TIME SCHEDULE

Owner : PT ABC KOGEN DAIRY Contractual


Project : Waste Water Treatment Plant Location : Cicalengka - Bandung Design & Engineering Civil Works
Date : 27 Nov 2023 Procurement & Fabrication Material Delivery to Site
Rev : 0 Site Fabrication & Installation M&E
Test & Commissioning

1 2 3 4 5 6 7 8 9

Task Name Duration Nov 2023 Dec 2023 Jan 2024 Feb 2024 Mar 2024 Apr 2023 Mei 2024 Jun 2024 Juli 2024 Agustus 2024 Remarks
(Days) 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3
A. CONTRACTUAL
- LoA
B. DESIGN ENGINEERING & DRAWING
- Design, Engineering & Shop Drawing

C. CIVIL WORKS
1 Preparation Works
2 Bore Pile
3 Equalization Tank + CT Foundation(New)
5 Foundation DAF (New)
4 Foundation Oil Separator
6 Blower Room
7 Chemical Room

8 Modification MCC Panel room


9 MBBR & Aeration #2Tank (Modif. dditional Wall 0.5 m )
10 Modification Clarfiier A
11 Modification Clarfiier B

D. MECHANICAL & ELECTRICAL WORKS MECHANICAL, ELECTRICAL & INSTRUMENTATIO WORKS


1 Procurements & Fabrications
- Pumps
- Oil Separator
- DAF (Dissolved Air Floatation) Unit
- Diffuser
- MBBR Media

- Cooling Tower
- MBBR Screen
- Air Blower
- Dosing Pumps & Agitator
- Instrumentation
- Panel Control
- Electrical Cable & Acessories
- Pipe, Fitting & Valves
- Chemical
2 Delivery & Material On Site
- 1st Shipment
- 2nd Shipment
- 3th Shipment

3 Installation
- Oil Separator
- Cooling Tower
- Balance Pump
- Equalization Pump
- Chemical Dosing Pumps & Agitator
- 1st Aeration (Replacement Diffuser)
- DAF (Dissolved Air Floatation) System

- Air Blower
- Scrapper of Secondary Clarifier
- RAS Pump
- Control Panel
Interconnection Cable and Accessories
- Interconnection Pipe, Fitting * Valves
- Instrumentation
4 Testing & Commissioning

1 Preparation Testing & Com (Cek motor, jartest, etc)


2 Seeding Bacteria
3 Testing & Commissioning

You might also like