W = Weight of hammer (Ton.) = 3.50 4.50 Ton. fc' = Concrete strength (Prestressed) = 350 kg./cm2 A = Area of pile = 900.00 cm2 L = Height of pile (m.) = 7.00 m. H = Height of drop (cm.) = 40 cm. W 3.50 40.00
Height of drop H = 40.00 50.00 60.00 70.00 80.00 cm. S = 7.216 H = 40.00 Last 10 blows S = 7.216 9.364 11.512 13.659 15.807 cm. λ = 0.7393 W = 3.50 Blows per foot N = 42 33 27 22 19 blows. K = 1.940 Cd = 0.81 RECHECK FROM LAST 10 BLOWS Weight of hammer = 4.50 Ton. WH Qu = = 100.00 Ton. Height of drop H = 40.00 50.00 60.00 70.00 80.00 cm. KS
Last 10 blows S = 9.869 12.681 15.492 18.303 21.114 cm. WH
Qa = / F .S = 40.00 Ton. Blows per foot N = 31 24 20 17 15 blows. KS