Professional Documents
Culture Documents
Cement Batch Mixer
Cement Batch Mixer
© 2008 Halliburton
All Rights Reserved. Printed in the United States of America.
Section 1—Introduction
Section 4—Operation
i
ii
Section
1
Introduction
Overview
The BMR-100 batch-mixing trailer is a 100-barrel capacity batch-mixer trailer designed by
Halliburton for mixing oilfield slurries for use in a wide variety of purposes, including
drilling muds and spacers. Figure 1.1 shows an isometric view of the BMR-100 batch-mixer
trailer.
Figure 1.1—Isometric view of the BMR-100 batch-mixer trailer from the passenger's
side of the trailer
These units are built with a single-engine power pack, either one or two centrifugal pumps,
two 50-barrel batch tanks with agitators, and an operator's platform with control stand. Batch
tank agitators and centrifugal pumps are powered hydraulically and all power comes from the
single-engine power pack.
This manual provides information on the major components and systems of the BMR-100
batch-mixer trailer. Operating procedures, descriptions of major components, and basic
maintenance information will be covered in a task-oriented manner. An operator can best
use this manual for operation theory, training, basic setup of the unit, and preventative or
periodic maintenance. If maintenance and repair for major components is needed, see the
referenced repair manuals. A list of maintenance and repair manuals for other components
is included in this manual.
• The engine package is mounted on the gooseneck portion of the trailer, resulting in less
noise and maintenance access to both sides of the engine.
• Personnel can safely stand and work on top of the 50-barrel batch tanks. The top surface
of the batch tanks is equipped with handrails built to OSHA specifications.
• The trailer has the same 344-in. wheelbase and configuration as that used on the 75TC4
and Elite cementing trailers.
• The recirculation/booster pump is hydraulically operated for better speed control. The
hydraulic system is identical to that of the Elite cementing trailers and ISO Advantage
cementing skids.
• The trailer has an overall lower center of gravity.
• The eductor hopper and elbow assembly for the blower hose can remain permanently
mounted on top of the tank. These items are lower than the 13-ft, 6-in. height restriction
that is used as a design standard for land equipment.
• The trailer includes an arrangement for the bulk blower hoses wherein each elbow
assembly can be teed together in a Y configuration so that a single bulk hose from the
bulk truck can feed either batch tank.
• The low-pressure manifold has been designed to allow the suction lines from each
batch tank to be pressurized and washed out using the 6 × 5 centrifugal pump.
• The engine package is mounted on rubber isolators to reduce noise and vibration.
• Each batch tank includes two clean, in-place spray nozzles to assist in scrubbing and
washing the tanks after the job is complete.
• The fuel tank is mounted to allow the unit to be refueled at ground level.
• The batch tanks include large center opening hatches with removable lids to allow
access to the inside of the tank.
• Each batch tank includes four paddle-type, unsupported agitators instead of one. Four agitators
provide equivalent fluid movement and mixing, and eliminate maintenance of the previously
used bottom bearing.
• The design includes a 30° stair-type ladder that provides a very safe approach for boarding and
deboarding the unit.
• The unit includes a standard non-radioactive densometer and includes a 19-in. spool in the
discharge manifold for a conventional nuclear densometer, if required.
• The unit includes a 1-in. air diaphragm pump to be used for pumping chemicals from a drum at
ground level into each batch tank.
• The unit is designed to be manufactured with two 6 × 5 × 11 × 11 centrifugal pumps.
• Flat-topped tanks allow for material in sacks or buckets to be placed on top of the tank.
• The unit is equipped with an emission-certified engine that produces lesser quantities of pollu-
tion and smoke.
• The unit includes storage for up to 100 feet of suction hose and/or bulk hose, along with storage
capacity for loose iron and high-pressure rotary hoses.
Notes
2
Major Components and
Systems
Trailer Chassis
The trailer chassis wheelbase is 344 in. long when measured from the kingpin to the center of
the bogie. The trailer frame is manufactured from high-strength, low-alloy (HSLA) steel. The
trailer chassis is equipped with the following items:
The deck engine is equipped with a gear-type 13.2-cfm air compressor. This air compressor
supplies air for the 3-position valves in the control stand that are used to open and close
butterfly valves on the trailer. The engine also includes a 12-volt 100-amp alternator that
charges the two batteries on board the trailer. The batteries are located next to the engine on
the maintenance platform on the driver's side of the trailer.
Attached to the engine is a pump drive with built-in clutch. The pump drive can include up to
four hydraulic pumps. All four of these circuits are closed loop, and speed is controlled by a
joystick controller within the control stand of the unit. The four hydraulic pumps are:
• One or two Eaton ACL064 Closed-Loop Pumps—This pump is used to power the hydraulic
motor on the 6 × 5 pump that supplies fluid to the prehydrators.
If the trailer is equipped with two 6 × 5 centrifugal pumps, it will also include a second Eaton
closed-loop pump to power the hydraulic motor for the second 6 × 5 pump. This second 6 × 5
pump is capable of boosting or recirculating the batch tanks.
Note The second 6 × 5 centrifugal pump is optional and not all trailers are equipped to
include it. If the second pump is not included, one of the pads of the pump drive will
be covered with a blanking plate.
Similar to previous hydraulic-powered centrifugal pumps on other units, the centrifugal pump and
motor are direct coupled via a Woods-type coupling. Speed control of the centrifugal pump will be
accomplished by the joystick-type controller in the control stand. With the engine running at the
fully loaded speed of 2,200 rpm, each centrifugal pump should have a top speed of approximately
1,710 rpm while loaded and circulating water. This speed is a designed speed and is dependent on
several factors, including volumetric efficiency of the hydraulic system and age of the unit. The
speed of the centrifugal pumps may be +/- 50 rpm of the calculated speed.
An air-pressured oiler tank is included on the handrail of one of the batch tanks. This tank assembly
includes a 1/4-in. air ball valve with vent and an air-pressure regulator. The air regulator pressure
should be set between 3 to 6 psi.
Batch-Tank Modules
Table 2.2 lists the subcomponents included in each 50-barrel batch-tank module. The front 50-
barrel batch tank is shown in Figure 2.2.
Qty. Component
4 24-in. Diameter agitator
4 Parker/Ross 24.7-in.³/rev motor
1 Haldex-Barnes flow divider
1 Prehydrator with single built-in jet
1 5-in. Elbow assembly
2 Internal tank-washing nozzles
2 Handrail gates for loading bulk material
1 Inspection hatch near platform
1 Center service hatch
Each of the four agitators is equipped with two rows of blades. The bottom rows of blades are posi-
tioned so that they are at a 90° angle to the fluid surface. The upper rows of blades are positioned
so that the blades are at a 45° angle to the fluid surface. Two of the agitators have the upper row of
blades mounted at a 45° angle so that the fluid is directed downward into the tank when the agitators
are rotated clockwise (CW). The other two agitators have the upper row of blades mounted at a 45°
angle so that the fluid is directed downward into the tank when the agitators are rotated counter-
clockwise (CCW). The rotation and placement of the four agitators is shown in Figure 2.3. The
agitators are placed and rotated in a way that helps ensure that fluid is moved around the tank and
towards the center of the tank for more thorough mixing and delivery to the suction of the centrif-
ugal pump(s). The velocity of the fluid mixed will be greatest near the walls and corners of the tank.
Each tank has four agitators that are capable of variable speed control up to 135 rpm. All four agita-
tors on each tank are rotated at the same speed and are controlled by a single joystick controller
within the control stand.
Similar to previous batch mixers, each batch tank is equipped with a dry-material jet prehydrator,
which helps enable thorough mixing of the base fluid with dry ingredients as they flow together into
the mix tank. Flow of bulk cement can be throttled and regulated using the 5-in. butterfly valve in
the elbow assembly mounted directly above the jet prehydrator. Flow of fluid from the discharge of
the 6 × 5 pump can also be throttled and regulated using the 3-in. butterfly valve mounted on the
discharge manifold of the 6 × 5 pump before entering the prehydrator. The bulk inlet connections
for both the front tank and rear tank prehydrator are tied together and piped with flexible hoses
below the walkway of the trailer so that the hose from the bulk truck can be tied into the trailer at
ground level.
Each batch tank is equipped with a large service hatch in the center and a small inspection hatch
near the operator's platform. The service hatch can be used as an access point to wash the inside of
the tank after completing a job. Two levels of protection are present to help prevent items from inad-
vertently entering the hatch. Each hatch has fiberglass screening to prevent items such as tally
books, hardhats, and clipboards from falling into the tanks. This screening is not attached and can
be easily removed to allow better access to the inside of the tanks if necessary. Underneath the
screening, bolt-in sheet metal bars are spaced in such a way to help prevent a person from inadvert-
ently falling into the tank.
Inside each tank are two internal tank spray nozzles. These spray nozzles are plumbed to the
discharge manifold of the centrifugal pump(s) and include isolation valves to prevent cement slurry
from being pumped through them.
Caution Ensure that the 1-in. isolation valves are closed at all times during pumping or
recirculation. These valves should be used after the cement fluid has been
removed from the tank during washup, when the centrifugal pumps are pumping
water.
During washup of the tanks, the 1-in. isolation valve to the spray nozzles can be opened, allowing
water to flow through the spray nozzles. The spray nozzles spray water in a 270° spherical pattern,
thereby assisting in spraying the sides of the batch tank, top of the batch tank, and the agitator
paddles.
Remove and clean the nozzles on a regular basis to help prevent cement buildup. Each of the four
spray nozzles is attached with a 1-in. low-pressure Weco® union, which enables easy removal for
cleaning.
Figure 2.4 shows one of the spray nozzles in relation to the agitators and the inside of the tank.
Non-Radioactive Densometer
The BMR-100 batch mixer is equipped with a Micro Motion DL200 mass flowmeter. A mass flow-
meter is an instrument that can be configured to provide density of a fluid as an output parameter.
The Micro Motion DL200 mass flowmeter includes two 2-in. diameter inlet and outlet connections.
The inlet to the mass flowmeter is attached to the discharge piping of the centrifugal pump near the
centrifugal pump volute. The outlet of the mass flowmeter is attached to the top of the batch tank.
Fluid from the centrifugal pump is slip-streamed from the discharge of the centrifugal pump,
through the mass flowmeter, and into the top of the batch tank. Density of the fluid from the mass
flowmeter is read from a 4-20 mA display mounted in the control stand.
Calibration of the mass flowmeter should not be required after it is calibrated with water. If calibra-
tion is required, refer to the Micro Motion literature or website for instructions.
Take care to keep the mass flowmeter clean and free of cement buildup. If the meter plugs during
the job while the fluid is circulating, close the 3-in. throttling valve from the centrifugal pump to
the batch tank to force all flow of the centrifugal pump through the mass flowmeter. This action
should remove the obstruction. After the job, perform this same procedure to remove any cement
residue in the meter and adequately clean the meter. Also following the job, open the ½-in. ball
valve mounted to the volute of the centrifugal pump to drain washup water from the meter.
The DL200 mass flowmeter is mounted in a horizontal position underneath the operator's platform
(Figure 2.5). The mass flowmeter is self-draining, and fluid will drain from it into the centrifugal
pump and through the ½-in. ball valve in the volute of the centrifugal pump. The 4- to 20-mA
readout for the DL200 mass flowmeter is mounted inside the control stand (Figure 2.6).
Controls for the air actuators for the butterfly valves are located on the control stand along with
joystick speed controls for the centrifugal pumps and batch-tank agitators. Engine control functions
such as start, stop, throttle, engine speed, and emergency kill are included in the control stand.
Analog gauges for engine oil pressure, engine coolant temperature, voltmeter, and hydraulic oil
temperature are also included.
In addition to the analog gauges, the Murphy Powerview display is included for reading basic
engine parameters along with other engine parameters necessary for diagnostic and maintenance
purposes. The Murphy Powerview displays the following parameters:
• Engine rpm
• Engine hours
• Machine hours
• System voltage
• % Engine load at the current rpm
• Coolant temperature
• Oil pressure
• Fuel economy
• Throttle position
• Engine manifold air temperature
• Current fuel consumption
• Transmission gear oil pressure (not used)
• Transmission gear oil temperature (not used)
• Active service codes
• Stored service codes from the engine
• Set units for display (English or metric)
• Engine configuration parameters
A copy of the Murphy Powerview display manual is included in the appendix of this manual
detailing operation of this instrument.
System and charge pressure gauges for each of the hydraulic circuits are also included in the control
stand.
In the center of the control stand is a process and instrument (PI) diagram for the valve actuators for
the low-pressure manifold detailing which valve opens a specific actuator. This diagram can help
personnel develop confidence as they operate the unit.
The 4 to 20 mA readout for the mass flowmeter is also included in the control stand. The transmitter
for the DL200 mass flowmeter is either mounted inside of the control stand or very near to the
control stand. The 4- to 20-mA readout for the mass flowmeter is wired into this transmitter.
Light switches for lighting on the truck are also included in the control stand. Toggle switches for
halogen lights on the trailer are included for the front batch tank, rear batch tank, and control stand.
3
Pre-Trip Inspection
Before using the BMR-100 batch-mixer trailer on a cementing job, perform the following
steps before the trailer leaves the yard to help ensure that the unit is ready to perform a
cementing job. Verifying these basic prejob inspection items will, in most cases, diagnose a
component that is in danger of failure.
1. Check the engine water filters for signs of leakage before and after the engine is started.
2. Inspect the radiator hoses and connections for leaks. Check the coolant level in the radi-
ator. The fluid level should be 1 1/2 to 2 in. below the filler neck in the top tank.
Caution Do not remove the cap from a hot radiator. Major burns could result from
this action.
4
Operation
Introduction
Before operating the unit, the operator should become familiar with the BMR-100 batch-
mixer trailer by reading the manual and operating the unit in the yard's wash rack before using
the unit on location.
Operating Procedures
To operate the unit, perform the following steps:
1. Verify that the mass flowmeter is working correctly on the unit and is calibrated
correctly. The ideal way to verify is to circulate water through the mass flowmeter. With
water, the meter should read 8.2 to 8.3 lb/gal.
2. Verify that the ball valve for the cleanup nozzles is closed.
3. Run a suction line from the mixing water source to the suction side of the centrifugal
pump.
4. Open the correct butterfly valves and prime the centrifugal pump(s).
5. Engage the centrifugal pump to full speed and begin filling one of the batch tanks
through the prehydrator.
6. Check the jet pattern of the water jet.
7. Check the mixing bowl and elbow assembly for dry-cement buildup and clean out if
necessary.
Note Ensure that water in the batch tank from this procedure is either mixed with the
slurry or pumped off the unit before mixing.
8. If the water pattern is satisfactory and the bowl is clean, take on a premeasured amount
of water in each tank. To take on the water, either use the centrifugal pump or have the
water pumped into the tanks through the high-pressure fill line. If the unit is equipped
with a second centrifugal pump, this pump can also be used to fill the tank with the premea-
sured amount of water.
9. Attach the bulk delivery hose. If the material used is in sacks, attach the hopper to the prehy-
drator.
10. To begin mixing, open the appropriate discharge valves on the centrifugal pump connected to
the prehydrator and begin recirculating the water in the batch tank.
11. Turn on the batch-tank agitators.
12. Ensure that the bulk equipment operator is ready to provide a steady delivery of dry material.
13. When the operator is ready, open the master cement valve to begin adding cement or other dry
material. The slurry will be circulated through the centrifugal pump, through the mass flow-
meter, and into the batch tank. Slurry from the mass flowmeter will be circulated directly into
the batch tank. The remaining slurry will be circulated into the tank through the prehydrator.
As the slurry is circulated through the prehydrator, more dry material will be added. This
procedure will continue until the slurry is near the desired density.
14. After all cement has been mixed and pumped to a pumping unit, put at least 10 barrels of water
into the tank and circulate through the low-pressure manifold and the prehydrator to help
ensure that no cement remains.
15. Open the ball valve to the cleanup nozzles so that the nozzles can help wash the inside of the
tanks. Thoroughly rinse the agitator paddles and the inside of the tanks as well as any cement
that may be have accumulated on the outside of the unit.
The low-pressure suction manifold can be pressurized and flushed using the centrifugal pump(s).
Each length of suction manifold from the tank to the centrifugal pump is equipped with a 4-in.
discharge manifold tied into the suction manifold just after the tank outlet valve. To flush the
suction manifold, draw fresh water from one of the batch tanks with the centrifugal pump(s).
Discharge the water through the 4-in. discharge manifold. Close and open the appropriate valves to
direct water into the opposite suction manifold for the other tank and then through the pit connec-
tion, and ultimately into the waste pit.
After the suction manifold for one tank is flushed, reverse the process for the second tank. Flushing
suction lines in this manner was not possible with the previous trailer design. Flushing the lines in
this manner after each job can greatly reduce the likelihood of cement buildup in the suction lines.
The cleanup water can be discharged from the unit at the pit connection of the trailer. The pit
connection of the trailer is shown in Figure 4.1.
Notes
5
Test and Setup Procedures
Introduction
This section includes three test and setup procedures for the BMR-100 batch-mixer trailer.
The specifications and procedures can also be found on Matrix.
Notes
1. TEST INFORMATION
a. Instructions for use
i. This test procedure is intended to identify the minimum requirements for the testing of a
Batch Mixer Trailer (2003) with 2ea 50 bbl mixing tanks, twin Halliburton 6x5x11x11
centrifugal pumps, CAT C7 300 hp engine, Funk pump drive, Micromotion DL200
densometer with RFT9739 transmitter, Precision Digital loop-powered meter, and
Murphy PowerView.
ii. This test assumes the work will be performed by qualified technicians familiar with the
operation of the tested unit, the associated tools, and the equipment used in performing
the test. The test technician should read the entire procedure prior to starting. If there
are any questions concerning the test, please contact the Duncan Technology Center.
iii. This work is to be documented on test data sheet(s) at the end of this procedure by the
test technician(s) performing the work. Items in this test procedure that do not apply to
the unit being tested shall be indicated as being not applicable, “n/a”, in appropriate
locations on the test data sheet(s). This procedure is available in electronic format
through the Halliburton network and has been designed to enable manual or electronic
data entry.
b. Use the latest revision of the test
i. Retrieve latest version of the test procedure from matrix by the following procedure:
1. Open matrix checker and find the spec number of this document.
2. Open the latest revision to the specification that is in production release and print the specification.
3. Use the specification (test procedure) as a checklist to complete this testing.
2. UNIT INFORMATION
a. Operating and service standards for this unit.
MANUAL DESCRIPTION REF. NO.
Lubrication Standard 278.90538
Caterpillar C7 Service Manual 101502885
Caterpillar C7 Parts Manual 101502860
Funk Pump Drive Service Manual 100032617
Halliburton Centrifugal Manual 100003124
Alternator Service Manual 100047095
Alternator Parts Manual 100047096
Murphy PowerView Installation and Operations Manuel D00118626
Precision Digital Loop-Powered Meter Operations Sheet D00120037
b. General operating parameters for this unit.
Deck Engine - Cat, C7, 300 Bhp, 2100-2200 Rpm, Industrial, SAE 1 Flywheel Housing, ADEM 4, Dry Exhaust
Manifold, 13.2 CFM Air Compressor, EPA And CARB Tier 3 And EC Stage 3A Non-Road Emission
Certified
1 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
2 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
ii. Verify that high pressure filters are installed for correct direction of flow and fill with
ATF.
iii. Fill charge and loop filters with ATF and verify that they are properly installed for
direction of flow.
iv. Check all valves, filters, backflow preventers, hoses, etc... for correct installation and
direction of flow.
v. Fill inlet hoses, hydraulic pumps, and motor cases.
vi. Open all valves on suction lines to supply all pumps with fluid
vii. Purge air from main drive pump suction line.
viii. Remove upper case drain hoses or fittings if necessary and fill all hydraulic pump
and motor cases, (equipped with a case drain connection), with hydraulic fluid.
ix. Loosen suction hoses at all hydraulic pumps until oil is present, this will allow air to
escape from suction hoses.
x. Re-tighten all hoses, fitting, and plugs.
xi. Prime all hydraulic pumps driven by the pump drive.
xii. Automatic Transmission Fluid Halliburton Part No. 100001835 per lubrication standard,
Part No. 100053807
g. Halliburton centrifugal pumps (6x5)
i. Fill the pump lube tank(s) with Automatic Transmission Fluid Halliburton Part No.
100001835 per lubrication standard, Part No. 100053807
ii. Do not grease mechanical seal.
iii. If using an oil lubricant or grease system for a lip seal , be sure that the lubricating
system is connected to the pump and operating properly. The oil system should be
pressured at 5 to 7 psi.
iv. With a hand-operated grease gun (Part No. 70.24620 - Cartridge), grease the bearings
with five shots of Marine Lube “A” or an equivalent. Make sure that the pump turns
freely by hand.
v. Caution—If heat buildup is excessive, reduce the amount of grease. Grease expands
when heated, increasing pressure on the pump.
h. Axle hubs
i. Fill to site glass level if low.
ii. Lubricant per lubrication standard (Part No. 100053807).
i. Install all required grease zerks and fill with lithium grease, Part No. 100026247 (i.e.
pillow block bearings, flange block bearings, drive shafts, landing legs and leveling
jacks, discharge chutes, and belt tensioners, augers, Lo-Torq valves etc….).
4. PRE-START INSPECTION
a. Inspect overall unit to verify wiring and hoses are properly routed, secured, and
protected. Bend radii must not be less than minimum bend radii recommendations
for the particular material.
i. Wiring is secured at approximately 2-foot intervals.
ii. Hoses are secured at approximately 4-foot intervals.
iii. Wiring and hose are clear of rotating components.
iv. Wiring and hoses are armored at wear or pinch points.
v. Wire and hose bends exceed minimum bend radii
vi. Wiring and hoses are protected from hot spots
3 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
vii. Wiring and hoses are shielded when going over sharp corners, contacting other rub
surfaces, near hot surfaces, and near rotating shafts.
b. Pump primer on the fuel filter and prime fuel system.
c. Connect suction hose(s) to water supply and provide water with a centrifugal pump.
d. Inspect unit for general hazards that could endanger personnel when the unit is
started:
i. Leaks
ii. Missed welds
iii. Loose nuts or bolts, (including drive line bolts)
iv. Misaligned connectors or shafts
v. Loose wires, cables, or hoses
vi. Deformed or cracked components
vii. Covers, lids or guards that are not properly installed,
viii. Loose chains, belts, or idlers.
ix. Check woods coupling for proper alignment.
x. Hydraulic components that are improperly installed, routed, or reversed.
xi. Pneumatic components that are improperly installed, routed, or reversed.
e. Check all fluid levels.
f. Verify that the battery cables are labeled with a Pos and Neg nameplate or color coded
cables and connected correctly.
g. Verify that all suction valves on hydraulic lines/tank, fuel lines/tank, water lines/tank
are open.
h. Verify that all quick-disconnects are properly tightened and secured.
i. Open all hydraulic valves to purge air from system.
j. Connect data recording devices, as appropriate to record pump discharge pressure
and suction pressures. Identify recording device (unipro, gauges, DAS,
thermocouples, pressure transducers) and calibration information on Test Data Sheet
(serial Number, Description, Last Cal, Next Cal).
5. INSPECTION AND ADJUSTMENTS
a. Ensure the Loop Flushing Valve on each set of the RexRoth hydraulic piping is
partially open. There are two per unit, one on each agitator circuit.
b. Adjust pressure regulator to maintain 5-7 psi in centrifugal pump lube tanks.
c. Adjust pressure regulator to maintain 90-100 psi for control valves.
d. Connect water supply hose to suction manifold of driver side prehydrator pump.
e. Connect data recording devices, as appropriate to record pump discharge pressure
and suction pressures. Identify recording device (unipro, gauges, DAS,
thermocouples, pressure transducers) and calibration information on Test Data Sheet
(serial Number, Description, Last Cal, Next Cal).
f. Verify that the Loop-Powered meter is installed correctly and connected to the power
supply.
i. Turn on, set-up and calibrate the density measuring system .
ii. Calibrate the low side (4mA) to air (0 LB per gal).
iii. Calibrate the high side (20mA) by driving a 20mA signal from a portable computing
device to the Loop-Powered meter and setting this as 26 LB per gal.
iv. Check 9.1384 mA to flowing water (approx. 8.35 LB per gal) at the end of step 7.
4 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
g. Complete setup and test of the DL200 per Test Specification D00252345
h. Verify that all suction valves on hydraulic lines/tank, fuel lines/tank, water lines/tank
are open.
i. Pump primer on the fuel filter and prime fuel system.
j. Engage the engine clutch.
6. Startup
a. Safety
i. Verify that personnel and equipment are clear of potentially moving or rotating
components and that all guards and shielding are properly installed.
ii. Verify that all lubrication has been completed and that supply valves from tanks and
reservoirs (fuel, hydraulic fluid, pump lube, etc) are open.
iii. Verify that muffler is properly positioned with exhaust ventilation system, and that
exhaust ventilation system is running.
b. Setup and Adjustment
i. Connect CAT Engine Technician (ET) diagnostic software to Engine.
1. Turn the main power on and correct all engine faults
2. Set all customer parameters to appropriate values.
3. Confirm that run/stop control switch, engine throttle controls, and emergency kill switches are
working correctly.
4. Test over speed verify switch (if included on equipment).
5. Set over speed verify to off or disable.
c. Starting Procedure
i. Turn the main power switch on at the control panel of the enclosure.
ii. Crank engine with the run/kill switch in the kill position until engine oil pressure gauge
indicates 3 to 5 psi.
iii. Start the engine.
iv. Observe Unit for Major leaks and shut down immediately if necessary.
v. Observe the engine oil pressure gauge. If the oil pressure does not rise to above 5.9 psi
within 15 seconds after the engine starts, shut the engine down and determine the cause.
vi. Observe hydraulic oil pressure gauge and shut down the engine within 30 seconds if the
hydraulic oil pressure is low.
d. Engine Package
i. Verify the following items with engine idling at approximately 1000 rpm.
1. Engine oil pressure is acceptable.
2. Low Idle speed is correct.
3. Rated speed is correct.
4. Top No Load Speed is correct.
5. Hydraulic oil pressure is acceptable on all pumps
6. All leaks have been corrected.
7. The charging system is operating correctly.
8. The radiator fan is blowing air through radiator.
9. All engine faults have been corrected.
10. Main and remote throttle controls are operational.
11. Main Emergency shutdown controls and remote emergency shutdown controls are operational.
12. Murphy PowerView is initialized per D00118626 (PowerView operating instructions) and correct
any faults displayed.
e. Verify operation of the engine gauges and controls.
i. System voltage gauge
5 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
6 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
should start showing on the gauges within 30 seconds after disengaging clutch. If not,
shut down engine and check plumbing and pump rotation.
e. If charge pressure is indicated, leave at idle with stroke controls in the neutral or off
position until air is purged from the system indicated by a steady reading on gauge.
f. Verify that the oil pressure gauge on the engine is reading the appropriate oil
pressure. Allow the oil to circulate and the engine to warm itself for at least 10
minutes.
g. After 10 minutes, verify that the water temperature is adequate (minimum 170°F and
that the alternator is outputting the correct voltage.
h. Increase the throttle to full speed (2200 RPM).
i. The charge pressure for the centrifugal pump circuits should be within the following
ranges:
i. charge pressure in neutral (minimum) = 350 to 370 psi
ii. charge pressure in stroked position (minimum) = 325 to 345 psi
1. If the charge-pressure setting is not acceptable in neutral, adjust the charge relief in the pump. If the
charge pressure setting is not acceptable in the stroked position, adjust the pressure-relief in the
hydraulic motor.
j. Stroke the prehydrator pump slightly and check for proper rotation of the pump.
i. Prime centrifugal pump (run with water only during this testing, and do not operate
without water in the suction lines.)
1. Ensure water supply line is engaged and flowing.
ii. The proper orientation of the stroke control is forward to engage and back to neutral.
iii. Adjust the stroke-control neutral-position lock screw to prevent the valve from passing
the center position.
iv. If the centrifugal pump rotation is incorrect, determine the cause as per the engineering
drawing and correct the problem accordingly.
k. Stroke the recirculation pump slightly and check for proper rotation of the pump.
i. Prime centrifugal pump (run with water only during this testing, and do not operate
without water in the suction lines.)
1. Ensure water supply line is engaged and flowing.
ii. The proper orientation of the stroke control is forward to engage and back to neutral.
iii. Adjust the stroke-control neutral-position lock screw to prevent the valve from passing
the center position.
iv. If the centrifugal pump rotation is incorrect, determine the cause as per the engineering
drawing and correct the problem accordingly.
l. To allow air to escape from the loop, stroke the pumps in gradual increments a few
times before reaching full stroke.
i. All air has been purged when the charge-pressure reading is steady.
m. The charge pressure for the agitator pump circuits should be within the following
ranges:
i. charge pressure in neutral (minimum) = 340 to 360 psi
ii. charge pressure in stroked position (minimum) = 315 to 335 psi
1. If the charge-pressure setting is not acceptable in neutral, adjust the charge relief in the pump. If the
charge pressure setting is not acceptable in the stroked position, adjust the pressure-relief in the
hydraulic motor.
7 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
n. Once air is bleed from the system fully close the Loop Flushing Valve on each set of
the RexRoth hydraulic piping. There are two per unit, one on each agitator circuit.
o. Stroke the front agitator pump slightly and check for proper rotation of the agitator.
i. The proper orientation of the stroke control is forward to engage and back to neutral.
ii. Adjust the stroke-control neutral-position lock screw to prevent the valve from passing
the center position.
iii. Verify that the correct agitators are installed on the correct hydraulic motor. Each tank
contains two different configurations of agitators. Check agitator rotation and correct
installation of agitator to each motor. See engineering drawing D00100801, sheet 7 of
7. The correct rotation is clock wise as viewed from above looking down on the
agitator and the fluid should be pushed down.
p. Stroke the rear agitator pump slightly and check for proper rotation of the agitator.
i. The proper orientation of the stroke control is forward to engage and back to neutral.
ii. Adjust the stroke-control neutral-position lock screw to prevent the valve from passing
the center position.
iii. Verify that the correct agitators are installed on the correct hydraulic motor. Each tank
contains two different configurations of agitators. Check agitator rotation and correct
installation of agitator to each motor. See engineering drawing D00100801, sheet 7 of
7. The correct rotation is clock wise as viewed from above looking down on the
agitator and the fluid should be pushed down.
q. To allow air to escape from the loop, stroke the pump in gradual increments a few
times before reaching full stroke.
i. All air has been purged when the charge-pressure reading is steady.
r. When the charge pressures are steady and while a technician watches the gauge,
slowly open the Loop Flushing Valve on each set of the RexRoth hydraulic piping till a
50 psi drop is seen in each charge pressure. There are two per unit, one on each
agitator circuit.
s. Check oil level in hydraulic reservoir and refill as needed.
8. Function Test
a. Ensure engine speed is set to 2,200 rev/min.
b. Engage the DS 6x5 centrifugal pump, circulate water at maximum speed and finish
filling the front mixing tank.
i. Record centrifugal pump system pressure on test sheet.
c. Record the discharge pressure of the centrifugal pump while circulating water.
i. The minimum acceptable performance at “open” conditions is:
1. 6 X 5 PUMP – 15-25 PSI.
ii. Measure bearing/seal temperature(s) on pump with infrared thermometer on 5 minute
intervals. Record measured values on test data sheet.
iii. After bearing/seal temperature(s) have stabilized for three measurements (10 minutes),
record full open flow rate, discharge pressure, bearing/seal temperature(s), engine rpm,
engine temperature, engine oil pressure and system voltage.
d. Close the valves on the discharge side of the centrifugal pump after the pressure
gauge, and record the closed-in pressure.
i. Caution: Do not operate the pump closed-in for more than one minute at a time.
ii. Open the discharge valves
8 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
9 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
viii. Record agitator speed of each of the four agitators in both the front tank and rear
tank. Record the speed of the agitators. Agitator speeds should not deviate by more
than 15% from the slowest to the fastest agitator. Observe system pressure gauge.
Observe system pressure gauge and note if the hydraulic system surges or hunts for a
system pressure. If this condition occurs, note the severity and compare to the
performance once the oil is heated to operating temperature.
j. System Test Precautions to Watch during the Fully Loaded 30-Minute Run
i. During the 30-min test run, take the following precautions to ensure proper operation.
1. Keep the hydraulic reservoir filled to the full mark, and continually observe the system connections
for leaks.
2. Watch and listen for cavitation noises at hydraulic pumps.
3. Tighten all hoses that appear to leak any hydraulic fluid. Hoses that are not sufficiently tightened will
loosen even more when delivered to location, resulting in serious leaks when received by the field
location.
4. Ensure that the hydraulic temperature does not exceed 180°F.
5. With the system warm, check the hoses at the heat exchanger to make certain that oil is not bypassing
the heat exchanger.
6. Make certain that the arrow on the cooler check valve points from the inlet to the outlet line.
7. Check the filter bypass indicators for the bypass condition and change the elements if the bypass is
indicated or a major failure occurs on the system.
8. Check all low-pressure piping on the suction and discharge side of the centrifugal pumps. Correct
leaks at valve, victaulic connections, or welded joints.
k. Record speed of agitators on test sheet. (min 120 rpm)
l. After operating the system for 30 minutes and while fully loaded, record the hydraulic
oil pressure, water temperature, engine speed, air pressure, and voltmeter reading for
the engine.
m. Record the hydraulic oil temperature from the gauges in the case drain lines of the
hydrostatic pumps and the temperature of the oil in the reservoir.
n. Unload the engine and record speed on test sheet.
o. Follow proper system shutdown procedures.
p. Check the following fluid levels.
i. Engine crank case
ii. Hydraulic tank
iii. Fuel tank
iv. Radiator
q. Grease all zerks with lithium grease, Part No. 100026247.
9. Performance Test
a. This performance test allow the thermal cycling of the system since shutdown prior to
the road test being completed.
b. Complete inspections, adjustments and startups as stated above.
c. After 10 minutes, verify that the engine water temperature is adequate (minimum
170°F and that the alternator is outputting the correct voltage.
d. Ensure the hydraulic system is warmed up prior to running test.
e. Ensure engine speed is set to 2,200 rev/min.
f. Engage the DS 6x5 centrifugal pump and circulate water at maximum speed.
i. Record centrifugal pump system pressure on test sheet.
g. Record the discharge pressure of the centrifugal pump while circulating water.
10 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
11 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
viii. Record agitator speed of each of the four agitators in both the front tank and rear
tank. Record the speed of the agitators. Agitator speeds should not deviate by more
than 15% from the slowest to the fastest agitator. Observe system pressure gauge.
Observe system pressure gauge and note if the hydraulic system surges or hunts for a
system pressure. If this condition occurs, note the severity and compare to the
performance once the oil is heated to operating temperature.
n. System Test Precautions to Watch during the Fully Loaded 30-Minute Run
i. During the 30-min test run, take the following precautions to ensure proper operation.
1. Keep the hydraulic reservoir filled to the full mark, and continually observe the system connections
for leaks.
2. Watch and listen for cavitation noises at hydraulic pumps.
3. Tighten all hoses that appear to leak any hydraulic fluid. Hoses that are not sufficiently tightened will
loosen even more when delivered to location, resulting in serious leaks when received by the field
location.
4. Ensure that the hydraulic temperature does not exceed 180°F.
5. With the system warm, check the hoses at the heat exchanger to make certain that oil is not bypassing
the heat exchanger.
6. Make certain that the arrow on the cooler check valve points from the inlet to the outlet line.
7. Check the filter bypass indicators for the bypass condition and change the elements if the bypass is
indicated or a major failure occurs on the system.
8. Check all low-pressure piping on the suction and discharge side of the centrifugal pumps. Correct
leaks at valve, victaulic connections, or welded joints.
o. Record speed of agitators on test sheet. (min 120 rpm)
p. After operating the system for 30 minutes and while fully loaded, record the hydraulic
oil pressure, water temperature, engine speed, air pressure, and voltmeter reading for
the engine.
q. Record the hydraulic oil temperature from the gauges in the case drain lines of the
hydrostatic pumps and the temperature of the oil in the reservoir.
r. Unload the engine and record speed on test sheet.
s. Follow proper system shutdown procedures.
t. Check the following fluid levels.
i. Engine crank case
ii. Hydraulic tank
iii. Fuel tank
iv. Radiator
u. Grease all zerks with lithium grease, Part No. 100026247.
10.COMPLETE ROAD TEST PROCEDURE (Specification D00113295)
11.COMPLETE FINAL INSPECTION TEST PROCEDURE (Spec D00113918).
12.ACCEPTANCE CERTIFICATION
a. Review Recent Service Bulletins for this unit type and verify that all known issues
have been corrected on this unit.
b. Identify any components or systems of this unit that were not accepted, tested or
corrected or that did not meet the performance requirements identified in this
procedure or otherwise known as exceptions in the Acceptance Certification Section.
c. Fill in Signatory fields of the Acceptance Certification.
12 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
4 Pre-Start Inspection
Wiring is secured at approximately 2-foot intervals.
Hoses are secured at approximately 4-foot intervals.
Wiring and hoses are clear of rotating components.
Wiring and hoses are armored at wear or pinch points.
Wire and hose bends exceed minimum bend radii.
Wiring and hoses are protected from hot spots
Wiring and hoses are shielded when going over sharp corners, contacting other rub surfaces,
near hot surfaces, and near rotating shafts.
Inspect for the following hazards
Leaks
Missed welds
Loose nuts or bolts, (including drive line bolts)
Misaligned connectors or shafts
Loose wires, cables, or hoses
Loose chains, belts, or idlers.
Deformed or cracked components
Covers, lids or guards that are not properly installed
Check woods couplings for proper alignment.
Battery cables properly labeled
13 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
TEST INSTRUMENTS
TI # Description (DAS, Gauge, Unipro) Serial No. Last Cal Cal Due
1
2
3
4
14 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
Front agitator neutral charge pressure (psi) after opening loop flushing valve
Rear agitator neutral charge pressure (psi) after opening loop flushing valve
Front agitator stroked charge pressure (psi) after opening loop flushing valve
Rear agitator stroked charge pressure (psi) after opening loop flushing valve
8 Function Test
PUMP TEST RESULTS DS
Record average values for listed parameters during each run in the spaces provided below.
Flow Condition Full Flow Closed In
Bearing/Seal Temp (°F)
Discharge Rate ( GPM )
Discharge Pressure (psi)
Charge pressure (psi)
System pressure (psi)
Engine Speed (rpm)
Engine Temperature (°F)
Engine Oil Pressure (psi)
System Voltage (V)
PUMP TEST RESULTS PS
Record average values for listed parameters during each run in the spaces provided below.
Flow Condition Full Flow Closed In
Bearing/Seal Temp (°F)
Discharge Rate ( GPM )
Discharge Pressure (psi)
Charge pressure (psi)
System pressure (psi)
Engine Speed (rpm)
Engine Temperature (°F)
Engine Oil Pressure (psi)
System Voltage (V)
8 Function Test
Start of 30 Minute Test Run
Engine speed unloaded (rpm)
Engine speed loaded (rpm)
DS Centrifugal stroked charge pressure loaded (psi)
PS Centrifugal stroked charge pressure loaded (psi)
Front agitator stroked charge pressure loaded (psi)
Rear agitator stroked charge pressure loaded (psi)
DS Centrifugal system pressure loaded (psi)
PS Centrifugal system pressure loaded (psi)
Front agitator system pressure loaded (psi)
Rear agitator system pressure loaded (psi)
DS Centrifugal pump speed loaded (rpm)
PS Centrifugal pump speed loaded (rpm)
Maximum tub agitator speed (rpm) Front #1
Maximum tub agitator speed (rpm) Front #2
Maximum tub agitator speed (rpm) Front #3
Maximum tub agitator speed (rpm) Front #4
Maximum tub agitator speed (rpm) Rear #1
Maximum tub agitator speed (rpm) Rear #2
15 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
16 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
9 Road Test
Road Test (D00113295) completed.
10 Performance Test
8 Function Test
Start of 30 Minute Test Run
Engine speed unloaded (rpm)
Engine speed loaded (rpm)
DS Centrifugal stroked charge pressure loaded (psi)
PS Centrifugal stroked charge pressure loaded (psi)
Front agitator stroked charge pressure loaded (psi)
Rear agitator stroked charge pressure loaded (psi)
DS Centrifugal system pressure loaded (psi)
PS Centrifugal system pressure loaded (psi)
Front agitator system pressure loaded (psi)
Rear agitator system pressure loaded (psi)
DS Centrifugal pump speed loaded (rpm)
PS Centrifugal pump speed loaded (rpm)
Maximum tub agitator speed (rpm) Front #1
Maximum tub agitator speed (rpm) Front #2
Maximum tub agitator speed (rpm) Front #3
Maximum tub agitator speed (rpm) Front #4
Maximum tub agitator speed (rpm) Rear #1
Maximum tub agitator speed (rpm) Rear #2
Maximum tub agitator speed (rpm) Rear #3
Maximum tub agitator speed (rpm) Rear #4
Tub agitator motor Temperature (F) Front #1
Tub agitator motor Temperature (F) Front #2
Tub agitator motor Temperature (F) Front #3
Tub agitator motor Temperature (F) Front #4
Tub agitator motor Temperature (F) Rear #1
Tub agitator motor Temperature (F) Rear #2
Tub agitator motor Temperature (F) Rear #3
Tub agitator motor Temperature (F) Rear #4
PUMP TEST RESULTS DS
Record average values for listed parameters during each run in the spaces provided below.
Full Flow Flow Condition
Bearing/Seal Temp (°F)
Discharge Rate ( GPM )
Discharge Pressure (psi)
Charge pressure (psi)
System pressure (psi)
PUMP TEST RESULTS PS
Record average values for listed parameters during each run in the spaces provided below.
Full Flow Flow Condition
Bearing/Seal Temp (°F)
Discharge Rate ( GPM )
Discharge Pressure (psi)
Charge pressure (psi)
System pressure (psi)
Engine Speed (rpm)
18 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
19 of 20
Halliburton Energy Services Specification D00120521 Revision D
Tested Unit: BMR100,Batch Mixer Trailer, Twin
Duncan, OK Centrifugal Pump, CAT C7
Date: 07/06/2007
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
11 Final Inspection
Final Inspection (D00113918) completed.
ACCEPTANCE CERTIFICATION
I certify by signature below:
The above testing has been completed and this unit performed in accordance with established criteria described
herein and/or known to me with exceptions as noted below.
I have reviewed recent Service Bulletins for this unit type and have corrected all known issues on this unit.
I have identified all components or systems of this unit that were not accepted, tested or corrected or that did not
meet the performance requirements of this procedure or otherwise known to me as exceptions below.
Exceptions: Reason Accepted:
20 of 20
Halliburton Energy Services Specification D00113295 Revision A
Tested Unit: Unit Road Testing
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
1. TEST INFORMATION
a. Instructions for use
i. This test procedure is intended to identify the minimum requirements for the Road
Testing of a unit. This test assumes the work will be performed by qualified technicians
familiar with the operation of the unit and the tools and equipment used in performing
the test. The test technician should read through the entire procedure prior to starting.
If there are any questions concerning the test, please contact the Duncan Technology
Center.
ii. At any time during the performance of this test, should the operator of the pulling
vehicle feel or see an item of safety concern, this test is to be immediately terminated
and the vehicle pulled off the road and proper safety precautions taken.
iii. This testing is to be completed prior to the performance testing being completed. The
driver should be aware of and obey all laws, rules, and regulations applicable to this
testing. The purpose of this testing is to:
1. Verify the proper installation and operation of lighting.
2. Verify that the trailer is road worthy.
3. Confirm that all components are properly secured so that normal loads incurred while roading the
unit will not prevent the unit from catching a job.
iv. This work is to be documented on test data sheet(s) at the end of this procedure by the
test technician(s) performing the work. Items in this test procedure that do not apply to
the unit being tested shall be indicated as being not applicable, “n/a”, in appropriate
locations on the test data sheet(s). This procedure is available in electronic format
through the Halliburton network and has been designed to enable manual or electronic
data entry.
b. Use the latest revision of the test
i. Retrieve latest version of the test procedure from matrix by the following procedure:
1. Open matrix checker and find the spec number of this document.
2. Open the latest revision to the specification that is in production release and print the specification.
3. Use the specification (test procedure) as a checklist to complete this testing.
2. UNIT INFORMATION
a. Operating and service standards for this unit.
MANUAL DESCRIPTION PART NO.
Lubrication Standard 278.90538
3. LUBRICATION PROCEDURE
a. Trailer Axles
i. Fill to site glass level if low.
ii. Lubricant per Lubrication Standard (Part No. 100053807).
b. Install grease zerks and fill with lithium grease, Part No. 100026247
i. Slack adjusters.
ii. Walkway support bearings.
iii. Manifold supports.
iv. Trailer jacks.
v. Any other zerks called out in the appropriate drawings.
4. Test setup
a. Connect trailer to tractor.
b. Remove any test equipment, tools, and etc.
1 of 8
Halliburton Energy Services Specification D00113295 Revision A
Tested Unit: Unit Road Testing
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
c. Verify that the wheel bearings lubricant level is at the oil level mark on the hubcap
sight glass.
d. Verify that the trailer is equipped with a hub odometer.
e. Verify brake chamber rod travel less than 2 inches.
f. Verify that air is exhausted from air ride suspension air spring when spring brakes
are applied, if applicable.
g. Confirm dot brake hose has been installed.
h. Confirm anti-lock brake system (ABS) installed.
i. Check tire pressure. For standard tires, inflate to pressure listed on the fmvss tag.
For trailers equipped with 24R21 desert tires, inflate to 60 psi for highway operation
(40 mph maximum highway speed).
j. Verify ride height/leveling valve adjustment operation.
k. Re-torque lug nuts to appropriate torque for type of wheel.
l. Test landing gear operation.
m. Verify underide protection compliance.
n. Inspect trailer for loose items and etc and secure/remove as appropriate.
o. Assure that the fire extinguisher, first aid kit, and flare kit reported on the vehicle are
as required on the assembly drawing and stowed in an accessible location.
5. ADJUST BRAKES.
a. Manual type slack adjusters.
i. Wheel off the ground method (preferred method). Position wrench or socket over the
adjusting screw and disengage the locking sleeve by depressing the lock sleeve. Turn
the adjusting screw with the locking sleeve depressed until the brakes begin to drag.
Adjustment should then be backed off until the wheel turns freely. This will result in an
actuator stroke as short as possible without the brakes dragging. When the adjustment
is completed, the adjusting screw nut should be positioned so the locking sleeve engages
the adjusting screw nut, thus locking the adjusting screw in place. Do not attempt to
turn the adjusting screw without fully depressing the lock sleeve.
ii. Wheel on the ground method. Turn adjusting screw by using above procedure for
depressing the lock sleeve until the brake lining firmly contacts the brake drum. The
adjusting screw should then be backed off 3/4 of a turn.
b. Automatic type.
i. Apply and release the vehicle brake several times. Observe that the automatic slack
adjuster and its external components move freely and without binding.
ii. Observe the brake chamber stroke or the distance the brake chamber rod moves when a
service brake application is made. With the brake chamber push rod fully retracted, the
brakes must be completely released. In the applied position, the brake chamber stroke
should not exceed 2 inches.
iii. If automatic adjustor needs readjusting, it can be done manually.
6. CHECK FOR POSSIBLE SUSPENSION AND BRAKE CHAMBER
INTERFERENCE AND SUFFICIENT TIRE CLEARANCE.
a. Spring suspension.
i. Perform a visual inspection for loose bolts, nuts, and u-bolts. Also, check all welded
areas.
2 of 8
Halliburton Energy Services Specification D00113295 Revision A
Tested Unit: Unit Road Testing
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
ii. On hutch suspensions, make sure all the alignment plates are welded located at the
spring seat/axle area.
b. Air suspension.
i. Check for interference between the air bag and the brake chamber clamp. Perform a
visual inspection of the shock bolts, air leveling valve, air connection and all welds for
loose or incorrect installation. Check the air system for leaks and the air suspension is
set at their proper ride height. Make sure that all of the adjustment collars on the frame
brackets are welded (four per suspension).
7. AIR SYSTEM
a. With trailer brake system air supply connected, check for air system leaks.
b. Check that air brake hose does not rub cross members or other components.
c. Brake systems checks
i. Place scotch blocks
1. Air compressor governor test with trailer connected
* Governor cut-in (approx. 98 psi)
* Release parking brake
* Governor cutout (approx. 118 psi)
2. Perform a brake leakage test with governor at its cut out setting and engine not running.
*Brakes off Allowable loss
*Brakes on
11.ACCEPTANCE CERTIFICATION
a. Review Recent Service Bulletins for this unit type and verify that all known issues
have been corrected on this unit.
b. Identify any components or systems of this unit that were not accepted, tested, or
corrected or that did not meet the performance requirements identified in this
procedure or otherwise known as exceptions in the Acceptance Certification Section.
c. Fill in Signatory fields of the Acceptance Certification.
5 of 8
Halliburton Energy Services Specification D00113295 Revision A
Tested Unit: Unit Road Testing
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
3 LUBRICATION
QTY Component Lubricant Estimated QTY
Trailer Axle Lubricant SAE 90 Gear Lube, 100016248 Fill
Walkway Supports Lithium Grease, 100026247 Fill
Manifold Supports Lithium Grease, 100026247 Fill
Pump Mounts Lithium Grease, 100026247 Fill
Trailer Jack Lithium Grease, 100026247 Fill
7 AIR SYSTEM
No air leaks present
All lines clear trailer members
Brakes hold vehicle in place
11 ACCEPTANCE
No wheel seal leaks present.
Off road testing completed.
7 of 8
Halliburton Energy Services Specification D00113295 Revision A
Tested Unit: Unit Road Testing
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
ACCEPTANCE CERTIFICATION
I certify by signature below:
1. The above testing has been completed and this unit performed in accordance with
established criteria described herein and/or known to me with exceptions as noted
below.
2. I have reviewed recent Service Bulletins for this unit type and have corrected all
known issues on this unit.
3. I have identified all components or systems of this unit that were not accepted,
tested, or corrected or that did not meet the performance requirements of this
procedure or otherwise known to me as exceptions below.
Exceptions: Reason Accepted:
8 of 8
Halliburton Energy Services Specification D00113918 Revision A
Tested Unit: Final Inspection
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
1. TEST INFORMATION
a. Instructions for use
i. This test procedure is intended to identify the minimum requirements for a Unit’s Final
Inspection. This test assumes the work will be performed by qualified technicians
familiar with the operation of the unit and the tools and equipment used in performing
the test. The test technician should read through the entire procedure prior to starting.
If there are any questions concerning the test, please contact the Duncan Technology
Center.
ii. This testing shall be completed as the final step of all testing/painting processes. This
testing is to confirm that the unit has not been damaged during painting, all tape and
adverse overspray has been removed, any parts removed for painting or repairs were
properly reattached, and to install all required certifications and manufacturers labeling
for release to the field.
iii. This work is to be documented on test data sheet(s) at the end of this procedure by the
test technician(s) performing the work. As this is a general testing procedure, items in
this test procedure that do not apply to the unit being tested shall be indicated as being
not applicable, “n/a”, in appropriate locations on the test data sheet(s). This procedure
is available in electronic format through the Halliburton network and has been designed
to enable manual or electronic data entry.
b. Use the latest revision of the test
i. Retrieve latest version of the test procedure from matrix by the following procedure:
1. Open matrix checker and find the spec number of this document.
2. Open the latest revision to the specification that is in production release and print the specification.
3. Use the specification (test procedure) as a checklist to complete this testing.
2. UNIT INFORMATION
a. Operating and service standards for this unit.
MANUAL DESCRIPTION PART NO.
Lubrication Standard 278.90538
3. INSPECT VEHICLE
a. General
i. Hoses protected from sharp edges.
ii. Hose end tie straps cut.
iii. Check overall appearance of paint.
iv. Confirm that all masking tape, paint shielding and etc. have been removed.
v. Confirm that all items removed for final painting were properly installed and operate
correctly.
vi. Confirm that all loose equipment has been installed and secured (see specific assembly)
i.e. walkways, ladders, high pressure iron, manifold caps, rain caps, etc.
vii. Confirm that all guards, shielding, and flaps are properly installed.
viii. Replace hydraulic filter elements.
ix. Confirm that all fluid levels are acceptable.
x. Confirm that unit is fueled.
xi. Confirm that there are no visible leaks.
xii. Confirm that manifolds and tanks are free of water.
xiii. Confirm that all wheel lugs are properly torqued.
1 of 4
Halliburton Energy Services Specification D00113918 Revision A
Tested Unit: Final Inspection
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
b. Functional Test
i. Power up controller, start engine(s) and run through all gears (manifold does not need to
be connected for this testing).
ii. Verify that all components and controls work properly.
iii. Run Engine at high idle with transmission in neutral for approximately ten minutes to
cool down unit.
iv. Perform emergency shutdown test of each engine.
v. Reset ECM and ASO valves.
vi. Secure control panel lid.
4. INSPECT LIGHTING
a. Check chassis lighting. Confirm all required lamps are present, correct color and
operational.
b. Complete light inspection section of test data sheet.
i. STOP, TAIL, AND TURN LAMPS - RED
ii. LICENSE PLATE LAMP - WHITE
iii. REAR SIDE MARKER LAMPS - RED
iv. REAR CLEARANCE LAMPS - RED
v. INTERMEDIATE SIDE MARKERS - AMBER
vi. REAR IDENTIFICATION LAMP CLUSTER - RED
vii. REAR REFLEX REFLECTORS - RED
viii. REAR SIDE REFLEX REFLECTORS - RED
ix. INTERMEDIATE SIDE RELEX REFLECTORS - AMBER
5. DECAL AND MARKINGS
a. Install bumper marking conspicuity (reflective tape) treatment
b. Install side marking conspicuity (reflective tape) treatment
c. Apply decals, labels and unit number
d. Attach vehicle certification nameplate. Nameplate must be visible without removing
equipment.
e. Attach I.F.T.A. decal.
f. Attach proposition 65 warning label.
g. STAMP THE REQUIRED DATA ON THE CERTIFICATION NAMEPLATE (See
the incomplete vehicle nameplate or the incomplete vehicle documents.)
6. ACCEPTANCE CERTIFICATION
a. Review Recent Service Bulletins for this unit type and verify that all known issues
have been corrected on this unit.
b. Identify any components or systems of this unit that were not accepted, tested or
corrected or that did not meet the performance requirements identified in this
procedure or otherwise known as exceptions in the Acceptance Certification Section.
c. If required, perform Pickling Procedure of Note 278.95008.
d. Fill in signatory fields of the Acceptance Certification.
2 of 4
Halliburton Energy Services Specification D00113918 Revision A
Tested Unit: Final Inspection
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
3 INSPECT VEHICLE
Hoses protected.
Hose tie straps cut.
Paint is acceptable.
All masking tape, paint shielding and etc. Have been removed.
All items removed for final painting were properly re-installed and operate correctly.
All loose equipment has been installed and secured.
All guards and shielding are properly installed.
All fluid levels are acceptable.
There are no visible leaks.
Manifolds and tanks are free of water.
Wheel lugs are properly torqued.
Engines started and run through all gears.
All controls and components operate properly.
Emergency kill operates correctly.
Control panel secured.
4 INSPECT LIGHTING
Stop, tail, and turn lamps Red
License plate lamp White
Rear side marker lamps Red
Rear clearance lamps Red
Intermediate side markers Amber
Front side markers Amber
Front clearance lamps Amber
Rear identification lamp cluster Red
Rear reflex reflectors Red
Rear side reflex reflectors Red
Intermediate side reflex reflectors Amber
Front side reflex reflectors Amber
Abs indicator lamp Amber
3 of 4
Halliburton Energy Services Specification D00113918 Revision A
Tested Unit: Final Inspection
Duncan, OK Date: 7/29/03
The information contained hereon shall be considered the sole property of Halliburton Energy Services (HES) and the recipient thereof agrees not to
disclose said information to parties outside the recipient’s organization and not to use or duplicate said information for any purpose except as specified
by HES with the written permission of HES.
ACCEPTANCE CERTIFICATION
I certify by signature below:
1. The above testing has been completed and this unit performed in accordance with
established criteria described herein and/or known to me with exceptions as noted
below.
2. I have reviewed recent Service Bulletins for this unit type and have corrected all
known issues on this unit.
3. I have identified all components or systems of this unit that were not accepted,
tested or corrected or that did not meet the performance requirements of this
procedure or otherwise known to me as exceptions below.
Exceptions: Reason Accepted:
4 of 4
Appendix
A
Unit Wiring Schematic
This section provides a wiring schematic for the BMR-100 batch-mixer trailer. Refer to
drawing number D00120079 for a larger version of this wiring diagram.
DENSOMETER MICRO-MOTION
DL200 (S+) (S-)
WHT
BLK
- +
P 20 19 18 17 16 15 14
MICRO-MOTION
TRANSMITTER
GRN/YEL
WHT
BLK
0 1 2 3 4 5 6 7 8 9
SINGLE POINT S 27 26 25 24 23 22 21
GROUND
ORANGE
BROWN
YELLOW
GREEN
BLACK
WHITE
GRAY
VIOLET
BLUE
RED
9 WHITE
8 GRAY
BLK 4 GA. 7 VIOLET
6 BLUE
5 GREEN
4
3
YELLOW
ORANGE
(TB4) ENG. WIRING
2 RED
1 BROWN TYP. WIRING
+
29A 29A 1 DIODES AND WIRE PER DIAGRAM ON THE
12 VOLTS
12 VOLTS
7 SIDE OF THE DIODE CASE.
9
TYPICAL THESE DIODES ONLY.
BLK 6 GA.
10 29B 29B
RED 6 GA. 1
8 70.05713 2-16 GA. POWER
2
INLET AIR
HEATER
8 9 10 11 12 13 14 M
TB4-25 YEL
DB1-11 YEL
DB1-M BLK
5 BLU
WHT TB4-52 BLK
1 +BAT. (UNSWITCHED) CB6 SW11-2 WHT ENGINE 4
BLK RED 10 GA. TACH
31 +BAT. (UNSWITCHED) CB7 OFF
RED 15 AMP.
32 +BAT. (UNSWITCHED) START 1 REF. 70.74988
BLK 35 AMP TB4-29 GRN
17 J1939 DATA LINK + - +
2 DPDT MOM.
18 J1939 DATA LINK -
WHT TB4 1 4 5 6 "B" "A"
3
HYD. OIL
TEMP
16 J1939 SHIELD HYD. OIL
4 SW8 WARNING LIGHT
GND
GRN/BLK BLK SHLD 1 RUN 5
22 ETHER START VALVE RELAY BLK
ENG TACH 2 BLK- TACH (-) 2 DB1-10 YEL
WHT STOP
WHT TB4-19 BRN NO C NC
WHT- TACH SIG. 3 6 BLU
ECM
RED
ORG/BLK TACH SENDER SHLD 4 TB4-20 BRN
27 GROUND LEVEL SHUTDOWN SW WHT +BAT (UNSWITCHED) RED TB4-51 BLK
5
BLK +BAT (UNSWITCHED) RED
6
RED +BAT (UNSWITCHED) RED
7 P1 J1
BLU +BAT (SWITCHED) CB8
8
CAT 3126B CONNECTOR 26 +BAT. (SWITCHED)
BLU
DENSOMETER 11
WHT (+) 9
15 AMP. RED
BLK
A
B
A
B
7 BRACKET BLK GND 10 TACH PWR THROTTLE
GND STUD +12V IGN. BRN WHT C C
GRN 11 5 102.00067
38 STARTING AID SW
ALTERNATOR 12 P1-A RED RED 1 MATING PARTS REQ'D
8 HOUR METER POWER
REF. 278.51300
ORG 13 "1" RED BLK 6 70.84879 RECEPTACLE
40 E-STOP VERIFY SW
2 14 "6" BLK YEL 2
VIEW 70.84883 CONTACT PINS
YEL BLK
J1939 LINK + 15 "2" YEL GRN 3
REG. RED WHT
RED J1939 LINK - 16 "3" GRN GRY 4
RED 10 CONDUCTOR 12 GA. 3
WHT 1 SHLD 17 "4" GRY TB4-28 BLK
3 1 RED/BLK 120ê 2
THROTTLE 18 P1-C WHT TB4-24 BLK
WHT
BLK 24 DIAGNOSTIC LAMP SW11-6 BRN
AUX. BLK 3 ORG/BLK 19
14 GA. 25 WARNING LAMP ENGINE STOP SW8-6 BRN N.O. PROTECTED
BAT. 20 SW8-5 BRN
SW9 TOGGLE SWITCH
(FOR 75% TEST
21 CIRCUIT)
GRN
STARTING AID SW 22
4 2 BLK GRN/BLK
STARTING RELAY VALVE 23
AIR INLET SOLENOID BLK ORG
PRESS E-STOP VERIFY SW 24 SW9-2 BLK DIODE
SWITCH 4N3889 WHT
DIAGNOSTIC LAMP 25 CHK ENG. TRANSZORB
RED 14 GA. C RED BLK
WARNING LAMP 26 STOP ENG. 70.74764 ENGINE BLOCK
HEATER
RED 14 GA. 27
BLK 14 GA. 28
4
9-PIN DEUTCH WHT 29A GRN AUX. START HEATER SWT.
CONNECTOR 3 START
BLK 29B 85 86
REF 70.84874 SOCKET SEE DIODE TERMINAL DETAIL 31 CR1-86 BLK 14 GA.
SW12
WHT 10 GA. 70.84875 RECEP. REF 70.18167 SW7-6 GRN TB4-31 BLK OFF ON
BRN 14 GA. 32 CR1-30 RED 14 GA.
+ G G BLK 14 GA.
BLK 10 GA. GRN 14 GA. 33 SW12-1 BLU 14 GA. 87A
3 1
WHT H H BLK 14 GA.
BLU 14 GA. 34 NOT USED
CR1
START 2
BLK 30
- S
SOLENOID
WEBASTO THERMO 90 E E RED 14 GA.
VIO 14 GA.
ORG 14 GA.
35
36
NOT USED
NOT USED TB4-32 RED
RED 10 GA. 87
RED 10 GA. F F RED 14 GA.
YEL 14 GA. 37 NOT USED
B B GRN 14 GA.
MODEL THERMO 90 D (DIESEL) BLK 10 GA. 38 HEATER LAMP BLK
WHT
A A BRN 14 GA.
39 BLK 10 GA.
C C BLU 14 GA. TB4-33 BLU
COOLANT HEATER RED 10 GA. 40 RED 10 GA.
J J VIO 16 GA.
41 TB4-38 BLK 14 GA.
RED 6 GA. REF. 70.97407 (TWISTED PAIR NOT USED) 42
43
WHT 44 SW11-3 WHT
3 E-KILL
BLK 45 P1-B BLK
LIGHT SWITCH 46 SW11-5 BLK
REF 70.77658
47
48
STARTER FRONT BATCH TANK REAR FRONT
CONTROL
STAND
BLU CONTROL STAND LAMPS 49
PLATFORM 50
FRAME (REF D00000951) BATCH TANK BATCH TANK SW1
1 SW4
GROUND 3 SW3 SW2 51 HYD OIL TEMP GND BLK
GRN 2 GRN
OFF ON OFF ON OFF ON OFF ON 52 SWT10-C LAMP TEST BLK EMERG KILL
3
YEL 3 YEL BLU SW11 0N
3 1 3 1 3 1 3 1 53 CASE DRAIN HYD OIL TEMP BLK
GRN 4
3
54 CASE DRAIN HYD OIL TEMP BLK
YEL 5 2 2 2 2 CB1 2 TB4-44 WHT
35 AMP WHT
GRN
YEL
6
1
HEATER
J-BOX (REF 278.96327) SW6 6
TB4-19 BRN CABLE LEGEND
(REF 70.11178)
HIGH TB5 TB4-46 BLK
5
RED CB9 4
+12V 15 AMP 1 REF 70.41253 10-#12 7 REF 70.12341 1-#2/0
OFF OFF
3 RED RED 10 GA. TB3-40 RED
RED 10 GA.
HEATER BLK 2 REF 70.71011 2-#16 8 REF 70.12201 1-#6 RED
LOW
FAN
GRN
YEL
(70.51968)
3 REF 70.12335 2-#14 9 REF 70.04625 1-#10 RED
CR3
YEL
3 6 CR2
J-BOX
RED 10 GA.
GRN
(REF 70.11178)
YEL
86 85
86 85
86 85
RED 10 GA.
3
RED 10 GA.
30
GRN
YEL
30
30
87
87
87
RED
A
REF 70.92785 3-#8 GA. 70.92785 3-#8 GA.
RED B
BLK
+
+
12 VOLTS
12 VOLTS
+12V BATTERY
ON TRACTOR
B
Hydraulic Piping
Appendix B provides parts lists and schematics for the hydraulic piping in the BMR-100 batch-
mixer trailer.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (1 of 6)
January 2008
Page B-9 of 14
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (2 of 6)
BMR-100 Batch-Mixer Trailer
App. B—Hydraulic Piping
Page B-10 of 14
January 2008
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (3 of 6)
January 2008
Page B-11 of 14
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (4 of 6)
BMR-100 Batch-Mixer Trailer
App. B—Hydraulic Piping
Page B-12 of 14
January 2008
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (5 of 6)
January 2008
Page B-13 of 14
D00100866 Rev. C—Installation, piping, hydraulic, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (6 of 6)
BMR-100 Batch-Mixer Trailer
C
Air Piping
Appendix C provides schematics and parts lists for the air piping in the BMR-100 batch-mixer
trailer.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
Find
Part No. Ref. No. Qty. Description
No.
D00100864 Rev. C—Installation, piping, air, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (1 of 5)
January 2008
Page C-9 of 12
D00100864 Rev. C—Installation, piping, air, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (2 of 5)
BMR-100 Batch-Mixer Trailer
App. C—Air Piping
Page C-10 of 12
January 2008
D00100864 Rev. C—Installation, piping, air, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (3 of 5)
January 2008
Page C-11 of 12
D00100864 Rev. C—Installation, piping, air, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (4 of 5)
BMR-100 Batch-Mixer Trailer
App. C—Air Piping
Page C-12 of 12
January 2008
D00100864 Rev. C—Installation, piping, air, complete, twin centrifugal pumps, batch mixer trailer, 2003 model (5 of 5)
Appendix
D
Component Repair and
Service Manuals
Appendix D includes the following repair and service manuals for individual components: