2 Mahape
f Mahape
g Mahape
j Mahape
3 Mahape
c Mahape
i Mahape
k Mahape
l Mahape
4 Mahape
q Mahape
t Mahape
5 Mahape
6 4D
7 Interface
b Interface
8 Interface
9 Interface
10 Thane
11 Interface
12 Interface
13 Interface
15 Interface
16 Interface
MEP related R&M work of mumbai circle offices and MSC locations
Fire Fighting System & related work
Office Work
Supply and fixing of1150x740mm aluminium framing glass fixing louvers window in pantry
for concealing of MSC cables 1 Job
Supply and installation of table border patti. 15 Rmt
Supply and Installation of shutter outside the mahape main double glass door. 1 Nos
Washroom Refusrbuishment
Sink Cock Faucets Tap for Kitchen Sink/Basin Taps with Wall Flange & Teflon Tape
(Mark),SILVER, Medium 4 Nos
Supply and installation of pull-out drawers near basin sink for consumable material storage 6 Nos
Supply & Installation of waterproofing chemical for wall and ceiling slab by Dr. Fixit or
equivalent make, high performance polymer modified cementitious membrane. This 600 sqft
includes crack filling and 2 coats of chemical application
Brick work in super structure class designation- 105, above DPC level in mortar mix 1:4 (1
cement : 4 course sand) including all materials, labour and tools and plants etc. required for 3 Cu.m
proper completion of work with minimum 6-days curing.
Washroom work
Office Work
Workstation soft board cushion replacement 4650 Sqft
Washroom work
Common Area
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
5,281,345.00 1,491,785.00
Total 6,773,130.00