Professional Documents
Culture Documents
Hitung Besi Farid (Training)
Hitung Besi Farid (Training)
Hitung Besi Farid (Training)
8 METER
TULANGAN ATAS & BAWAH
7 METER
8 METER
TULANGAN TENGAH (TUMPUAN)
TB1 7 METER
8 METER
TULANGAN TENGAH (LAPANGAN)
7 METER
4 METER
TULANGAN ATAS & BAWAH
3 METER
4 METER
TB2 TULANGAN TENGAH (TUMPUAN)
3 METER
4 METER
TULANGAN TENGAH (LAPANGAN)
3 METER
8 METER
SENGKANG/CINCIN (TUMPUAN)
7 METER
TB1 & TB2
8 METER
SENGKANG/CINCIN (LAPANGAN)
7 METER
NOTE :
TUMPUAN TB1 = 40X16 640
LAPANGAN TB1 = 40X16 640
TUMPUAN TB2 = 40X10 400
LAPANGAN TB2 = 40X10 400
32.8 M'
13.12 M'
11.12 M'
26 M'
20.4 M'
5.6 M'
67.2 M' D10
4.6 M'
5.6 M'
4.6 M'
100 BH
40 BH
45 BH
370 M' ⌀10
67 BH
26.66667 BH
30 BH
0.32 M'
0.128 M'
0.64 M' D10
0.192 M'
MM
MM
MM
MM
MM
KEBUTUHAN WASTE/BTG TOTAL KEBUTUHAN/BTG
5.65 6.00 BTG 10% 1 7
23.96 23 BTG 10% 2 25
30.83 31 BTG 10% 3 34