Professional Documents
Culture Documents
G024 Latrine Pit Excavation Booklet
G024 Latrine Pit Excavation Booklet
Alternatively, tailor-make a
programme from our wide range of
stand-alone modules to suit your
particular professional development
requirements.
Water, Engineering and Development Centre
Or you may prefer to invite us to
School of Civil and Building Engineering
collaborate with you to devise a
Loughborough University
programme especially for your staff.
Leicestershire LE11 3TU UK
Go straight to details about one of our
T: + 44 (0) 1509 222885 Linkedin: WEDC UK learning opportunities.
E: wedc@lboro.ac.uk Twitter: wedcuk
W: wedc.lboro.ac.uk YouTube: wedclboro
8 1
Pit excavation
Pits are usually dug by hand. Great care must be taken to protect the workers from pit
collapse. When soils are loose or likely to collapse the pit walls must have temporary
supports until a lining can be constructed. There must always be one person at the
surface and at the top of the excavation to help in case of an accident.
0.5m minimum
from the base (Figures 1 & 2). If the soil Pit lining
is very loose, the sides of the excavation
should be sloped (wider at the top than Open joints in lining for
leaching liquid wastes
at the base) to prevent them collapsing
into the hole whilst the lining is being
constructed.
Deep pits
Unlined pits
2t
Even pits in firm, self-supporting soils Foundation of Sand or
concrete blocks gravel fill
must be lined for the top 0.5m - 1.0m. or bricks
Construct as follows:
not lined then pit latrine excavations will Table 1. Soil types and pit lining
Foundations
Sandbag pit lining in emergencies not require lining either.
Nearly all linings need a foundation
to prevent the lining sinking into the In Kenya and Sudan, sandbags have In fact the process of excavating a pit is Soil types that Soil types that do
ground below. In firm soils a simple pad been used to line pits in unstable similar to the process of digging a well. require lining not require lining
foundation about three times the width soils in refugee and internally-
In the absence of any other information Soft sands and Soils with a
of the linings is sufficient (see Figure 7a). displaced people camps. These were
the suggestions given in Table 1 may gravels significant clay
The foundation is usually made of the found to be cheaper, more durable
help. content*
same material as the lining. and more stable than oil-drum
liners that had been used previously. Lining material
In soft ground a thicker foundation may Unconsolidated Most consolidated
Sandbags are placed within the The pit can be lined using any material
be needed. Cover the base with a 10 to soils sedimentary rocks
circular pit. In areas of shallow that is strong enough to prevent the walls
15cm layer of compacted mixed stone (loose) (strongly bonded)
groundwater, cement was added to of the pit from collapse, can support the
and construct the foundation on that (see
the sand mix to improve stability. weight of the structure above, and is
Figure 7b). Filled land Soils with a high
A dry mix was used when the bags durable enough to ensure that it will last proportion of iron
When only partially lining the pit, leave a were first filled and a few buckets of for as long as the pit will be in use. oxides (laterites)
step in the pit wall on which to build the water were poured over them once
foundation (see Figure 7c). the bags were installed in the pit. Common lining materials include: Compressed
• Local stone, burnt bricks, concrete mudstones and
Dome shaped shales
blocks, soil/cement blocks
w concrete slab
(1:2:3)
• Termite resistent timber * Soils with a high clay content can change
1.5m Ø
w their stability with soil moisture content. The
Bamboo and cane should only be used if characteristics of the soil when it is excavated may
3w a pit is intended to have a very short life change as the soil dries out.
Compacted mixed stone
(less than 2 years). There is even more uncertainty if the soil is subject
(a) (b)
to periodic wetting and drying, for example, when
Jointing the water table rises and falls at different times of
No matter what type of lining is used, the year.
the top 0.5m of the pit should be fully
3.4m
Important
1.3m
Pits that are likely to be emptied and re-used should always be fully lined.
(c) Sand bag lining The pit lining should extend at least 10cm above ground level. This will help
142mm thick
Figure 7. Foundations prevent surface water getting in the pit.
4 5
of support. The sealed ring serves a Brick, blockwork and stone Thin linings
number of purposes: Thin linings such as old oil drums are
linings
not strong enough to carry the weight of
• it supports the weak soils that are Linings made of brick, blockwork or
a floor slab or superstructure without
found close to the surface; stone are built up from the foundations.
bending or breaking. They should be
With deep pits it is important to allow
• it provides a foundation for the cover strengthened at the top by a ring beam
time for the cement mortar to gain
slab and superstructure above; and such as the one shown in Figure 6.
strength before the space behind the
• it prevents surface water and lining is filled to prevent deformation of Corbelled
burrowing animals (rats, mice, the lining. Again, with the exception of brickwork
rabbits etc.) from entering the pit. the first 0.5m – 1.0m, some joints are left
unmortared to allow some infiltration of
Below the sealed ring, the lining must
the liquid into the soil.
be porous so that any liquid wastes can
percolate into the surrounding soils. A
porous lining can be made by leaving Corbelling
some of the vertical joints in brick and If the size of the pit is reduced as it
blockwork unmortared or leaving holes in approaches the surface then the size of
continuous linings of concrete or clay. the cover slab can also be reduced. This
Perspective view
can be achieved by ‘corbelling’ the lining.
A large number of small holes is better Figure 5. Pit with corbelled lining
than a small number of big ones. Big The pit lining is constructed in the
holes may allow the soil behind the lining shape of a dome either using brick or
to fall into the pit, producing voids that blockwork, concrete or ferrocement Lining bent Space between
could cause the pit to collapse. This (see Figure 5). The method reduces the outwards to key MJOJOHmMMFEXJUI
into concrete cement mortar
information holds true for all pit latrines quantity of lining material required as
except raised pits without soil mounds. In well as the size of the coverslab. However
this case the lining must be fully sealed it is a skilled process so experienced
above ground and for the first 0.5m below masons should be employed.
ground.
Pit lining
Behind the lining
Space between the back of the lining
and the excavated soil face must also
be filled. Where the lining is porous, the
space should be filled with a granular Section
material such as sand or gravel. Close
to the surface where the lining is sealed,
Figure 4. A porous section of lining gaps should be filled with compacted Figure 6. Thin linings require a ring beam
earth.