B 00 1512 005 Rev1 Proj NCR Proc 2
B 00 1512 005 Rev1 Proj NCR Proc 2
TABLE OF CONTENTS
1.0 OBJECTIVE
2.0 SCOPE
3.0 RESPONSIBILITIES
3.1 The QA/QC Manager
3.2 The Recipient
3.3 The Identifier / Originator
3.4 The Document Control Center – D.C.C.
4.0 DEFINITIONS
5.0 REFERENCES
6.0 PROCEDURE
6.1 Discovery of Nonconformance
6.2 Issue of the Non-conformance
6.3 Non-conformance Criteria
6.4 Proposal and Agreement of Corrective Actions
6.5 Corrective Action Request Upgrade
6.6 Preventative Action
6.7 Register of Non-conformances
6.8 Non-conformance Identification
6.9 Disposition of the Non-conformance
6.10 Close out of the Non-conformance
6.11 Review and Analysis
6.12 Records
7.0 APPENDICES
_______________________________________________________________________________
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 2 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
For quick reference the table below is showing when Alteration or Addition to this Document
has been made - X is placed in the applicable Page Number / Revision Status box.
PAGE Rev Rev Rev Rev Rev Rev Rev PAGE Rev Rev Rev Rev Rev Rev Rev
NUMBER 0 1 2 3 4 5 6 NUMBER 0 1 2 3 4 5 6
1 43
2 44
3 45
4 46
5 47
6 48
7 49
8 50
9 51
10 52
11 53
12 54
13 55
14 56
15 57
16 58
17 59
18 60
19 61
20 62
21 63
22 64
23 65
24 66
25 67
26 68
27 69
28 70
29 71
30 72
31 73
32 74
33 75
34 76
35 77
36 78
37 79
38 80
39 81
40 82
41 83
42 84
_______________________________________________________________________________
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 3 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
1.0 OBJECTIVE
This procedure defines the method for raising, recording, controlling and closing out
the Non-Conformance(s) Reports (NCR’s) within the IRAN LNG Project.
In addition, its aim is to share learning to prevent further loss, and to increase the
overall knowledge of staff, by recording and distributing key information among all
IRAN LNG Project Staff.
2.0 SCOPE
This procedure applies to Non-conformance reporting at any phase of the IRAN LNG
project development. Any member of the Project Team can identify non-
conformances.
Where applicable to their scope of work the IRAN LNG Contractors shall comply with
the requirements of this procedure
3.0 RESPONSIBILITIES
_______________________________________________________________________________
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 4 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
the Contractor the officially transmitted original of the closed-out NCR and for filing in
a specific NCR filing systems.
4.0 DEFINITIONS
4.1 Non-conformance
Any failure to comply with specified Project specifications that if uncorrected could
lead to loss of life, loss of production or the loss of the use of a utility or facility.
6.0 PROCEDURE
All NCR’s shall be processed in accordance with the following procedure and the
attached Flowchart, reference Appendix 1.
In the event that corrective action is not implemented within the required time frame
then the identifier shall discuss the issue with his immediate supervisor and obtain
agreement that a NCR should be raised. Also a check shall be carried out to ensure
that the discrepancy is not already the subject of an existing NCR, concession,
deviation, change request or other formal process for remedial action.
_______________________________________________________________________________
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 5 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
The NCR / CAR shall be drafted in complete and precise detail including sub-system
identification, such that traceability and monitoring of the nonconforming item can be
readily achieved. It shall also be worded such that it can be closed out subsequent to
corrective action having been completed by the recipient. It shall be the responsibility
of the CSR or IRAN LNG Project Processes and Management Systems owner to
initiate the appropriate immediate action i.e. stop the work, introduce an immediate
system change, etc., until the corrective action has been proposed, completed and
accepted.
The DCC shall transmit the original NCR to the recipient; undercover of a Transmittal
Note. The DCC shall also update their NCR index and maintain a copy of the NCR
on file.
The proposed corrective action(s) and the proposed time scale for close out shall be
agreed with the QA/QC Manager, in conjunction with the CSR or equivalent, prior to
implementation.
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 6 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
The method used may vary according to the type of product and the type of Non-
conformance (e.g. tag and quarantine a valve, lock out a CAD model).
For an NCR relating to management systems a Quality Bulletin (or Project Email)
may be used to alert others of the nature of the Non-conformance and the probability
that the system is to be modified.
o Carry out remedial work in accordance with an approved procedure and re-
inspect to the original requirements.
o Reject the product in it’s entirety and return to the supplier or re-fabricate to the
original requirements.
The disposition method used shall be noted for the inclusion in Project quality
records
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
DOCUMENT TITLE DOCUMENT NO.
PROJECT NON - Doc. Unit Seq.
FWBS Rev Page 7 of 7
Type Number Number
CONFORMANCE REPORTING
PROCEDURE ILC B 00 1512 005 1
The QA/QC Manager shall verify that the Non-conformance has been processed in
accordance with this Non-conformance Procedure by finally counter signing the
NCR. The QA/QC Manager shall record the close out details in the NCR register file
a copy of the NCR and all relevant documentation, for inclusion in the Project quality
records. The NCR shall then be considered formally closed out. The original will then
be officially transmitted to the Contractor.
In the event that there is a request from the Contractor to perform a Joint QC
Inspection or for the Final Joint PC&C Inspection prior to the closeout of associated
NCR’s then at the discretion of the QA/QC Manager the closure of the NCR’s may be
carried over and recorded as a punch item on the relevant Punch List.
If after review and analysis any significant trends of failures are identified then
measures shall be taken to prevent continuing re-occurrence and the details shall be
recorded through the lessons learned philosophy.
The QA/QC Manager will produce as required, on a weekly basis a chart of open
NCR and closed NCR. This information will be passed to the team as an inclusion
into the weekly report
6.12 Records
NCR records are crucial for project demonstration of Technical Integrity and hand
over. The IRAN LNG Project Team Leaders shall maintain all records related to the
NCR for inclusion in the “Handover” documentation
7.0 APPENDICES
o Appendix 1 NCR Flow Chart
o Appendix 2 Non-conformance Report
o Appendix 3 NCR Register
_______________________________________________________________________________
ILC B-00-1512-005Rev1
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
IRAN LNG PROJECT
REF. Activity Description ILC REP. ILC QA/QC ILC CSR ILC DCC Contractor
REF. Activity Description ILC REP. ILC QA/QC ILC CSR ILC DCC Contractor
Sub - System
ILC Team Member/REP ILC QA/QC Department ILC Discipline Engineer
Issued By Endorsed By: Acknowledged:
Name Name Name:
Title Title Title
Signature Signature Signature
Date Date Date
Controlling Code, Specification or Procedure : Including Section & Paragraph
Details of Non-Conformance:
The ILC QC confirms Corrective Action has been completed and is acceptable with ILC Specifications
Name: Title: Signed: Date:
The Completion of the above Corrective Action has been verified by ILC Discipline Engineer
Name: Title: Signed: Date:
The Completion of the above Corrective Action has been Accepted and Closed ILC QA/QC
Name: Title: Signed: Date:
ILC B-00-1512-005
Project Non Conformance Reporting Procedure
Custodian: ILC QA/QC
Appendix 3 - NCR Register
IRAN LNG PROJECT
Non - Conformance Register
NCR No. Sub System Issued Discipline Location Description Date Issued Proposed Comments
No. to Closed out date
ILC B-00-1512-005
Project Non Conformance Procedure
Custodian: ILC QA/QC