Electrical DWG Wintech Lift REV1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

CIDRZ OFFICE BUILDING

AND ASSOCIATED EXTERNAL WORKS

ELECTRICAL SERVICES SNAGS


5th June, 2024
SNAGS REPORT

ITEM DESCRIPTION COMMENTS IMAGE CONTRACTOR AND SUB-CONTRACTORS COMMENTS IMAGES SHOWING RECTIFICATION
NO.
1 DB labeling is not Martech to ensure that
complete. labeling is done. 1.1 DB labeling has been done concluded as of
17/06/2024
Cleaning of the Martech to clean the
DBs. DBs with Vacuum
cleaner. 1.2 All DBs, floor boxes and other electrical components
have been cleaned with vacuum cleaners.

2 Fire alarm panel Martech/ main


installation is not contractor to ensure
leveled/ or wood that fire alarm panel is
cutting not leveled correctly.
straight

3 Strip lights on the Martech to ensure that


bridge in not works are complete.
complete.

Page 2 of 4
4 Cable trays in the Martech to add cable Cable tray supports have been added to withhold the
Server room are trays supports to strength of the cables as shown in accompanying image
disturbed and withhold the strength
slanting. of the cables.

5. There is no Martech to provide Manhole has been supplied and installed as shown in
manhole cover man hole cover. accompanying image.
near feeder pillar NO IMAGE
at pump house.

6. Grating is not Main contractor/ Supplying and providing metal grating for the
done in the Martech to ensure that substation and electrical rooms was not a part of the
Electrical and grating is done. main contractor’s civil works.
Server rooms,
and substation Therefore, we kindly request that the PA issue an
instruction so that we may generate a variation
showing our cost for supplying and installing metal
grating in these locations.

Page 3 of 4
7. Covers on soffit Main contractor to Covers have been replaced and painted with corrosion
opening for the replace the cover with resistatant cover as shown in attached image.
cables. corrosion resistant
cover.

8. Cleaning of Martech to clean all


fittings. electrical fittings.

Leveling of data Data contractor to


sockets. ensure that data socket
outlets are leveled with
other sockets.

Page 4 of 4
9. Cleaning of floor Martech to clean all NO IMAGE All Floor boxes have been cleaned and vaccumed and
boxes. floor boxes with are ready for use as per attached image.
vacuum cleaner.

10. Electrical Rooms, Martech/ main NO IMAGE Labeling of doors or electrical rooms with signage is not
Substation contractor to label all within the main contractor’s and subcontractors scope
the rooms. of works. However, these work can be done provided a
Where necessary site instruction is issued and a variation order is issued
provide Hazard sign once our quotation for the supply and installation of
signage and labeling is accepted.

General Comments;
 Testing and commissioning of all installations are pending. The contractor should ensurethat they provide all necessary instruments for tests.
 The contractor shall prepare handover documentations (certificate of compliance, operation and maintenance manuals, etc.). and once the tests are carried out andaccepted produce as-built
drawings.
Prepared by: Jamshid Yazahmeidi, Electrical Engineer

05th June 2024


Page 5 of 4

You might also like