SECTION A – PRELIMINARIES (Cont’d)

3. TENDER AND SUB-CONTRACT (Cont’d)

3.34 Sub-Contractor’s Claims for Extras

The Sub-Contractor shall send to the Main Contractor (copied to the Architect and
Quantity Surveyor) once in every month an account giving particulars (as full and detailed
as possible) of all claims for any extension of time or additional expense to which the
Sub-Contractor may consider himself entitled and of all extra or additional work contained
in Architect’s Instructions issued during the preceding month.

No consideration will be given to any claim for extension of time or for payment for any
such additional expense or extra or additional work which has not been made within 30
days to enable the circumstances and reasons for extensions or the additional expense
to be ascertained and evaluated.

3.35 Sub-Contractor’s Expenses in Connection with Variations and Settlement of Accounts

The Employer or the Main Contractor will not be liable for any expense incurred by the
Sub-Contractor in connection with the measurement of variations or the adjustment and
settlement of accounts.