DETAILED ESTIMATE FOR THE PROPOSED RESIDENTIAL BUILDING FOR :- MR.BINOY PHILIP ,
VILAYIL HOUSE, PAZHAMTHOTTAM , PAZHAMTHOTTAM (PO) MOB:9747260445 , IN RB NO:44, RS
NO: 79/1/3 , WARD:14 , OF AIKKARANDU PANCHAYATH AND AIKKARANDU NORTH VILLAGE
CENTER LINES
GOUND FLOOR
Sl N'o Heig
Descriptions Length Width Qty Unit Rate Amount
No s ht
A FOUNDATION
A-1 Earth work excavation in
hard soil and desposting with
lead up to 50 m. and lift up to
1.50 m including neat
banking and all labour
charges etc. complete.
foundation 1 88.90 0.60 0.60 32.00
etc complete…
Foundation 1 88.90 0.60 0.60 32.00
B RCC WORKS
3
Providing mechanicaly
vibrated reinforced cement
concrete M20 grade (1: 1 1/2
: 3) with minimum cement
content - 320 kg/m3 using
20mm hard granite broken
stone including cost and
conveyance of all materials,
precast concrete cover
blocks, labour form work,
watering, mixing, laying,
compacting, curing etc
complete. Including all cost of
materials and labour charges
etc complete....
B-1 Ground Floor
First Floor
Ground Floor
First Floor
Ground Floor
First Floor
4
Qty 4.30 m3
Deduction of Non lintel area
Ground Floor
First Floor
0.38
m3
Net Total qty 3.93
GROUND FLOOR
FIRST FLOOR
Ground Floor
Flat roof slab 1 110.48 0.12 13.26
FIRST FLOOR
Qty 25.98 m3
C BRICK MASONRY
5
Deduction Openings
Ground floor
First Floor
Say 50 m3 @ Rs.5500 / m3
50.00 m3 5500 275,000.00
D PLASTERING
D-1 Plastering inside walls and
partion walls with C.M.1:6
(river sand) 12mm thick one
coat floated hard and
trowelled smooth including
plastering on all joints of
masonry to rcc and all
chasing made in the walls for
electrical and plumbing lines,
finishing the top skirting with
cement screed, scaffolding ,
curing all labour charges ,
cost and conveyance of all
materials etc complete....
Ground floor
First Floor
Deduction Openings
Ground floor
First Floor
First Floor
E JOINERY
Lifting and fixing all joinery
woodden frames including
cutting masonry or concrete
wherever necessery for fixing
the joineries with cement
concrete and all necessary
hold fast , screws etc, all
labour charges and cost of
materials etc complete…
Ground Floor
First Floor
Ground floor
First floor
Bedroom 3 1 3.80 3.20 12.16
I
Glazed tiles bath roomwalls
including cement mortar 1:3
12mm thick onr coat
including cost and
conveyance of all materials
and all labour charges
Ground floor