AE Metrocycle World Corporation
NOTICE TO PROCEED
March 10, 2021
Mr. Gilberto Bermardo Landayan
GBL-R Builders Design and Trading
388 Aquino St. Cutcut, Guiguinto Bulacan Region 3, (Central Luzon)
ProjectName: — TCM STO. NINO
Scope of Works: INTERIOR RENOVATION
This is to nofify you to commence the INTERIOR RENOVATION of TCM STO. NINO
Branch with your Official Day 1 on March 15, 2021. Contract Duration is FORTY
FIVE (45) working days excluding Sundays and Holidays with the Completion
Date on May 5, 2021 .(Any changes on the schedule shall be agreed upon by
both parties).
Please be reminded that in the event the project is not completed within the
aforesaid period of time at no fault to Metrocycle World Corporation,
Metrocycle World Corporation,. is entitled and shall have the right to deduct
from any sum to become due to GBL-R Builders Design and Trading
the amount equivalent to 1/10 of One Percent of the Agreed Coniract Amount
for every working day of delay as LIQUIDATED DAMAGES. and not by way of
penalty.AE Metrocycle World Corporation
The Agreed Contract Amount isT EIGHT HUNDRED FIFTY THOUSAND PESOS ONLY
{PH 850,000.00 )
INTERIOR RENOVATION OF TCM STO. NINO Php 850,000.00
GRAND TOTAL Php 850,000.00
Please acknowledge receipt and acceptance of this notice by signing both
copies in the space provided below. Keep one copy and retumn the other to.
Metrocycle World Corporation.
Signed:
Engr. John Matthew Ang f. Gilberto Bernafao Landayan
Assistant Project Manager GBL-R Builders Design and Trading