CONSTRUCTION AND ENVIRONMENTAL PERMITTING PROCEDURES AND FORMALITIES

COMPANY: VVSR DATE: FEBRUARY 09, 2024 ATN TO: MR. HARSHA KARETI LOCATION: VILLA VARANDA IN
TULUM QUINTANA ROO WORK: MARBLE SWIMMING POOL COVERING

NUM CODE DESCRIPTION UNIT QUANTITY Unit Price TOTAL

001 MARBLE IN SWIMMING POOL

01 MARML01 SUPPLY OF TRAVERTINE MARBLE PUEBLA FIORITO M2 200 $ 1,150.00 $ 230,000.00


SANDBLASTED FINISH. 0.35 X 1.00 X 0.01 MTS.
OF FIRST LINE. INCLUDES: CEMIX ADHESIVE, PEGAMIX
FLOORS AND MARBLE, GROUT AND FINAL SEALER.
02 MARML02 PLACEMENT (LABOR) AND HABILITATION OF MARBLE IN M2 200 $ 855.00 $ 171,000.00
SWIMMING POOL INCLUDES: CUTS, LABOR, 1CM THICK TILE
ADHESIVE, MODULATIONS, HAULING AND LIGHT TOOLS.
03 MARML03 HAND FORGED FINISH TILE FOR SWIMMING POOL EDGES. M2 80.9 $ 376.00 $ 30,418.00
INCLUDES: CUTS, LABOR, 1 CM THICK TILE ADHESIVE,
MODULATIONS, HAULING AND LIGHT TOOLS.

TOTAL MARBLE IN SWIMMING POOL $431,418.40

TOTAL: FOUR HUNDRED AND THIRTY-ONE THOUSAND, FOUR HUNDRED, AND EIGHTEEN PESOS 40/100.

CONDITIONS:
* Form of payment: 60% IN ADVANCE PAYMENT - 30% AGAINST PROGRESS OF WORK - 10% AGAINST DELIVERY.
* Time of delivery of the material on site: 4 weeks from the date of the advance payment.
* Time of delivery of the works: 3 weeks from the beginning of the works.
* Duration of the quotation: 30 days
* This quotation includes all freight for transportation of material, hauling, unloading of material, and labor
* This quotation is made with cash payment prices; if the payment would be made via transfer, 16% VAT would have to be added.
The above, for tax issues ruled by the Tax Administration Service in México (SAT)