Professional Documents
Culture Documents
Air Blowing (Rupture Blowing) Works - Precommissioning Rams
Air Blowing (Rupture Blowing) Works - Precommissioning Rams
Air Blowing (Rupture Blowing) Works - Precommissioning Rams
Bapco BAPCO
CONSTRUCTION
;r.. f. �(/1N\
QUAL
[7
APPROVED
HSE L
□
APPROVED WITH COMMENTS
ENGINE I
c:=>-
□
REVISE AND RESUBMIT
COMMISSIONING � NOT APPLICABLE
SIGNATURE/ DATE
AREA2:
jJ-
CONSTRUCTION □
□
APPROVED
QUALITY
c:=>-
HSE
□
APPROVED WITH COMMENTS
ENGINEERING
□
REVISE AND RESUBMIT
COMMISSIONING �
JL
NOT APPLICABLE
SIGNATUREJ DATE
ARE A4:
CONSTRUCTION
QUALIT
□
APPROVED
�
HSE � c:=>-
□
APPROVED WITH COMMENTS
ENGINEE ING
□
REVISE AND RESUBMIT
COMMISSIONING � NOT APPLICABLE
SIGNATURE/ DATE
AREAS:
J1
□ c4--
CONSTRUCTION APPROVED �� �d'� [Y"
QUALi
HSE ��
□
APPROVED WITH COM NTS
ENGINE R
c:=>- REVISE AND RESUBMIT
COMMISSIONING � NOT APPLICABLE
SIGNATURE/ DATE
AREA6:
�
CONSTRUCTION
QUALITY □
□
APPROVED
HSE
□
APPROVED WITH COMMENTS
ENGINEERING
COMMISSIONING
□
REVISE AND RESUBMIT
NOT APPLICABLE
SIGNATURE/ DATE
A = APPROVED
AC = APPROVED WITH COMMENTS
RC = REVISE AND RESUBMIT
N/A = NOT APPLICABLE
Note: this approval form, once filled, is to be attached with the document
submitted to the return transmittal.
TTSJV W.L.L. - P.O. Box 28110 Muharraq - Block 215, Road 1531, Building 1130 Flat 12, Kingdom of Bahrain
±:::':::ir:it:""' -
RISK ASSESSMENT NARRATIVE Reference No. NSH4-RAMS-0135
Location: AREA 3, 4 & 5 Job Title: AIR BLOWING (RUPTURE BLOWING ) WORKS Issue Date/Rev No. 24-03-2024 00
Purpose:
The following work steps have been anticipated to determine the precise safe work execution of above mentioned activities. This RAMS specifically refers to Scope of works and
Limited boundaries. Daily work activity will be executed in normal day time starting from 06:00HRS until 17:00HRS and night time from 17:00HRS to 06:00HRS.
This RAMS is also valid for the night shift work due to summer day shift ban from 16:00 HRS to 03:00 HRS and day shift from 03:00 HRS to 12:00 HRS..
Scope of Work :
1). Obtaining permit
2). Air blowing preparation
3). Protection of equipment’s and workers in the vicinity of air outlet
4). Polyethylene blasting method (Rupture blowing)
People Involved:
Superintendents, Supervisors, Foreman, Equipment Operators, Driver, Traffic Controllers, Riggers, Pipe Fitters, Electricians, Fire watchers, Skilled Labors
Note:
1. Night shift work shall be done only by prior approval of the TTSJV / OWNER.
2. TTSJV inspection team must inspect all equipment and issue site sticker prior to entry to site.
3. All cargo straps must meet the requirements of BS EN 12195 part 2 & 3
4. Other relevant hazards shall be communicated & managed through TBT/ START meeting on site.
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
1.7 Employees unaware about the 1.4.1 Sufficient fresh cool drinking water to be
ongoing air blowing activity provided as per the man power ratio prior
to commence the activity.
1.4.2 Rest shelters and toilets to be provided as
per ratio of TTSJV requirement. Rest
shelters shall be equipped with industrial
water mist fan
TTSJV.
1.6.2 The affected person shall be immediately
shifted to the nearest shaded location or
heat stress shelter. Medical attention shall
be made available at the earliest.
1.6.3 First aider’s shall ensure that sufficient cold
packs are available along with the first aid
kit
1.7.1 No work shall be carried out in the air
blowing exclusion zone.
1.7.2 Restrict access into air blowing area to
authorized personnel only.
1.7.3 The area will be demarcated with the
hazard tape (black/yellow)
1.7.4 Standby man should be assigned near the
blow out area to restrict unauthorized
entry.
Page 3 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 4 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 5 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 6 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 7 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 8 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 9 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
humid condition, 7.2 Poor visibility. ache, sun burn, 7.1.2 Lone working is prohibited.
Sand storm, fog Electrocution 7.1.3 Sufficient cool drinking water shall be
and Rain 7.3 Instable ground due to rain. available in the nearby location.
7.4 Electrocution. 7.1.4 Rest shelters with fan, and relevant heat
stress prevention posters shall be in
place.
7.1.5 Specific campaigns shall be conducted
periodically to enhance the workers
awareness to act for preventing heat
related issues.
7.1.6 Emergency contact numbers shall be
posted in all welfare facilities nearby.
7.1.7 Urine color identification posters shall be
posted in all urinals/toilets.
7.1.8 Emphasis workers about the importance
of sufficient fluid and food intake.
7.1.9 Emphasis work force to wear loose cotton
coverall.
7.2.1 Wear mask and clear glass during sand
storm. Buses/rest shelters or portables
shall be arranged in nearby location in
case of heavy sand storm and rain. Do
not operate any equipment and do not
work on elevated platforms during heavy
wind and fog.
7.3.1 All cranes booms shall be retracted
completely. All outriggers shall be fully
extended. All crawler cranes lattice boom
tips shall either be lowered completely
and shall be rested on the ground surface
or else the hook blocks shall be lowered
to ground level and must be arrested with
sufficient counter blocks. After the rain all
activities including equipment operation
shall only be restarted after the
confirmation from competent persons and
the HSE managers OF NSH and TTSJV.
7.3.2 After the rain, all scaffolds shall be re
inspected by the scaffold inspector prior
to use.
7.1.1 In case of inclement weather like rain the
work should be stopped. All power
connections shall switched off.
7.1.2 All junction boxes shall be weather proof.
7.1.3 After the rain the power generator and
welding generator shall only be activated
after thorough inspection of competent
Page 11 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
electrician.
Page 13 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 14 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 15 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 16 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 17 of
RISK ASSESSMENT FORM Reference No. GAC-RAMS-0135
Page 18 of
ACTION ITEM TRACKING FORM Reference No. NSH4-RAMS-0135
Location: Job Title: AIR BLOWING (PRE-COMMISSIONING ) WORKS Issue Date/Rev No. 00
AREA 3, 4 & 5 24-03-2024
I have read and understood the hazards and controls associated with this / my job
Department /Company Name Badge Number Job Title Signature Date
NSH 2-RAMS-0001
Likelihood Level
HSE SEVERITY AND RISK MATRIX 1 - Rare 2 - Remote 3 - Occasional 4 - Frequent 5 - Almost certain
Exposure to
Activity occurs less than
activity by Activity occurs yearly Activity occurs quaterly Activity occurs monthly Activity occurs weekly
yearly
location
People Environment** Reputation Schedule Cost Incident has occurred in last 5 Incident has occurred more Incident has occurred more than
Frequency of Incident has never occurred in Incident has occurred in a year
years than 3 times a year in the 3 times a year in the
Incident last 5 years in the company in the company
in the company company work place
Score 1 2 4 8 16
- Extended Duration of impact > 1 year International impact with major - Major miss-operation, heavy cost to recover.
- Recovery requires external assistance consequences on strategy continuity - Activity delay over 16 weeks - profit loss > 5%
- Multiple breaches of environmental license of Technip FMC wide activities - - Contract delivery delay consistent - impact on entity/Region figures > 20%
16 16 32 64 128 256
conditions & regulations or contractual Damage to relationship with a client with critical time extension leading to- reduction of assest availability > 10%
Illness: Life Threating Illness: A very requirements resulted in a fine or that can affect other Clients and/or pay 50% to 100% of LD's for delay
serious illness contracted at work that might prosecution. GBU level - service downtime > 24 hrs 3) Projects adjusted scale
result in death - Enforcement action by Regulatory Agency - Fleet unavailability over 3 weeks e.g: financial loss > 5% of Project gross margin
Injury : Lost Time Injury / Partial or total 3) Projects adjusted scale 1&2) Entity, Asset, Dept, functions adjusted scale
e.g: e.g:
Severity Level
negative impact on relationship with - Contract delivery delay consistent - impact on entity/asset figures between 5% to 10%
- Extended Duration of impact < 3 months
key Stakeholders - Possible impact with critical time extension - reduction of assest availability between 2% to 5%
- Recovery requires external assistance 4 4 8 16 32 64
on relationship with a key Client (exposure < 20% of LD's for delay)
- Repeated Breach of license conditions,
Illness: Illness resulting in sick leave and beyond the contract or on multiple - service downtime from 3 to 12 3) Projects adjusted scale
regulation, Contractual requirement.
requiring medical treatment and / or recurrent projects hours e.g: financial loss between 0,1 and 1% of Project
- Enforcement action by Regulatory Agency
illness. Illness resulting in temporal work - Fleet unavailability 4 days to 1 gross margin
restriction and/or resulting in change of work weeks
extension within grace period (if any)- impact on entity figures < 5%
- No external assistance / Easy controlled / from local community - Impact on
- service downtime from 1 to 3 hours - reduction of assest availability < 2% 2 2 4 8 16 32
Recovery by worksite. Client's relationship confined at
- Fleet unavailability 1 to 4 days
- Single Breach of license conditions, contract level / on single Project.
3) Projects adjusted scale
Illness: Any disorder or illness which has regulation, Contractual requirement.
e.g: financial loss < 0,1% of Project gross margin
short term impact on the task of the employee - Warning provided by Regulatory Agency
with no medical treatment
* This document is a combined table of people, environmental and property damage categories and is in no way or manner intended to be a comparison of those categories
** For Impact Definition please refer to the Environmental Incident Classification Guideline
CONSEQUENCES:
Ache/pain
Back and arm disorders
Back and neck pain
Back injuries
Burns
Bursting of sludge drain
Cancer
Carpel Tunnel Syndrome
Causes burns to any area of contact & destructive to upper respiratory tract
Cold burns
Cuts or lacerations
Death
Diseases and infections
Drowning
Environmental impact
Electrical Shock
Explosion
Eye burns
Eye cataract
Eye irritation
Eyestrain
Fatigue/stress
Fire
First aid injury
Fractures
Frost bite
Head injury
Heat dermatitis
Heat exhaustion
Heat stress
Heat stroke
Irritation to respiratory system
Irritation to respiratory system and eyes
Irritation to respiratory system, eyes and skin
Irritation to skin
Irritation to skin, and respiratory tract
Irritation to the eyes and throat
Lost Time/ Non Lost Time injury (i.e. sprains, fracture, cut, lacerations, burns or bruises) or health effect (i.e.
deafness or dermatitis)
Lower back injury
Lower performance
Major injuries (i.e. amputations, major fractures, multiple injuries) or health effects (i.e. severely life shortening
disease, occupational illness)
May cause irritation to skin, eyes, and respiratory tract and may cause allergic reaction and breathing
difficulties
Neck pain
NIHL
Nuisances smell
Page 22 of 32
Oxygen deficiency
Phosgene
Physical injury
Psychological pressure
Redness of skin
Serious burns
Serious burns or death
Single or multiple fatalities or permanent disability
Slips or trips under insufficient lighting
Sprains and fractures
Sprints, cuts or fractures
Stinging eye irritation and nose or throat irritation
Toxic
Unconsciousness
Upper limb disorders
Visual discomfort
Wrist pain and tense muscles
HAZARDS:
WORK PLACE HAZARDS: CHEMICAL HAZARDS: PHYSICAL HAZARDS: EQUIPMENT HAZARDS: PROCESS HAZARDS:
Access/Egress Acid Burn Awkward posture Brazing Propulsion of materials
Adverse weather Acid splash Broken glass Cleaning Restricted working space
Electrical hazards Asphyxiation Contact with hot materials Contact with cold surfaces Steam leaks
Charging chemicals to the Use of machines - moving parts
Electrical shocks system Glaring light Contact with hot surfaces hazards
Ergonomic problems Chemical burn Infrared emissions Caught in Between OTHER HAZARDS:
Excessive use of mouse Chemical explosion Ionizing radiations Cutting pipes Biological hazards
Extended work hours Chemical fumes Manual lifting/handling Drowning Circadian rhythm disorder
Fire/Explosion Chemical spillage Needle stick Entanglement Collision
Glaring light Chemical Splash Non-Ionizing radiations Excavation Exposure to asbestos
Personal noise exposure 80 dBA Failure of drain cleaning
Heating Cleaning - spillage of Steamate and peak of 135 dBC (trapped Pipes) Exposure to insects and rodents
Personal noise exposure 85 dBA
Hot working environment Contact with gas and peak 137 dBC Failure to isolate the systems Confined spaces
Personal noise exposure 87 dBA
Improper storage/stacking Contact with hot materials and peak 140 dBC Fall of objects from height Handling gas cylinders
Long exposure to DCS/PC
monitors Contact with liquids Poor lighting Fall of persons from height Medical emergency
Obstruction Corrosive materials UV/IR radiation Falling from heights Musculoskeletal problem
Office ergonomics Diesel spill Vibrations Fall from ladders Natural phenomena / calamity
Poor housekeeping Exposure to <300 ppm H2S Water Leak Fall from ladders >6m Non-occupational hazards
Exposure to 300 ppm to <1,000 Head impact into low height pipes
Poor lighting ppm H2S Water Spill Oil Spill