LAPORAN PROGRESS HARI KE : 30 Tanggal : 07 September 2023

Bobot Bobot Total Progress Real.


Item Pekerjaan Remark KURVA S PEKERJAAN TBM 32000 JAM PLTMG
Rencana Realisasi / Pekerjaan
ENGINE 5
Mechanical 24,24% 24,24% 100,00% Closed
100% Kurva S
Electrical, Control, & Automation 23,81% 23,81% 100,00% Closed
90%
Commissioning 1,57% 1,57% 100,00% Closed
ENGINE 19
80%
Mechanical 22,57% 22,57% 100,00% Closed
Electrical, Control, & Automation 25,67% 25,67% 100,00% Closed
Commissioning 70%
2,14% 2,14% 100,00% Closed

60%

% Complete
Total Progress Rencana 100,00%
Total Progress Realisasi 100,00%
50%

Progress Keseluruhan : Leading 0,00%


40%

30%

20%

10%

0% 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Rencana 0,00 1,7%3,7%5,4%7,8% 10,7 14,4 19,2 23,0 27,5 31,0 34,6 37,5 40,7 43,8 47,0 50,6 53,8 56,3 61,2 65,9 71,4 75,2 78,7 83,1 87,0 91,0 95,1 97,4 99,8 100,
Realisasi 0,00 1,6%3,7%5,5%8,5% 11,4 15,1 19,8 23,7 28,3 31,8 35,4 38,3 41,3 44,7 47,7 51,1 54,6 56,9 61,6 66,4 71,5 75,4 79,1 83,1 86,6 91,2 95,7 98,6 100, 100,

Diketahui Oleh Disaksikan Oleh Disetujui Oleh


Project Manager Team Leader Outage Management Asman Pemeliharaan
TAHUN 2023

LAMPIRAN PROGRESS HARI KE : 30 Tanggal : 07 September 2023

Item Pekerjaan Rencana Realisasi Kondisi REVIEW PEKERJAAN

ENGINE 5
Mechanical 100,00% 100,00% On Schedule 0,00%
Electrical, Control, & Automation 100,00% 100,00% On Schedule 0,00%
Commissioning 100,00% 100,00% On Schedule 0,00%
ENGINE 19
Mechanical 100,00% 100,00% On Schedule 0,00%
Electrical, Control, & Automation 100,00% 100,00% On Schedule 0,00%
Commissioning 100,00% 100,00% On Schedule 0,00%