Takt Time Calculator

Note: A shift = 4 days x 10 hours


Net Available Time Customer Demand

Working shifts / day 2 shifts Customer demand / day 1300 pieces


Hours / shift 10 hours
Available time / shift 600 minutes
Break time / shift 30 minutes
Lunch time / shift 30 minutes Net available time / day 64800 seconds / day
Planned downtime / shift 0 minutes Customer demand / day 1300 pieces / day
Net working time / shift 540 minutes
Net working time / shift 32400 seconds
Net available time / day 64800 seconds takt time = 50 seconds / piece

Takt Time Calculator


Note: B shift = 3 days x 12 hours
Net Available Time Customer Demand

Working shifts / day 1 shifts Customer demand / day 770 pieces


Hours / shift 12 hours
Available time / shift 720 minutes
Break time / shift 45 minutes
Lunch time / shift 30 minutes Net available time / day 38700 seconds /day
Planned downtime / shift 0 minutes Customer demand / Day 770 pieces / day
Net working time / Shift 645 minutes
Net working time / shift 38700 seconds
Net available time / day 38700 seconds takt time = 50 seconds / piece
/ piece

/ piece