Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

Mapeo de campos Sistema Ecosys a Sistema Project Online: Sync WBS

Nro
Nombre de Nro Nombre de Nombre Atributos
paráme Field Name API Field Name Flujo 1 Object Type Field Group Tipo de Dato Atributo Tipo de Dato Requerido Homologación Condiciones y reglas
Entidad parámetro Entidad API
tro Parking Lot
ECOSYS PROJECT ONLINE
<> 1 "" : [
Projects / Task
{
1.1.1 WBS Path ID WBS Path ID (1) Transaction Summary Attributes String 1.1.1
1.1.2 Description WBS Name (2) Transaction Summary Attributes String 1.1.2
1.1.3 Cost Account ID Cost Account ID (3) Transaction Summary Attributes String 1.1.3
1.1.4 UOM Transaction Summary Categories String 1.1.4
1.1.5 CostinProjectCurrency Budget in Project Currency (5) Transaction Summary Cost> Forecast Cost Money 1.1.5
1.1.6 Project Currency Project Currency (4) Root Cost Object Multi-Currency String 1.1.6
1.1.2 Description WBS Name (2) Transaction Summary Attributes String 1.1.2
1.1.8 PEP PEP (6) Cost Object Custom Field String 1.1.8
1.1.9 P50 Start Date Fecha Planeada Start (7) Cost Object MS Project Date 1.1.9
1.1.10 P50 End Date Fecha Planeada End (8) Cost Object MS Project Date 1.1.10

1.1.1 Object GUID SCH MSPO Cost Object Attributes String 1.1.1 IdDelProyecto IdDelProyecto Guid YES Id GUID created by MS Project.
1.1.2 Object GUID SCH MSPO Cost Object Attributes String 1.1.2 IdTarea IdDeTarea Guid YES Id GUID created by MS Project.
1.1.3 Hierarchy Path ID Cost Object Attributes String 1.1.3 EDT/WBS EDTDeLaTarea String YES
1.1.4 Cost Object Name Cost Object Attributes String 1.1.4 NombreTarea NombreDeLaTarea String YES
1.1.5 Object RollUp SCH MSPO Cost Object Ms Project String 1.1.5 Rollup LaTareaEsUnResumen String YES

}
</ > ]
Control de Versionamiento

Versión Fecha Modificado Por

0 2/15/2023 Maritza Parra Documento inicial


Versionamiento

Descripción

ocumento inicial
Sync WBS
Task
Unidirectional
MS Project EcoSys
Id Project, ID Task, Name Task,
Rollup

Business Rules

1. EcoSys must import via API provided by MS Project, the information Task level of one
project exist en MSPO

2. Periodicity
o Automatic: every Tuesday 00:01 a.m.
o On demand: for a specific project selected.

3. Information Filters
EcoSys:

a. Project with “Status” <> Close


b. Project was already created in MS Project -> ExternalKey != null

Project:
a. All task of project

4. Update Rules

a. If the MSPO taks don't exist in EcoSys, add row in project structure of EcoSys
b. If the MSPO taks exist in EcoSys, update row in project structure of EcoSysc.
c. task type according to Rollup field
oSys
Integración EcoSys - Project: Sync WBS

Scheduled
EcoSys API
Task Ecosys

UpdateWBS()

RequestAVProjects()

ReturnAVProjects()

RequestAuthorization()

ResponseAuthorization()

GenerateToken()

Loop Sync WBS

RequestTaskWBS()

UpdateWBS( ) ReturnTaskWBS()

ResponseUpdateWBS()
Project
Online

RequestAuthorization()

ResponseAuthorization()

eToken()

RequestTaskWBS()

ReturnTaskWBS()