Lorry Crane 01.04.2024

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


TICK (√) – ROUTINELIFT NON–ROUTINE LIFT
CONTRACTOR: RICHEE ENGINEERING ENTERPRISE PTE LTD LM NO: LM924439K LM EXPIRY DATE (LTA): 30/07/2023

LP Reference No. GBWFJV 2024 - 01 Start Date - Expiry Date 30/03/2024 – 29/04/2024

IMPORTANT:
 Lifting Plan (LP) shall be submitted to GBWFJV CR111 Lifting Engineer for review at least 24 HOURS IN ADVANCE.
 Method of Statement Title: MOS No. ________________________
 Temporary Traffic Arrangements / Lane Closure required? YES NO TCP No. ________________________
 For all USED Materials, Machineries or Equipment as LOAD to be lifted to substances resided in them (such as oil, residue, etc.).
 Without a written consent by GBWFJV CR111 Lifting Engineer, and approval by GBWFJV CR111 Management, deviation of LP (from the
Approved one) is strictly NOT ALLOWED

Tick (√)
No. Checklist Remarks by GBWFJV LE
YES NO N.A.
Have the Approved Crane Contractor and the Contractor managing the lift
01
been determined? √
Have all clear copies of LM Cert, LG/LA Certs, Load Chart, Insurance Cert and
02
latest Service Record been attached? √
Are there adequate numbers of manpower resources to carry out the Lifting
03
Op comfortably and without undue pressure? √
Have all clear copies of the Involved Personnel relevant certificates, LOAs
04
and/or Undertaking Letter been attached? √
Has the Mean of Communication for the Lifting Op been determined and
05
agreed by all Involved Personnel? √
Have the details of Ground Bearing Capacity been indicated, and the COS been
06
attached? √
Have the required Manufacturer’s Design or PE’s Design with COS of the Load’s
07
Lifting Lug(s) been attached? √
Have the description of each Load to be lifted been indicated, and the Safety
08
Factor of the LM been calculated? √
Have the Rigging Method(s) been specifically shown, and the details of
09
measurements been indicated? √
Have all the LG/LA to be used been determined, and all clear copies of their
10
valid certificates been attached? √

Description Name Designation Signature Date

Prepared by LIFTING SUPERVISOR

Acknowledged by CM/DPM/PM

Reviewed by GBWFJV LIFTING ENGINEER

Vetted by GBWFJV WSHC / WSHO

Approved by GBWFJV CM /PM/PD

Rev_01 1
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


A – Details of Contractor(s) Involved – Check MOM’s website for the List of Approved Crane Contractor.

Approved Crane Contractor (ACC) RICHEE

Contractor Managing Lifting Activity / GBWFJV PIC

B – Details of Lifting Machine (LM) – Attach clear copies of LM Certificate / Load Chart / Insurance Certificate / Latest Service Report.

Brand / Model of Crawler Crane

Date of Print (P) & Expiry (E) of (P) – 12/12/2023


LM924439K
LM Certificate Number Certification (E) – 11/12/2024
Maximum SWL as certified in the LM Maximum Work Radius (MH) – 16.5M
9500 KG
Certificate (Main Hook / Aux Hook) (AH) –
Maximum Boom Length / Jib (B) – 16.55M Maximum SWL at Maximum (MH) – 1645 KG

Length as stated in LM Cert (J) – N.A. Radius (Main Hook / Aux H) (AH) –
Weight / SWL of MAIN HOOK (WT)_________/________(SWL) Total Counterweights to be

Weight / SWL of AUX HOOK (WT)_________/________(SWL) installed on LM


Wind Speed Monitoring ANEMOMETER Maximum In-Service Wind

N.A. Speed for LM

C – Details of Involved Personnel – Attach clear copies of all relevant certificates / proof of competencies.

Day Shift Night Shift


Designation Name Work Exp. Designation Name Work Exp.
OPERATOR SAW SEONG CHUAN 13 YEARS OPERATOR YEARS
MOLLA IMRAN 3 YEARS
LIFTING SUPERVISOR AHMED MD ATIQUE 3 YEARS LIFTING SUPERVISOR YEARS
JEGADEESAN KUMAR 2 YEARS
RIGGER RIGGER YEARS
SIGNALMAN SIGNALMAN YEARS
BANKSMAN BANKSMAN YEARS
SITE PIC BISWAS TAFIQUL SITE PIC YEARS

D – Means of Communication – To be determined and agreed by all Involved Personnel for the lifting operations.

OPEN LIFTING / STANDARD HAND SIGNALS BLIND LIFTING / USE OF WALKIE-TALKIES


OTHERS (clarify) –

Rev_01
2
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


E – Details of Ground Bearing – Refer to LM’s Ops Manual & Site’s Max Permissible Ground Pressure and/or attach COS as evidence.

Front 7.8m
Outrigger Dimension Outrigger Pressure (OP) 3.62T
Back 5.72m
Area of Base Plate / Crane Mats 1M X 1M Force= OP x Gravity 35.5KN

Pressure = Force ÷ Area 35.5KN/Sqm Max Permissible Pressure @ Site 100Kpa


Plan View of Actual Site location & LM positioning within the ‘Fatal / Collapse Zone’

ESS LOCATION

3
Rev_01
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


F – Description of the Load to be Lifted – Attach evidence of PE Design & COS for any lifting lug fabricated on the Load.
Item:1. I-Beam Loading / UnLoading

Centra of Gravity Dimension of I-Beam :


Obvious / Estimated / Calculated 350mm x 175mm x 10500mm

Max. Weight Weight Weight of Total Max. Max. Safe Corresponding Crane Safety
SWL of of Load of Hook Lifting Weight Boom Radius (m) SWL Capacity Factor
LM Block Gear Length Load Usage
(m) Chart

9500Kg 1000Kg 50Kg 20Kg 1070Kg 16.55m 16.55m 1645Kg 65.05% 1.537

Weight of Lifting Safety Factor @ Angle of


Sling Capacity Rigging Method
Gear 68°
3” x 6M webbing sling 3T
Single Chocker Using Webbing Sling 12.5Kg (Each) 2.78 x 2 = 5.56
– 2 nos

Rev_01 4
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


F – Description of the Load to be Lifted – Attach evidence of PE Design & COS for any lifting lug fabricated on the Load.
Item:1. Pipe Loading / UnLoading

Centra of Gravity Dimension of Pipe : 6mL


Obvious / Estimated / Calculated 1 bundle – 1.0Ton

Max. Weight Weight Weight of Total Max. Max. Safe Corresponding Crane Safety
SWL of of Load of Hook Lifting Weight Boom Radius (m) SWL Capacity Factor
LM Block Gear Length Load Usage
(m) Chart

9500Kg 1000Kg 50Kg 20Kg 1070Kg 16.55m 16.55m 1645Kg 65.05% 1.537

Weight of Lifting Safety Factor @ Angle of


Sling Capacity Rigging Method
Gear 68°
3” x 6M webbing sling 3T
Single Chocker Using Webbing Sling 12.5Kg (Each) 2 x 2.91 = 5.82
– 2 nos

Weight of Lifting Safety Factor @ Angle of


Sling Capacity Rigging Method
Gear 68°
6.5T – Pin Shackle – 2 nos Single Chocker Using Webbing Sling 12.5Kg (Each) 2 x 6.305 = 12.61

Rev_01 5
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


F – Description of the Load to be Lifted – Attach evidence of PE Design & COS for any lifting lug fabricated on the Load.
Item:1. Panel Loading / UnLoading

Centra of Gravity Dimension of Pipe :


Obvious / Estimated / Calculated 2.0m L x 1.0m W x 1.9m ht

Max. Weight Weight Weight of Total Max. Max. Safe Corresponding Crane Safety
SWL of of Load of Hook Lifting Weight Boom Radius (m) SWL Capacity Factor
LM Block Gear Length Load Usage
(m) Chart

9500Kg 1000Kg 50Kg 20Kg 1070Kg 16.55m 16.55m 1645Kg 65.05% 1.537

Weight of Lifting Safety Factor @ Angle of


Sling Capacity Rigging Method
Gear 68°
3” x 6M webbing sling 3T
Single Chocker Using Webbing Sling 12.5Kg (Each) 2 x 2.988 = 5.976
– 2 nos

Weight of Lifting Safety Factor @ Angle of


Sling Capacity Rigging Method
Gear 68°
6.5T – Pin Shackle – 2 nos Single Chocker Using Webbing Sling 12.5Kg (Each) 2 x 6.474 = 12.948

Rev_01 6
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


G - Summary of LGS to be used – Attach clear copies of relevant certificates for all the LGs / Las to be used.

S/No. Description of LG (Example: 3M – Chain Sling) SWL (Kg) LG No. Date of Inspection Owner

20

Rev_01 7
CR111- Design & Construction of Defu Station & Tunnels

LIFTING PLAN (LP) –LORRY CRANE


H – Summary of Lifting Plan

S/No. Description of Material Size of Material Max. Weight of Material Safety Factor

01 I-Beam – 2 Nos 350mm x 175mm x 10.5m 500Kg x 2 = 1000Kg 1.537

02 Pipe Bundle 6m L 1000Kg 1.537

03 Panel Bundle 2.0m x 1.0m x 1.9m 1000Kg 1.537

04

05

06

07

08

09

10

11

12

13

14

15

16

17

18

19

20

8
Rev_01

You might also like