K 13mm diameter 1.048,24 Kg 0,583% 0,146% 0,146% 0,146% 0,146%
L 19mm diameter 15.198,16 Kg 8,455% 2,114% 2,114% 2,114% 2,114%
M 22mm diameter 20.810,19 Kg 11,577% 2,894% 2,894% 2,894% 2,894%
Tie beams 0,000%
N 13mm diameter 6.225,68 Kg 3,464% 0,866% 0,866% 0,866% 0,866%
O 19mm diameter 14.969,37 Kg 8,328% 2,082% 2,082% 2,082% 2,082%
Reinforcement bar to deformed bars BjTd 40 (fy = 400 Mpa);
as described in (Cont'd)
Pad foundation
A 13mm diameter 36,26 Kg 0,020% 0,007% 0,007% 0,007%
Pedestal
B 10mm diameter 1.245,47 Kg 0,693% 0,231% 0,231% 0,231%
C 16mm diameter 1.655,18 Kg 0,921% 0,307% 0,307% 0,307%
D 19mm diameter 1.848,44 Kg 1,028% 0,343% 0,343% 0,343%
Formwork in Konvensional System, finish strutting at/from any
level and including rebates or groove formers as
described to
E Side of pile cap Exceeding 1000mm high 593,80 m2 4,758% 1,189% 1,189% 1,189% 1,189%
F Side of tie beam 500-1000mm high 448,49 m2 3,594% 0,898% 0,898% 0,898% 0,898%
G Side of pad foundation n.e 250mm high 1,92 m2 0,015% 0,004% 0,004% 0,004% 0,004%
H Side of pedestal 500-1000mm high 132,23 m2 1,724% 0,431% 0,431% 0,431% 0,431%
Grouting
I Extra over concrete grouting to pedestal column 50mm thick 1,00 Ls 0,880% 0,440% 0,440%
Cutting-off pile heads
Cutting off heads of pre-cast concrete pile , including
excavation, disposal of debris and cleaning, straightening
and bending of projecting reinforcement for casting into
pile cap
A Precast concrete pile; square size 400x400mm, length <2.00m 187,00 Nr 1,656% 0,331% 0,331% 0,331% 0,331% 0,331%

Progres rencana 100,000% 2,390% 2,559% 13,514% 13,698% 24,494% 24,494% 13,869% 2,667% 2,315%
Komulatif Rencana 2,390% 4,948% 18,463% 32,161% 56,654% 81,148% 95,017% 97,685% 100,000%
Realisasi Progres Kemajuan pekerjaan per Minggu 3,064% 4,715% 18,463%
Realisasi Progres Kemajuan pekerjaan Komulatif 3,064% 8,307% 26,837%
Deviasi 0,674% 3,359% 8,375%
Cepat/Lambat Cepat Cepat
Week 1 2 3 4 5 6 7 8 9

Di Periksa oleh, Mengetahui, Cilegon, 18 April 2016


PT. TEAMWORX INDONESIA PT. THERMAX INTERNATIONAL INDONESIA PT. CITRA KARSA DINAMIKA

FARIED INDRAYANTA SANJEEV GOYAL DEDE RUSNA.K


CONSTRUCTION MANAGER PROJECT MANAGER PROJECT MANAGER

You might also like