Professional Documents
Culture Documents
Economics - Section 8
Economics - Section 8
Section (8)
ü Cash flow
ü Sheet problems
i Discount rate
N Number of periods
TRR True rate of return and it is just another name for the DCFRR
DCFRR Discounted Cash Flow Rate of Return (Value of rate of return i at NPW = 0 and NFW = 0)
Cash flow
slightly above zero,
would this be
accepted??
if Meaning Therfore
NPV>0 the investment would add value to The project may be accepted
the firm
NPV<0 the investment would subtract value The project should be rejected
from the firm
Sheet - Problem 1:
• The following table shows the NPV of each cash
flow and the NPV of the whole project is the
summation of all the NPV of all the cash flows.
Also find the value of i (rate on return) that makes the project justified if the investment was
made 2 years ago instead of 1 year ago.
Initial fixed investment of $200,000, WCI of $20,000 and final salvage value of $20,000 and
the series of cash flow are:
Determine TRR ??
• Both the WCI & the salvage value are returned at the
end of the project, so both values are added here on
the cash of year 7
• Any value between brackets means it is a negative
value or out cash flow
• Equate the NPW with zero and get value of I, either
by trial and error or using calculator.
Sheet - Problem 4:
• If the project’s IRR is higher than the DCFRR, the project generates
a loss.
• Conversely, if the IRR is lower than the DCFRR, the project results in
a profit.
Project Evaluation:
challenging.
• Since the required rate of return (presumably IRR) is 15%, which is lower than the