Professional Documents
Culture Documents
PMPC Week 3-CLO 1
PMPC Week 3-CLO 1
PMPC Week 3-CLO 1
Control
Lesson 3
The Planning and Control Cycle
by Ir. Ts. Azri Adi B Arbai
Overall objective is to
finish the project within
the time, cost and
quality constraints set
by the client
• Project name
• Beneficial changes
• Key objectives
• Example:
• position of the crane and storage on a high rise building.
• Scope
• Objectives
• Authority
The main reasons that a project deviates from its plan are:
• Unexpected events will occur
Harrison (1995):
• The manager must be able to highlight the problem areas and
deviations from plan and budgets, and be able to take action to
maintain efficiency and achieve objectives.
• This is achieved through the collection and analysis of information
and comparison of actual progress and performance with the
baselines of schedule, cost and resources established in the project
plan.
• Reports on progress and performance should be prepared and the
project manager can then take action to deal with the problems
identified, that is, troubleshoot.
• In other words, the project manager must be able to ‘control’ the
project.
Work Authorization:
• Project manager (single point of responsibility) is responsible
for delegating and authorizing the scope of work.
• The method of authorizing work, reporting and applying
control should be discussed and agreed at the handover
meeting.
• A record of all decisions and instructions should be kept to
provide an audit trail, which is a sequence of steps supported
by proof documenting the real processing of a transaction flow
through an organization, a process or a system.
Expedite:
• Once instruction, orders and contracts have been issued,
project expediting takes a proactive approach to make the
instructions happen.
• It involves:
• Orders received from subcontractors
• Internal planning issued
• Material have been procured
• Skilled labour available
• Work started as planned
• Scheduled completion dates will be achieved
Change control:
• It ensures that all changes are captured and approved by the
designated people before being incorporated in baseline plan.
Decision-Making:
• It collate information and decides on the appropriate
corrective action.
• A typical decision-making process include:
• Define project objectives
• Define the problem
• Collect information
• Develop options and alternatives
• Evaluate and decide course of action
• Decide project team
• Implement the decision
• Project manager
• Has to monitors the project progress.
Other problems: