Working shifts / day 2 shifts Customer demand / day 1300 pieces
Hours / shift 10 hours Available time / shift 600 minutes Break time / shift 30 minutes Lunch time / shift 30 minutes Net available time / day 64800 seconds / day Planned downtime / shift 0 minutes Customer demand / day 1300 pieces / day Net working time / shift 540 minutes Net working time / shift 32400 seconds Net available time / day 64800 seconds takt time = 50 seconds / piece
Takt Time Calculator
Note: B shift = 3 days x 12 hours Net Available Time Customer Demand
Working shifts / day 1 shifts Customer demand / day 770 pieces
Hours / shift 12 hours Available time / shift 720 minutes Break time / shift 45 minutes Lunch time / shift 30 minutes Net available time / day 38700 seconds /day Planned downtime / shift 0 minutes Customer demand / Day 770 pieces / day Net working time / Shift 645 minutes Net working time / shift 38700 seconds Net available time / day 38700 seconds takt time = 50 seconds / piece / piece