GARDENS PARK MASTER PLANNING

CCM Meeting (Meeting No. 21)


Date: 30 April 2024
Time: 09:30am – 10:30am
Venue: Gamuda Gardens WFV PCMD Office

Present
No Name Designation Initial
1 Ms. Wong Chung Fong GL, PCMD
(Karen)
2 Mr. Chow Zhen Rong GL, PCMD
3 Mr. Haritz Daniel Shaharul GL, PCMD
4 Ms. Lim Jia Pey GL, PCMD
5 Mr. Sam Kit Seng GL, BSDB
6 Mr. Jasril Nazmi Rahman GL, PMU
7 Mr. Firdaus Ismail GL, PMU
8 Mr. Ernest Lee Eng Chi GL
9 Ms. Chai Yee Kuan GL
10 Mr. Guan Chun Wah GE
11 Mr. Faris Aiman Bin GE
Mazmeelairam
12 Ms. Ng Xue Yinn GE
13 Mr. Ong Tee Juan GE
14 Mr. Ng Chee Siang Sky
15 Ms. Siaw Chu Xuan Sky
16 Ms. Lim Sue Fern SSP
17 Mr. Ghafar Walrus
18 Mr. Chia Khoon Kean DRYGTJP S/B
19 Mr. Jason Chan DRYGTJP S/B
20 Mr. Jason Cheong TBSB
21 Ms. Low Mei Wen Sky
22 Mr. Zhourfan TB
23 Mr. Mohamed Amerul DRYGTJP S/B
24 Mr. Po Dineshkumar SSP
25 Mr. Hafiy Fauzan GIBS
26 Ms. Sufia Kadir GPARKS
27 Ms. Siti Nurhaslina SSP
28 Mr. Tan Weng Kang GE BIM
29 Ms. Lim Wan Ting GE BIM
30 Ir. Foo Kam Fai SSP

Page 1 of 3
Item Matters Action By Target
Arise Date
1 Authority Matter

1. EW: SSP resubmitted phase 1 EW for endorsement on SSP


05/4/24. On 17/04/2024, MPS approved SSP EW
submission. Pending Borang B approval in OSC System.
2. SSP have arranged a meeting with JKR En. Rafiq on SSP
16/04/2024 to present RSA Stage 3. On 23/04/2024 SSP
submitted RSA Stage 3 compliance report to JKR Gombak.
3. SSP did resubmission to IWK for upgrading of STP (Pindaan SSP
to PDC1) on 2/4/2024. Pending GL to process the
submission fee.
4. SSP have obtained approval from Air Selangor SSP

2 Developer Matter
-

3 Planner Matter

4 Architecture Matter

5 Civil & Structural Matter

1. SSP have emailed pedestrian crossing drawing and BQ to GE SSP


on 16/04/2024. However, GE has commented on several
items, SSP will revise the pedestrian crossing drawing and SSP
BQ accordingly.
1. RC Wall detail will be provided in the revised earthwork SSP
drawing.
2. It was highlighted by contractor that the slope toe clashes with SSP
pond area. SSP wil have a discussion with landscape
consultant and will change the pond alignment to avoid
clashing. GE can proceed with the slope construction.
3. SSP have provided tapping pressure to DRYGTEC, together SSP
with master infra drawing.

4. It was highlighted by contractor that the IWK sewerage pipe


SSP
clashes as it goes through bridge. SSP to look into it

Page 2 of 3
Item Matters Action By Target
Arise Date

6 Mechanical & Electrical Matter

1. TBSB are yet to share the latest master M&E layout plan for TBSB
SSP to superimpose on drawing. TBSB promised to the share
by 19th April 2024.
INFO
2. TBSB stated that the street-lighting will be along the road
median.
7
3. SSP will share put spine road cross-section with landscape for SSP
TBSB to review.

Landscape Architecture Matter

-
8
Other Matters

1. GE are yet to provide the as-built rock boundary for Phase 1 GE


area to SSP.
2. GL have given the EW Stage 1 LOA to SSP, pending contract
GL
binding.

Adjournment of Meeting

Meeting was adjourned and the next meeting is


scheduled as below:-

Date : 30/4/2024

Time : 9.30am - 11.30am