Intake 33 KV Line Estimation
Intake 33 KV Line Estimation
With reference to the above cited subject & as per the joint inspection conducted
in persenace of yourself along with the Executive Engineer, KUWSB, Kalaburgi &
C&M Staff, This estimate is prepared for construction of 21Km of new 33kV Single
Circuit line from existing 110/33/11KV Korwar sub-station to proposed 3.2MVA
Jack-well at Bennithora reservoir under Self Execution work. In this estimate the
33kV breaker and bay provision is not made at 110kV Korwar MUSS as this part
pertains to KPTCL authorities. Therefore estimate for 33kV breaker and bay alongwith
Yours faithfully,
2
Executive Engineer (Eleke/12
C&M Division, GESCOM,Kalaburagi.
Copy for kind information to:
1) The Chief Engineer (Electy), O8M Zone, GEScOM, Kalaburagi.
2) The Superintending Engineer (Ele), O&M Circle, GESCOM, Kalaburagi.
Copy t0
1) Executive Engineer, KUwSB, Kalaburgi for information.
2) The Asst. Executive Engineer (Ele), C&M Sub-Division-I(Farthabad Nodal Oficer),
GESCOM, Kalaburagi.