Method Statement For Piletest
Method Statement For Piletest
This document is property of Eni Tunisia B.V. who will safeguard its rights according to the civil and penal provision of the law.
Index
1. APPLICATION AREA....................………………………………………..…….……......…3
4. EQUIPEMENTS.......................................................................................................................3
The subject of this procedure is to describe the method adopted for in situ tests of piles foundation solution of
GREENFIELD Project TATAOUINE.
2. REFERENCE DOCUMENTS
3. PILES SOLUTION
According to all inputs with regards to geotechnical investigation reports and to TERRASOL Report , the
soil is considered unsuitable for piles ramming. So, the solution that will be adopted for Tracker
foundation is concrete micro piles.
In accordance with geotechnical study, the drilling holes will be conducted with 320mm diameter and
2000mm depth. These 2 required parameters are theorical sufficient. These two parameters will be
confirmed by site tests as per project requirement.
Eventually, and as additional piles solution tests (ramming technics), a trial tests will be conducted for
drill holes, with soil substitution and piles ramming. (without concrete).
4. EQUIPMENTS
Backhoe
Lifting sling
Tightener
Dynamometer
Pile
5. TEST STEPS
The tests will be conducted in different site areas to ensure a sufficient samples of typical soil types. And
to ensure as possible real conditions of piles loads.
1. Tightener attached with lifting sling from 2 sides: 1 side from piles and 2 side from backhoe
2. Lateral force pile from tightener will be calculate with the dynamometer
Test procedure