Professional Documents
Culture Documents
Costing For Materials and Labour
Costing For Materials and Labour
2) A business makes wedding dresses. Each machinist is paid $30 a day and each supervisor $40 a
day. Each supervisor can work with up to 10 machinists and each machinist can produce one
wedding dress a day.
If 95 wedding dresses a day are produced, what is the daily labour cost?
A costs that are the same in total up to a certain level then increase with output
B costs that are the same in total over any output level
C costs that are constant per unit as output increases
D costs that increase per unit as output increases
A carriage inwards
B production materials
C wages of machine operators
D wages of stores staff
A fixed
B semi-variable
C stepped
D variable
6) An employee works a standard 40-hour week. In that time he is expected to make 200 complete
units. He is paid a bonus of $10 for every hour saved in production.
For week 25 he worked 44 hours and produced 250 units.
7) A manager is preparing a quotation for Job 88. A specialised technician is hired to work for this
job only. He will use machinery that the company already owns.
8) A business provided the following information for the past two months.
9) A manufacturing company employs 20 workers who are paid a basic rate of $30 per hour for a 40-
hour week. To meet a special order, the workers each worked 50 hours and were paid a premium of
40% over basic rate for the overtime.
What was the value of wages paid to meet the special order?
A fixed cost
B semi-variable cost
C stepped cost
D variable cost
1 Jessie is a manufacturer and uses a single raw material to make her product. The following table shows
inventory transactions for the month of March 2019.
Per kilo
Date Kilos $
March 1 Opening balance 1500 1.90
3 Receipts 3500 1.92
10 Receipts 2000 1.95
17 Receipts 1500 2.00
Jessie uses the First In First Out (FIFO) method to value her inventory. The following issues to
production took place.
Date Kilos
March 5 3000
23 4500
REQUIRED
[2]
[3]