Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Stability Analysis in a Colombian Non-

Interconnected Zone with BESS and PV Systems in


Different Locations of a Recloser as Main
Protection
Luis Felipe Gaitán Cubides Juan David Gomez Ariza Luis Alberto Zapata Giraldo, M.Sc.
Ingeniería Especializada IEB S.A. Ingeniería Especializada IEB S.A. Ingeniería Especializada IEB S.A.
Universidad Pontificia Bolivariana Universidad Pontificia Bolivariana Medellín, Colombia
Medellín, Colombia Medellín, Colombia luis.zapata@ieb.co
luis.f.g@ieee.org juan.d.g@ieee.org

Jose de Jesus Jaramillo Serna, M.Sc. Jorge Wilson González Sánchez, Ph.D.
Ingeniería Especializada IEB S.A. Universidad Pontificia Bolivariana
Medellín, Colombia Medellín, Colombia
jose.jaramillo@ieb.co jorgew.gonzalez@upb.edu.co

Abstract— Various areas of Colombia meet their energy The reports available up to April 2022 show losses in the
needs from the generation of electricity with Diesel generators energy supply, but do not specify the faults that cause this type
since they are not connected to the National Interconnected of power outage. In addition, no information is found on the
System (SIN for its acronym in Spanish). In some of these areas, philosophy of protections in this type of network. A study that
generation systems have been installed from unconventional evidences the behavior of the protections of this kind of
sources, whose characteristics make them ideal power systems networks, arises as a necessity, to guarantee that, in the event
to propose and evaluate different protection strategies and of short circuits in some part of the system, the protection
schemes. Due to the importance of maintaining the electrical
devices manage to maintain the provision of energy in those
service in these populations, in this work the installation of a
areas of the country.
recloser in different parts of the system is proposed to increase
the reliability of the network in the event of failures in different For this reason, in this work the location of reclosers in the
parts of the distribution system and its stability is evaluated in power system of a NIZ is proposed to improve the reliability
the same way with the operation of these devices through RMS of the network. The content of this work is divided into several
simulations. sections. In Section II a brief summary of the characteristics
Keywords— Isolated Grid, Non-Interconnected Zone, of the reclosers is made and in Section III the details of the
Reclosers, Non-Conventional Sources of Renewable Energy, simulation of a NIZ and the short-circuit analysis in different
Stability. operating scenarios are specified. Subsequently, section IV
I. INTRODUCTION proposes the location of the reclosers, specifies the sequence
In Colombia, 80% of the electricity demand is met through of operation of these devices and the RMS analysis of their
the National Interconnected System (SIN), which covers operation. Finally, in Section V an analysis of the results
approximately 48% of the national territory. The populations obtained is carried out and in Section VI the conclusions of
found in 52% of the remaining territory meet their energy the work are presented.
needs from the operation of isolated generation units based on II. RECLOSER AS A PROTECTION DEVICE IN DISTRIBUTION
diesel [1]. These territories are called Non-Interconnected NETWORKS
Zones (NIZ) and correspond to municipalities, districts, towns
and villages that for different reasons are not connected to the In [5] they define the recloser as a protection device that
SIN[2]. combines the functions of detection, fault interruption and
reclosing. The main function of this device is to detect the
The Institute for the Planning and Promotion of Energy fault, clear it and try to restore the service automatically, in
Solutions for Non-Interconnected Areas (IPSE for its acronym such a way that the reliability conditions of the network are
in Spanish) is the entity in charge of implementing and improved. If the fault is permanent, the recloser must go
monitoring sustainable energy projects that allow access to through a predetermined sequence of opening and closing
electricity to the NIZ, promoting the use of non-conventional operations before locking in the open position.
energy sources (FNCE for its acronym in Spanish) as an
energy solution under criteria of efficient energy management In [6] point out that reclosers can eliminate approximately
[3]. These locations with FNCE represent a potential research 95% of power outages in overhead distribution systems, since
laboratory in microgrids and could provide lessons on most faults in these networks are temporary or transient and
integration with Distributed Energy Resources (DERs) in mostly last a few cycles or a few seconds; which means for
electrical distribution networks [1]. the network operator a reduction in maintenance costs.
IPSE has installed telemetry systems in 108 NIZ locations. A. Reclosers location and application criteria
From these localities there are daily measurements of active, The reclosers may be used in any part of the electrical
reactive and apparent energy consumption, power factor, system, as long as it is guaranteed that their design
hours of electricity service provision, average load curve by characteristics are ideal for the system requirements. Several
type of day of the week and average monthly load curve of authors have used power system indicators and the location of
these 108 localities with telemetry information, 10 have existing protection devices in the network, for the
diesel-solar hybrid generation systems [4].

XXX-X-XXXX-XXXX-X/XX/$XX.00 ©20XX IEEE


development of recloser location algorithms in mid and large The selection of the reclose delay depends on the nature of
networks [7] [8] [9]. the fault and the expected extinction time. For example, a
longer delay setting will reduce the chance of over tripping
In [6], [10] and [11] are indicated how one of the functions and automatic reclosing for intermittent faults.
of the recloser is to function as a disconnector for long circuits,
preventing outputs of the entire feeder in the event of a fault A delay time shorter than the intermittent fault time will
and also acting as protection against faults in the branches allow the recloser to reset, thus preventing lockout. Increasing
with important loads, derived from the main feeder. When the reset time on the recloser prevents excessive operations,
selecting a recloser, the operating sequence will be determined but could cause unwanted blocking operationsdeseadas [13].
by the network configuration, the type of loads associated with
it, and the characteristics of the other sectionalizing devices III. SIMULATION OF A COLOMBIAN NIZ
with which the recloser must coordinate. In [12], they point A. NIZ system Model
out the following recommendations for the selection of
reclosers in the network: The NIZ was modeled in DIgSILENT® PowerFactory
Software, corresponding to the electrical system of the towns
1. Identify the voltage level of the network. of Nazareth and Puerto Estrella, located in the municipality
2. Determine the maximum load current, anticipating the of Uribia, Guajira. This NIZ was selected because in addition
growth of the load on the network. to having diversified non-conventional energy sources, the
3. Determine the maximum symmetrical fault current at the system feeds two different populations. The information on
recloser location.
this system was taken from the latest telemetry report
4. Determine the minimum fault current at the end of the
available at the time of writing this paper [4] and is listed in
zone protected by the recloser.
5. From the chosen device, the coordination of protections Table I and in Fig. 2.
with the other devices in the circuit is performed. Table I. Modeled NIZ infrastructure. Source [4].
6. If various types of reclosers meet all the required Generation System
conditions, the flexibility of the recloser control should be Item Device Capacity Status
considered. 1 PV System 320 kWp Operating
364 kW / 659
2 SDMO Operating
Regarding the number of reclosers to be installed in a kVA
given distribution circuit, the general recommendation is not 600 kW / 455
3 CATERPILLAR Operating
to use more than those that can be effectively coordinated to kVA
BESS (480 batteries
guarantee their selective operation, in such way that the 4
3350 Ah 2V)
Operating
reliability of the distribution network is not affected [6] [12]. Transformers
Item Capacity Status
B. Sequence of Operation
1 300 kVA (MAGNETRON) Operating
In [6] it is pointed out that when a recloser detects a fault 2 300 kVA (RYMEL) Operating
in the system, this device must act quickly, in order to Loads
minimize the probability of damage to the distribution system. Number of
Item Population Capacity
The operating times of the first stage of recloser tripping Users
1 Nazareth 244
should be set at values that do not allow voltage drop. After 306,7 kW
2 Puerto Estrella 146
one or two fast operations, the recloser switches to a "slow"
tripping operation, which allows more time to clear
"persistent" faults and achieve with this combination of
tripping, a more effective coordination with other protection
devices of the system.
If after performing a reclosing sequence, the fault persists,
the recloser will remain open. In this situation, the fault must
be located and cleared, and the recloser closed. The typical
operating sequence can be seen in Fig. 1, with which the first
trip is intended to be as fast as possible, so as to prioritize the Fig. 2. Diagram of the NIZ of Uribia, Guajira. Source [4].
protection of both living beings and equipment that may be To determine the value of the power demand in the
affected by the fault. network, the power demand values by the NIZ from January
2020 to the last report available from IPSE were analyzed.
The power values identified in these reports are summarized
in Table II. The simulated model is shown in Fig. 3.
Table II. Telemetry Values in the NIZ of Uribia in La Guajira
Average Daily
Active Reactive Apparent Maximum
Power Service
Value Energy Energy Energy
Factor
Power
Performance
(kWh) (kVARh) (kVAh) (kW)
(h)
Fig. 1. Typical Reclosing Sequence. Source: [6]
Minimum 15660 7303 17279 0,89 103,4 3:51:00
On the other hand, reclosing attempts after the quick trip
are made more slowly, so that the protection devices closest Maximum 71218 22324 74635 0,97 306,7 13:49:00
to the fault (fuses or disconnectors) are given the opportunity Average 36872 14500 39718 0,92 223,7 8:51:43
to clear the fault. This criterion is extremely important to
improve the reliability of the network, due to the temporary or
transient nature of faults in distribution systems.
protection, however, existing generator protection models
can be used to represent time-delayed frequency and voltage
protection settings. [14].

Fig. 5. Schematic of the WECC Generic Model for Large-scale PV Plants.


Source: [15]
2) Battery Energy Storage System (BESS)
The WECC BESS Control System is used to control the
BESS. This model concentrates mainly on VSC controls for
frequency regulation, constant PQ control, constant power
Fig. 3. Schematic of the NIZ modeled in Powerfactory factor control and voltage regulation with droop
characteristic. [16][17][18].
B. Simulation Scenarios
For the development of this case study, two NIZ base
operating scenarios were considered for the analysis of load
flow and short circuits, which were determined according to
the actual operation of this electrical system documented
in [4].
1) Daytime Scenario (D)
In this scenario, the solar photovoltaic generation and the Fig. 6. Overall model structure of a BESS using WECC generic models.
battery group feed the two medium voltage circuits of Source: [18]
Nazareth and Puerto Estrella. On days with high levels of 3) Diesel Generation System
sunshine and low cloud cover, this scenario occurs from The TGOV1 control model is used for diesel generators.
6:00 A.M. to 5:00 P.M., but if during the day there are no This model is one of the simplest controls, where the different
good levels of sunshine or high cloud cover, this scenario electrical and mechanical behavior of the machine is
occurs from 6:00 A.M. to 3:00 P.M. represented. [19].
2) Night Scenario (N)
In this scenario, the 569 kVA diesel generator feeds the
two medium voltage circuits of Nazareth and Puerto Estrella.
This scenario occurs from 6:00 PM to 10:00 PM, on days with
high levels of sunshine and low cloud cover, but if during the
day there are no good levels of sunshine or high cloud cover,
this scenario occurs from 4:00 PM to 10:00 PM. After this
time, the power supply is cut off to save fuel. Fig. 4 shows
the average load curve of the NIZ. Fig. 7. Control model implemented in the simulation. Source: [19]
Finally, for the dispatch of the generation units during the
active simulation during Scenario D, an External Station
Controller is configured, which allows the parallel dispatch
of the photovoltaic system and the BESS, through the control
of the voltage level at the node where both units are
electrically connected and the distribution of reactive power,
which is performed according to the nominal power of the
units, resulting in a distribution of 66% for PV generation and
the remaining 33% for the BESS.
Fig. 4. Monthly Average Daily Load Curve in April 2021 (red) and April D. Assumptions
2022 (Blue). Source: [4].
Within the analysis performed, and based on the
C. Controls in the Generation Units information in Table II, the following assumptions were
On the other hand, different control models were included made:
in the simulation in the different generating units of the • For all loads a 0.97 power factor.
system. • Both the 244 loads of Puerto Estrella and the 146 loads
1) Photovoltaic System of Nazareth have a value of 0.78 kW.
The control with which the NIZ PV generation was • To model the electrical system of the two towns, 5
simulated is the WECC Large-scale PV Plant model, shown distribution transformers were placed for the town of
in Fig. 5. This model does not include inverter and plant Nazareth and 3 for Puerto Estrella; both of 45 kVA.
• Regardless of the simulation scenario, the demand will In DIgSILENT® PowerFactory Software, balanced RMS
be 306 kW, which is the maximum demand recorded simulations are performed, which consider the dynamics of
in the telemetry reports analyzed since January 2020 electromechanical, control and thermal devices [22].
and corresponds to the maximum demand presented in The simulated phenomena for study case 1 are shown in
August 2021. Table IV and for study case 2 are shown in Table V.
• The short-circuit data for all the transformers in the Table IV. Sequence of Operation Study Case 1.
model are taken from the Colombian Technical Event Time (s)
Standard on Transformers [20]. Simulation of the three-phase fault in
• The 455 kVA diesel generator is a backup generator 1 the primary node of the 300 kVA 5,2
that only comes into operation when the Caterpillar transformers.
2 Recloser opening 5,25
generator goes out of service. 3 Fault remains N/A
E. Short Circuit Analysis 4 Recloser closing 6,25
5 Recloser opening 6,3
In order to identify the short-circuit levels in the system, 6 Clear Fault 6,8
a short-circuit calculation is performed in the nodes of 7 Recloser closing 7,3
interest of the power system. Table III shows the results of Table V. Sequence of Operation Study Case 2.
this analysis. For this work, the "Complete Method", also Event Time (s)
known as superposition method, was used. This method is a 1
Simulation of the three-phase fault
5
development of DIgSILENT® PowerFactory and is used in the distribution circuit.
because it more faithfully reflects real short-circuit 2 Recloser opening 5,1
3 Fault remains N/A
conditions, which makes it ideal for application in operational 4 Recloser closing 6,1
analysis, such as those corresponding to electrical 5 Recloser opening 6,2
protections. 6 Clear Fault 6,7
7 Recloser closing 7,2
Table III. Short-circuit levels at both distribution and generation
nodes. V. ANALYSIS OF RESULTS
Voltage 3F [kA] 2F [kA] 2F-G [kA] 1F [kA]
Node [kV] Sc. D Sc. N Sc. D Sc. N Sc. D Sc. N Sc. D Sc. N A. Study Case 1
Generation
0,4 3,47 6,52 0,78 5,99 0,78 10,25 0,02 10,1
Node After the failure in the primary node of both 300 kVA
Puerto Estrella
13,2 0,08 0,12 0,02 0,11 0,12 0,16 0,04 0,16 transformers, the operation sequence seen in Table IV is
Circuit
Nazareth
executed in both scenarios, obtaining the following results.
13,2 0,08 0,12 0,02 0,11 0,12 0,16 0,04 0,16
Circuit
1) Daytime Scenario
IV. STABILITY ANALYSIS OF A RECLOSER AS A PROTECTIVE Fig. 8 shows the frequency of both the faulted node and
ELEMENT IN A NIZ the secondary of the distribution transformer to Nazareth. It
is evident that, at the time of the fault, the increase in the value
A. Recloser Location
of the system frequency is so high that the controllers of the
For the analysis of the operation of the recloser as a PV and BESS systems of the NIZ disconnect the generation
protection element within the NIZ, two case studies are of the circuit. Therefore, in this scenario, it is not appropriate
analyzed: to have the recloser connected at this point of the network.
1) Study case 1 (SC1)
In this study case, the recloser is located at the generation
output. Here we will analyze the behavior of the system in the
event of a fault in the primary node of both 300 kVA
transformers. Two recloser reclosures are simulated, in the
first one the fault is not cleared, the recloser recloses again
and then the fault is cleared.
2) Study case 2 (SC2)
In this study case, the recloser is located in the secondary Fig. 8. SC1-D Scenario Frequency
winding of the substation transformers. Here the behavior of 2) Night Scenario
the system in the event of a fault in the distribution circuit The upper part of Fig. 9 shows the frequency of the
will be evaluated. Two reclosing of the recloser are faulted node and the secondary of the distribution transformer
simulated, in the first one the fault is not cleared, the recloser to Nazareth, while the lower part shows the voltage and
recloses again and then the fault is cleared. frequency levels at the generator terminals. It is evidenced
B. RMS Simulations and Sequence of Operation that, after the first recloser closing at 6.25 s of the simulation,
In order to evaluate the system behavior in the two cases the observed frequency levels increase greatly, which would
of study mentioned above, an RMS simulation is performed, cause the protections to trip and the circuit to disconnect.
with the objective of identifying the changes in the power, Therefore, in this scenario it is not appropriate to have the
voltage and frequency variables of the system. In addition, recloser connected at this point of the network.
this type of simulations allows modeling short-circuit
contingencies in an outstanding way [21].
Fig. 9. SC1-N Scenario Frequency and Voltage Fig. 11. SC1-N Scenario Frequency and Voltage

B. Study Case 2 VI. CONCLUSIONS


After the fault occurs in the secondary winding of the The recloser is a protection device that offers advantages
transformer secondary winding of the distribution circuit of and benefits that could improve the reliability of a NIZ in the
the Puerto Estrella population and the operation sequence seen presence of electrical faults in the protected circuit, but this
in Table V is executed in both scenarios, obtaining the depends on the correct location of the devices in the power
following results.
system. In the stability analysis carried out in this work, it was
1) Daytime Scenario
evidenced that when placing the recloser at the generation
Fig. 10 shows the voltage and frequency in both the
output, with its tripping, very high frequency and voltage
secondary winding of the Nazareth 300 kVA distribution
levels are observed in both simulation scenarios, which
transformer and the common node of the generation units. It
translates into the disconnection of the devices before the
is observed that, although there is a drop in the voltage at the
tripping of the control and protection systems.
common node connecting the generators during recloser
However, when located in the distribution circuits of the
operations, the frequency value at that node remains stable.
network, a better behavior is observed in the Day scenario,
Similarly, during the recloser operations, the voltage and
which is the scenario of longer operation time in the system,
frequency drop in the circuit is observed, but on this occasion,
and where it is identified that after the recloser trip, the power
there is no total de-energization of the circuit.
system continues to operate.
VII. ACKNOWLEDGMENT
The authors would like to thank the engineer Gustavo
Alonso Gutierrez Rodriguez for his advice during the
development of this article.
REFERENCES
[1] D. López-García, A. Arango-Manrique, and S. X. Carvajal-
Quintero, “Integration of distributed energy resources in isolated
microgrids: the Colombian paradigm,” TecnoLógicas, vol. 21, no.
42, pp. 13–30, 2018, doi: 10.22430/22565337.774.
[2] Congreso de la República de Colombia, “Ley 1715 de 2014,” D.
Of., p. 104, 2014.
[3] Presidencia de la República, “Ministerio de minas y energía
decreto número 257 de 2004 28 de enero de 2004,” 2004.
[4] IPSE, BOLETÍN MENSUAL DE OPERACIÓN DE
LOCALIDADES CON TELEMETRÍA CNM-IPSE - ABRIL 2022.
Fig. 10. SC2-D Scenario Frequency Bogota, 2022.
[5] IEEE Standard Association, IEEE Guide for Protective Relay
2) Night Scenario Applications Applications to Distribution Lines, no. February.
The upper part of Fig. 11 shows the voltage and frequency 2007.
both in the secondary winding of the 300 kVA distribution [6] Z. Castrillón and H. Will, Coordinación de protecciones en
sistemas de distribución de energía, Primera Ed. Medellin:
transformer of Nazareth and in the common node of the Empresas Publicas de Medellin EPM, 2011.
generation units. It is evidenced that, after the recloser [7] S. Jamali and H. Shateri, “Optimal siting of recloser and
opening at 5.1s the observed frequency levels increase greatly sectionalizers to reduce non-distributed energy,” Proc. IEEE
and after the closing process (6.1s) and reopening (6.2s) they Power Eng. Soc. Transm. Distrib. Conf., vol. 2005, pp. 1–6, 2005,
doi: 10.1109/TDC.2005.1547113.
reach even higher levels, which would cause the protections [8] A. I. Karpov and D. A. Akimov, “Integral indicators improvement
to trip and the circuit to disconnect. (SAIFI) of power supply reliability in electric distribution systems
For this reason, in this scenario it is not appropriate to based on reclosers placement optimization,” Proc. 2018 IEEE
have the recloser connected at this point of the network. Conf. Russ. Young Res. Electr. Electron. Eng. ElConRus 2018, vol.
2018-January, pp. 663–666, 2018, doi:
10.1109/EIConRus.2018.8317182.
[9] J. W. Gonzalez Sanchez, “Optimization of Reclosers Placement in
Distribution Networks to Improve Service Quality Indices,” IEEE
Lat. Am. Trans., vol. 20, no. 2, pp. 241–249, 2022, doi:
10.1109/TLA.2022.9661463.
[10] S. Ramírez Castaño, Protección de Sistemas Eléctricos, vol.
Primera Ed. Manizales: Universidad Nacional de Colombia, 2014.
[11] IEEE Standard Association, IEEE Guide for Automatic Reclosing
of Circuit Breakers for AC Distribution and Transmission Lines,
vol. 2012, no. July. 2012.
[12] IEEE Standard Association, IEEE Standard Guide for the
Application , Operation , and Maintenance of Automatic Circuit
Reclosers. 1973.
[13] J. Burke, “Hard To Find Information About,” Current, vol. 1,
2002, [Online]. Available:
http://www.ieso.ca/imoweb/pubs/caa/CAA_SIAReport_2007-
281.pdf.
[14] WECC Modeling and Validation WorkGroup, WECC Solar
Photovoltaic Power Plant Modeling and Validation Guideline.
2019.
[15] WECC REMTF, “Generic Models (PV Plants),” 2019.
https://www.esig.energy/wiki-main-page/generic-models-pv-
plants/#WECC_Generic_Model_for_Large-scale_PV_Plants
(accessed Jun. 15, 2022).
[16] WECC Renewable Energy Modeling Task Force, WECC Battery
Storage Dynamic Modeling Guideline. 2016.
[17] F. Calero, C. A. Canizares, and K. Bhattacharya, “Dynamic
Modeling of Battery Energy Storage and Applications in
Transmission Systems,” IEEE Trans. Smart Grid, vol. 12, no. 1,
pp. 589–598, 2021, doi: 10.1109/TSG.2020.3016298.
[18] X. Xu, M. Bishop, O. Donna G, and H. Chen, “Application and
modeling of battery energy storage in power systems,” CSEE J.
Power Energy Syst., vol. 2, no. 3, pp. 82–90, 2016, doi:
10.17775/cseejpes.2016.00039.
[19] IEEE Power & Energy Society, “Dynamic Models for Turbine-
Governors in Power System Studies,” Tech. Rep. PES-TR1, pp. 1–
117, 2013, [Online]. Available: http://sites.ieee.org/fw-
pes/files/2013/01/PES_TR1.pdf.
[20] Instituto Colombiano De Normas Técnicas Y Certificación, “NTC
819. Transformadores trifásicos autorrefrigerados y sumergidos en
líquido. Corriente sin carga, pérdidas y tensión de cortocircuito,”
p. 9, 1995.
[21] L. Steinhäuser, M. Coumont, S. Weck, and J. Hanson,
“Comparison of RMS and EMT models of converter-interfaced
distributed generation units regarding analysis of short-term
voltage stability,” NEIS 2019 - Conf. Sustain. Energy Supply
Energy Storage Syst., pp. 31–36, 2019.
[22] DIgSILENT GmbH, DIgSILENT PowerFactory 2021 User
Manual. DIgSILENT GmbH, 2021.

You might also like