Professional Documents
Culture Documents
BR 376 Radon Protection To New Dwellings in Scotland.
BR 376 Radon Protection To New Dwellings in Scotland.
BR 376 Radon Protection To New Dwellings in Scotland.
fraser.walsh@scotland.gsi.gov.uk
On
09/04/2014
Radon:
guidance on
protective measures
for new dwellings
in Scotland
BRE Scottish Laboratory
BR376
ISBN 1 86081 334 8
Published by
Construction Research
Communications Ltd
by permission of
Building Research
Establishment Ltd
BRE material is also published quarterly on CD CRC supplies a wide range of building and
construction related information products from
Each CD contains: BRE and other highly respected organisations.
● BRE reports published in the current year
(accumulating throughout the year) Contact:
● A special feature: by post: CRC Ltd
usually a themed compilation of BRE publications 151 Rosebery Avenue
(for example on foundations or timber decay) London EC1R 4GB
The CD collection gives you the opportunity to build a by fax: 0171 505 6606
comprehensive library of BRE material at a fraction of by phone: 0171 505 6622
the cost of printed copies. by email: crc@construct.emap.co.uk
As a subscriber you also benefit from a 20% discount
on other BRE titles.
iii
Contents
Introduction 1
About the maps showing designated radon-affected areas 2
Acknowledgements 21
Further information 21
Introduction
2 Introduction
This report provides guidance for preventative measures in new dwellings
and extensions to existing buildings. Practical measures are outlined which,
when applied to new dwellings, will significantly reduce the ingress of radon.
Guidance is provided for both solid and suspended floors. The gas must be
dealt with before it becomes a risk to health and therefore the measures are
generally applied at or below the lowest floor level.
The initial research on floors was undertaken in some of the worst affected
areas in the UK. The floors of the properties on which monitoring could be
carried out, were mainly concrete. The recommendations for concrete floors
in this report have been based on that work (BRE Report Radon: guidance on
protective measures for new dwellings ).
Methods for dealing with timber suspended floors are the subject of a
current research programme. The results of that work were not available for
inclusion within this report. The details for timber floors are therefore
provided as best practice advice in terms of current knowledge. These
recommendations may be modified as more information becomes available.
Protection from radon at work is specified in the Ionising Radiations
Regulations 1985[1], legislation made under the Health and Safety at Work
Act[2] administered by the Health and Safety Executive. The technical advice
contained in the present report may, however, be of use to designers and
builders of new structures whose form of construction and compartmentation
is similar to housing and where the heating and ventilation regime is similar to
that used in housing. This is likely to include small office buildings and some
primary schools. Further information is contained in the HSE/BRE guide
Radon in the workplace.
Overview of
protective measures
Stage 3 protection
If tests show that further measures are required, the approach will be broadly
the same irrespective of location and initially assessed risk. Ventilation must
be induced below the floor or radon-proof membrane. Where a sump has not
been provided, it will need to be installed. The ventilation will reduce radon
seepage into the dwelling by dilution and either:
● depressurisation of the void or hardcore by sucking the gas out of the
subsoil and expelling it harmlessly to the atmosphere; or
● pressurisation, overcoming the natural tendency for radon to rise from the
subsoil and into the building.
A mechanical fan connected to the sump can drive either of these options.
Where a sump has been provided in an appropriate location, it may be driven
by heat convection and operate as a passive stack system.
Details of these methods can be found in BRE Report Radon sump systems: a
BRE guide to radon remedial measures in existing dwellings.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Stage 1 protection 7
Radon membrane
Floor topping
In-situ concrete dpc
floor slab
Cavity tray
Radon membrane
Floor topping
In-situ concrete dpc
floor slab
Cavity tray
Radon membrane
Floor topping
Solum void
Suspended
concrete floor
Air vent
Floor Solum
boards void
Air vent
In areas where there are higher levels of radon, minor imperfections in the
membrane may leak sufficient radon gas to cause the Action Level to be
exceeded. In these high radon areas this risk is addressed by the provision of
additional protection. When appropriate, this will be in the form of increasing
the ventilation across the solum. Alternatively it may be a radon sump
constructed below the barrier membrane, but at this stage non-operating. The
sump can be activated later if required.
Floor In-situ
Subfloor topping concrete
depressurisation floor slab
pipe dpc
Cavity
tray
Stage 2 protection 9
Radon Alternative position for subfloor depressurisation pipe.
membrane Pipe must be sealed where it penetrates the membrane
Cavity tray
Floor In-situ
topping concrete
Subfloor floor slab dpc
depressurisation
pipe
Air vent
The above examples are not the only options available; alternative solutions
may be adopted, such as raft foundations, fully tanked basement (eg fully
waterproofed using asphalt).
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Stage 3 protection
Where testing of a new dwelling incorporating Stages 1 and 2 protection
shows that the radon levels are above 200 Bq/m3, the property will require
additional, Stage 3, measures.
Where the property already has a sump and underground pipework in
place, a vertical discharge pipe can be connected to the pipework and the
system made live by fitting a fan to the discharge pipe. Where the sump and
discharge pipe are centrally located in the dwelling, the ventilation can also be
driven by passive stack ventilation (PSV). The discharge pipe will then heat up
with the rest of the dwelling and this, coupled with the effect of wind blowing
over the terminal, will drive the stack system.
In the case of suspended concrete floors, where Stage 2 is simply the
provision of additional ventilation below floor level, there is no sump system
to be activated. Should it be necessary, the rate of ventilation and radon
dispersion can be supplemented by the installation of an electrically powered
fan. This fan may replace one of the sub-floor ventilation grilles and should be
provided on the leeward side of the dwelling to extract air from the solum
void.
If the property does not have a sump, an edge sump (or sumps) should be
constructed by excavating a small cavity below the membrane and connecting
this to a vertical discharge pipe. This procedure, since it is post-construction,
is the same as that used for older properties where a radon problem has been
identified. BRE Report Radon sump systems: a BRE guide to radon remedial
measures in existing dwellings also provides details on this.
For larger dwellings which require Stage 1 measures only, the comparative
costs of fitting one central sump during construction or a number of edge-
located sumps after construction should be considered.
Activating the sump ventilation system will further reduce the radon on the
underside of the membrane. Although this is not directly an issue at the time
of construction, an awareness of the purpose and use of the sump is helpful in
making decisions regarding location and access.
Even with Stage 3 measures in place and active, it cannot be guaranteed
that the radon levels will be reduced to less than 200 Bq/m3. The radon level
can only be established by further testing. If it is found to exceed 200 Bq/m3,
fine-tuning the protection measures will be necessary and will differ for each
dwelling.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
The solum void shall be adequately ventilated A radon-proof membrane shall be (a) The flooring shall preferably be boarded
and air shall not be drawn from the void into incorporated in the floor construction. with tongued-and-grooved or rebated
the dwelling for any purpose. joints.The floor perimeter and all service
All joints in the floor and all service penetrations shall be sealed.
penetrations shall be sealed. (b) The solum void shall be adequately
A radon-proof membrane shall be ventilated and air shall not be drawn from
incorporated in the floor construction. the void into the dwelling for any purpose.
(c) A radon-proof membrane shall be
incorporated in the oversite concrete.
The ventilation of the solum void shall be as A radon-proof membrane shall be (a) The flooring shall preferably be boarded
required by the Technical Standards plus incorporated in the floor construction. with tongued-and-grooved or rebated
another 50%. A sump and stub-duct shall be provided in joints.
Air shall not be drawn from the void into the hardcore below the concrete. The floor perimeter and all service
dwelling for any purpose. penetrations shall be sealed.
All joints in the floor and all service penetrations (b) The solum void shall be adequately
shall be sealed. ventilated and air shall not be drawn from
A radon-proof membrane shall be the void into the dwelling for any purpose.
incorporated in the floor construction. (c) A radon-proof membrane shall be
incorporated in the oversite concrete, and
a sump and stub-duct shall be provided in
hardcore below that concrete.
Connect a fan to one of the subfloor airbricks. Connect the sump and stub-duct to a fan or passive stack for ventilation. Where a sump has not
been provided, this may be excavated under the floor membrane from outside the building.
*These areas of risk can be identified from the maps included in this report.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
12
Detailed information on
protective measures
Once the method by which protection is to be provided has been decided, the
following detailed guidance will need to be considered.
Radon-proof membranes
Membranes, materials and workmanship
With careful design, selection of material and good workmanship, a single
membrane will satisfy the requirements of both damp-proofing and radon
protection.
Generally a membrane of 300 micrometre (1200 gauge) polyethylene sheet
will be adequate as a radon-proof membrane. It is acknowledged that some
diffusion will occur through the sheet. However, as most radon entry is
through cracks or gaps, this diffusion, which is very small, can be ignored.
Where the detailing or forms of construction indicate a greater than normal
risk of puncturing the membrane, reinforced polyethylene sheet should be
considered.
The radon-proof membrane can be constructed with other materials that
match the airtightness and waterproofing properties offered by
300 micrometre (1200 gauge) polyethylene. Alternative materials that can
prove suitable include modern flexible sheet roofing materials, prefabricated
welded barriers, self-adhesive bituminous-coated sheet products and asphalt.
Prefabricated welded barriers are likely to offer a greater confidence in
achieving radon-proof joints than the use of polyethylene sheet, but are more
expensive. Using polyethylene sheet over the bulk area of the floor, with a
more robust material as a damp-proof course or cavity tray for edge details,
has been shown to be effective.
It is important that the radon-proof membrane is not damaged during
construction. This might be achieved by installing the membrane at a later
stage of construction, for example over the floor immediately before laying of
the screed, as shown in Figure 11. If laid beneath the slab, the membrane may
need to be protected against damage when fixing reinforcement and laying
the concrete.
It is essential to check that the membrane is not damaged in any way before
it is covered with concrete or other materials. Any damage should be repaired
before proceeding with later works. Damage to the membrane can be
repaired by overlaying it with a piece of membrane material held securely in
place, preferably by sealant, and with a minimum overlap of 150 mm.
Protection to cavities
One of the routes by which radon might enter a building is by way of the wall
cavities (Figure 12), and therefore the radon-proof membrane should extend
across the cavity to prevent radon entry. Where the membrane crosses the
cavity, it will need to be constructed in a manner that prevents water being
transferred from the outer to the inner leaf. The membrane should be
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Radon-proof membranes 13
1 2 3
External wall
Cavity tray extending Suspended and building Floor topping and
150-200 mm across concrete floor shell completed insulation installed
floor beyond the making the over membrane
inner face of wall structure weathertight taped to cavity tray.
Airbrick All work carried out
Weephole within weathertight
Cavity filled structure
with concrete
to provide
support to
cavity tray
Figure 11 Typical construction sequence showing membrane details at external wall for a suspended concrete floor
continuous and as airtight as possible; all joints, including any in the cavity
tray, should be carefully and durably sealed. Dry lapping is not satisfactory.
As with the provision of all damp-proof courses, weepholes will have to be
provided in the outer leaf to drain the cavity. To ensure that the cavity tray is
fully supported, the cavity should be filled up to the level of the membrane
with mortar.
Light partition
Figure 13 Ensuring continuity of the radon-proof membrane passing through internal walls
Service penetrations
Where possible, service entries should avoid penetrating the radon-proof
membrane. Where this is not possible it will be necessary to construct an
Tape
airtight seal around each entry (Figure 14). Prefabricated ‘top hat’ sections are
‘Top hat’ available from some membrane manufacturers for sealing around pipe entries.
Radon- The membrane should preferably not be lapped at penetrations because of the
proof
membrane
difficulty of sealing. With careful design all supply services, with the exception
of mains water, can be brought up the outside of the building to enter through
walls. However, accommodating service entries in walls may limit where
Figure 14 Achieving an airtight seal internal fixtures can be placed. Traps and other services should be located so
around service penetrations as not to damage the radon-proof membrane within the floor slab.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Subfloor ventilation 15
Tanking to basements and cellars
If a basement or cellar is to be fully tanked to prevent damp penetration, it will
also provide radon protection. There is no need to provide supplementary
protection such as a sump in such cases.
Blinding
Where a membrane is to be placed over fi ll material, the fi ll should be blinded (ie
its surface fi nished with a fi ne material) to leave a surface which will not puncture
the membrane. This is especially important if 1200 gauge polyethylene is used,
but care is required even with tougher reinforced membrane materials. Care
must be taken to ensure that the blinding material does not block up the voids
throughout the depth of the fill, or the efficiency of the sump system will be
impaired. This is particularly important if the permeable fill is of minimal
thickness. The material therefore should be granular, without sharp edges
that would puncture the membrane. Foam sheeting could be used instead of
blinding, but this is likely to be more expensive.
Where the radon-proof membrane would otherwise be left exposed within
a ventilated space, it is advisable to cover it with a thin topping of concrete to
reduce the risk of damage by following trades.
Reinforced slabs
Where an in-situ concrete slab is laid with its edge supported on the inner leaf
of an external wall, the slab must be strong enough to prevent cracking in the
centre of the slab should the fill beneath settle. Such slabs should be
reinforced. Where unreinforced slabs are laid, radon-proof membranes
should accommodate any possible settlement of the slab.
Subfloor ventilation
No air shall be drawn into the building from the floor void, for example for
the provision of air for solid fuel, oil- or gas-fired combustion appliances.
Periscope ventilators
Where periscope subfloor ventilators are used, the joints between the
different parts of the ventilators must be taped to reduce the risk of radon
entering the cavity. As it is difficult to seal a radon-proof membrane or cavity
tray to a periscope ventilator, it is important to try to position ventilators so
that they do not penetrate the membrane or cavity tray (Figure 15).
Weephole
Cavity fill
Sumps
Provision of sumps
Where the assessed risk is greater than 10%, a sump and its associated
pipework should be built into all new dwellings or extensions at the time of
construction. This provision for additional ventilation is not activated,
however, unless testing determines that it is necessary. The active ventilation
of the sump is defined as Stage 3 measures, but these are not part of the
construction of new dwellings. Sumps require associated pipework to link
them with a suitable outlet and for fans or passive stacks to be connected. The
cost and inconvenience of retrofitting these sumps and associated pipework,
after the building is completed, can be disproportionately high.
Location of sumps
For a typical dwelling a single sump will probably be sufficient. Where clean
permeable fill has been used, a single sump is likely to have an influence over
Pipe taken through the an area of approximately 250 m2, or for a distance of 15 metres from the sump.
wall or up through the roof Where any part of the dwelling on clean permeable fill is more than 17 metres
from the sump, or where an area of greater than 10 square metres is more than
15 metres from a proposed single sump, a second sump will be required.
Where two or more sumps are provided, it is possible to link these through a
single fan extract pipe.
A sump will operate in a more efficient manner when centrally located
under the dwelling (Figure 16). It should be constructed to ensure that the
Sump
entry to the connecting pipes is not blocked when the fill is placed. To allow
Plan views
for maximum depressurisation, fill material should not contain excessive fines.
Figure 16 Central positioning of sump It is also possible to provide the required ventilation by edge-located mini-
under dwelling sumps. However, they are not as efficient as central sumps and therefore in
larger dwellings, or dwellings with non-rectangular plan shapes, more than
one may be required. Depending on the location, this mini-sump may also
require its own vertical pipe and fan.
Sumps 17
Blinding
Bricks laid in
honeycomb
Ventilation
bond. Perpends
gaps
must be left open
Bricks laid in honeycomb bond.
Perpends must be left open
Access plug
Pipework
from sump
Hardcore
Sump
Key
Sump
Fan
Plan views
Hardcore
Location of fans
Although not required at the construction stage, fan location must be
considered in relation to sump positioning and the stub-duct and vertical pipe.
The vertical pipe should be positioned with the outlet well away from
windows, doors and ventilation grilles, ideally discharging just above eaves
level. Low-level discharge may be possible if there are no openings or vents
close by. Where pipework is ducted through the dwelling and a fan is fitted, it
Figure 22 Pipework ducted internally, should always be placed as close to the outlet as practical (Figure 22). This
with the fan outlet through the roof and not keeps most of the pipework under suction, since even slight leaks could
ventilated into the roof space increase indoor radon concentrations.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Extensions 19
Passive stack subfloor depressurisation
Subfloor depressurisation is usually achieved using an electric fan to provide
suction. However, it may be possible to depressurise the subfloor area
sufficiently without using a fan. Such a system would comprise a vertical stack
pipe taken through the dwelling from the radon sump to discharge at a point at
or above ridge level. Passive stack ventilation is best suited to centrally located
sumps. Further information is available in BRE Good Building Guide 25.
Extensions
Any extension erected in an affected area, even where exempted from
compliance with the Technical Standards, should have appropriate radon-
protective measures incorporated in the construction if it is to be enclosed.
For a dwelling with existing radon-protective measures, an extension
should incorporate protective measures complying with the latest
recommendations. The radon-proof membrane to the extension should be
linked to the system of protection for the existing dwelling. Guidance on how
this might be achieved can be found in BRE Good Building Guide 25 (see Part
4: Protecting new extensions and conservatories).
Where the dwelling has a system already operating from a sump, new
connections to this system could lead to short circuits in the airflow.
Extensions, or alterations affecting the system or subfloor, therefore must be
carefully considered and advice sought where necessary.
Other hazards
High water-table
In areas where it is known that the water-table is particularly high, or the level
fluctuates, there is a risk that radon sumps may become waterlogged and
therefore ineffective. In such cases tanking should be used to prevent water
ingress and provide radon protection. There is no need to provide a radon
sump when tanking is used. It should be noted that, generally, water will act as
a screen to radon. However, if the water level fluctuates, the air pressure in the
soil will also change, which in turn may drive more radon into the building.
Garages
Integral garages with occupied rooms above, or with direct access through a
doorway from the garage to the dwelling, need the same provision as the rest
of the dwelling.
Stepped foundations
Where possible, stepped foundations should be avoided, as they complicate
the achievement of radon protection using only sealing techniques. It may
prove less expensive to excavate around the dwelling (Figure 23) to provide a
ventilated space, than to try to build into the hillside and seal all the faces of
the building which are below ground level. Knowledge of how to construct
stepped foundations sealed against radon is limited, but the following points
should be considered.
● Where a suspended concrete floor is used, any void below it should be
ventilated to the outside.
Ventilation ● It is important that any radon-proof membrane should be incorporated in
space
such a way as not to create a slip plane. This is of particular importance for a
retaining wall. Similarly, continuity of any structural reinforcement will
need to be considered at points where it would penetrate the membrane.
Structural requirements remain of paramount importance.
● As with floors built on one level, it is important to try to avoid positioning
service entries where they would penetrate the radon-proof membrane.
Figure 23 Provision of a ventilated space Where they do penetrate the membrane they will need to be adequately
around a building built into the hillside sealed.
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontr
Existing buildings
In addition to the use of centrally located sumps, experience gained by BRE in
developing radon remedial measures for use in existing dwellings has led to the
development of externally excavated sump systems. Research has shown that
such systems can prove effective in reducing indoor radon levels within small to
medium-sized dwellings with a ground fl oor area of up to 30 m2 (see comments
under Location of sumps above). This would suggest that although it is preferable to
locate a sump centrally within a new dwelling, an edge-located mini-sump with
good surrounding fill could be adequate for small to medium-sized dwellings.
Guidance on externally excavated sumps can be found in BRE Report
Radon sump systems: a BRE guide to radon remedial measures in existing dwellings.
Acknowledgements 21
Acknowledgements
The guidance in this report draws upon the research and experience of
Building Research Establishment Ltd. Thanks go to the members of the
National Radiological Protection Board for their assistance in preparing this
report, and to all those who provided comment during the consultation stage.
Further information
● For further advice regarding building matters contact: BRE Scottish
Laboratory, Kelvin Road, East Kilbride, G57 0RZ; telephone 01355 576255.
● For further advice regarding radon measurement contact: Radon Survey,
National Radiological Protection Board, Chilton, Didcot, Oxon,
OX11 0RQ; telephone 01235 831600.
22
Maps of designated radon-affected areas
Map 1 Estimated proportion of dwellings exceeding the Action Level in each 5 km grid shown: Highland region
Licensed copy from CIS: fraser.walsh@scotland.gsi.gov.uk, Scottish Building Standards Agency, 09/04/2014, Uncontro
Insch
23