Al Ghubrah IWP

Document No.: AG-I-MC-TP-004-C-01


Inspection & Test Plan (ITP) for
GRP/GRE Piping Installation

Revision Control Index

This sheet is the record of Revision. The previous issues are to be marked "superseded" and
archived.

Rev. No Date Revision Description Issue Description


00 5/1/2014 First Issue For Information
01 7/4/2014 As per OE request For Information
Al Ghubrah IWP
Document No.: AG-I-MC-TP-004-C-01
Inspection & Test Plan (ITP) for
GRP/GRE Piping Installation

Detailed Legend

S: Surveillance Point. Does not require specific notification to Owner by Contractor.


Monitoring or observing to verify whether an item or activity conforms to specified
requirement could be checked by Owner during the course of erection/construction.

R: Report Review Point. Review of Contractor' documentation. Contractor is required to


prepare a certificate or documents attesting to satisfactory performance of the related
i i for
test or inspection f information.
i f i

W: Witness Point. Requires notification to the Owner by the Contractor. Upon proper
written notification by the Contractor to the Owner, work may proceed beyond a
Witness Point with or without action by the Owner. Contractor will submit Inspection
Request (IR) or inspection schedule to Owner for the items to be witnessed by Owner.
If Owner fails to participate in the test and inspection according to the IR or inspection
schedule, Contractor may proceed with the inspection as per the schedule without the
presence of Owner.

H: Hold Point. Verification points beyond which work may not proceed until the Contractor
notifies the Owner and the Owner performs verification and gives notice to the
Contractor to proceed. Downstream construction and activities shall not proceed without
attendance or written approval of Owner.
Al Ghubrah IWP

GRP/GRE Piping Installation


Doc. No. AG-I-MC-TP-004-C-01
Inspection and Test Plan (ITP)
System Identification:
System Description:
Process
Oper. Applicable Code & Sub
Operation Characteristic Contractor Owner Verifying Documents Remarks
Nr Standard/References Contractor
Description
Material control, A1 Conforming to the material specification Data sheet H R R Material certificate
handling, receipt
A2 Free from damages OEM manual H R R Delivery note

A3 Visual inspection of pipe and fittings OEM manual H S S Method statement

A4 Handling/storing OEM manual H S S Method statement

Consumable B1 Storage
g condition of lamination kits OEM manual H S S Log
g book
handling
B2 Check expire date Data sheet H S S Log book

Earth work & C1 Check trench condition provided by civil OEM manual H W S civil report
pipe stringing (dry, size and elevation, recesses)

C2 Check bedding condition prior to laying of pipe OEM Manual H W W civil report
(thickness and compaction)

C3 Manual backfill for haunch and up to 1-2 lifts OEM Manual H S S


backfill

C4 Pipe embedment zone backfilling & compaction OEM Manual H S S


- up to at least 150mm above pipe crown
- larger than 1000 mm, 300mm above crown

Lamination D1 Marking & cutting Drawing H S S

D2 Joint surface preparation OEM Manual H S S

D3 Alignment / assembly of joint OEM Manual H W S


Al Ghubrah IWP

GRP/GRE Piping Installation


Doc. No. AG-I-MC-TP-004-C-01
Inspection and Test Plan (ITP)
System Identification:
System Description:
Process
Oper. Applicable Code & Sub
Operation Characteristic Contractor Owner Verifying Documents Remarks
Nr Standard/References Contractor
Description
D4 Fit-up layers OEM Manual H S S

D5 Reinforcement layer OEM Manual H S S

D6 Inspection of joints OEM Manual H W S

D7 Barcol test Drawing H W W Barcol test report

D8 g assemblyy
Check flange OEM Manual H S S Pipe
p work pre-test
p checklist
(surface cleanliness, alignment and torque
value)

D9 Check support installation Drawing H S' S

D10 Approval for pressure test Drawing H H R Approval for pressure


testing
D11 Pressure test Test package H H W Pressure test report
ASME B31.3
D12 Draining & drying Test package H W S

Final inspection G1 Reinstatement of the piping system Pipe work post-test H H w Pipe work post-test
checklist checklist

Legend S: Surveillance R: Report Review W: Witness Point H: Hold Point