Financial Principles and Project Cost Management Assignment - Assignment

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

FINANCIAL PRINCIPLES AND PROJECT COST MANAGEMENT ASSIGNMENT

A. QUESTION 1

1. Answer is (b)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
150000.00 = +/- PV
12 = I/YR
50 = N
3826.91 = PMT

2. Answer is (e)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
15 = I/YR
20 = N
650 = +/- PMT
11439.56 = PV

3. Answer is (d)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
10 = I/YR
0 = CFj
200+/- = CFj
400 = CFj
600 = CFj
800+/- = CFj
400 = CFj
800 = CFj
SHIFT NPV = 753.09

4. Answer is (b)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
1500.00 = +/- PV
7 = I/YR

Financial Principles and Project Cost Management Assignment – EM / 059 Page 1


3=N
1837.56 = FV
FV – PV
1837.56 – 1500.00
= 337.56
337.56 = INTEREST EARNED

5. Answer is (a)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
INVESTMENT A
18000.00 = +/- PV
30000.00 = FV
5=N
10.76 = I/YR
INVESTMENT B
600.00 = +/- PV
3000.00 = FV
20 = N
8.38 = I/YR
INVESTMENT C
3400.00 = +/- PV
10000.00 = FV
10 = N
11.39 = I/YR
ALTERNATIVE INVESTMENT = 11%
THERFORE INVESTMENT C HAS HIGHER INTEREST

6. Answer is (d)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
2400.00 = +/- PMT
5=N
14 = I/YR
15864.25 = FV
15864.25 – 5000.00

Financial Principles and Project Cost Management Assignment – EM / 059 Page 2


= 10864.25
10864.25 = +/- PV
10 = I/YR
5=N
17496.98 = FV

7. Answer is (d)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
1000000.00 X 0.75 = 750000.00
750000.00 = +/-PV
12 = I/YR
20 = SHIFT x P/YR
8258.15 = PMT

8. Answer is (a)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
50000.00 = +/-CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
30520.98 = NPV
20.18 = IRR

9. Answer is (d)
If NPV is greater than zero then the IRR has to be greater than the cost of Capital
Therefore if Cost of Capital is 20% then the IRR rate has to be greater than 20%

Financial Principles and Project Cost Management Assignment – EM / 059 Page 3


10. Answer is (a)
Initial Investment is R500
Add Cash flows together from year 1 to 5 = R762
This is more than the initial investment
Add cash flows together from year 1 to 4 = R585
This is more than the initial investment
Add cash flows together from year 1 to 3 = R415
This is less than the initial investment
Add cash flows together from year 1 to 3 plus half of year 4 = R500
Therefore the payback period for Project A is 3.5 Years

11. Answer is (c)


1 SHIFT P/YR – This will set the calculator to 1 payment per year
1000 = +/-PV
3=N
10 = I/YR
1331.00 = FV
1000 = +/-PV
2.5 = N
10 = I/YR
1269.06 = FV
1331.00 – 1269.06
= 61.94

12. Answer is (c)


1 SHIFT P/YR – This will set the calculator to 1 payment per year
100 = +/-PV
200 = FV
8.7 = I/YR
8.31 = N

13. Answer is (b)


2 SHIFT P/YR – This will set the calculator to 2 payment per year
10000 = +/-PV
6 = I/YR
5 = SHIFT N

Financial Principles and Project Cost Management Assignment – EM / 059 Page 4


13439.16 = FV
1 SHIFT P/YR – This will set the calculator to 1 payment per year
13439.16 = FV
8 = I/YR
5=N
9149.47 = PV
9149.47 – 10000
= -853.53 Decrease in purchasing power

14. Answer is (a)


1 SHIFT P/YR – This will set the calculator to 1 payment per year
21144567 = +/-CFj0
2500000 = CFj1
2500000 = CFj2
2500000 = CFj3
2500000 = CFj4
2500000 = CFj5
2500000 = CFj6
2500000 = CFj7
2500000 = CFj8
2500000 = CFj9
2500000 = CFj10
15000000 = CFj11
18855433 = NPV
9.56 = IRR
Therefore the maximum amount that Company ABC should be willing to pay is R21144567

15. Answer is (c)


CASH FLOW ANALYSIS

PERIOD 0 1 2 3 4 5
COST OF ASSET -R 100,000.00
WEAR AND TEAR TAX
SAVINGS @ R 100,000.00 X
0.25 X 0.3 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00

TOTALS -R 100,000.00 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00

16. Answer is (a)

Financial Principles and Project Cost Management Assignment – EM / 059 Page 5


CASH FLOW ANALYSIS

PERIOD 0 1 2 3 4
COST OF NEW MACHINE -R 2,000,000.00
SAVING IN OPERATIONAL COSTS R 1,000,000.00 R 1,000,000.00 R 1,000,000.00 R 1,000,000.00
TAX ON SAVINGS @ 0.30 -R 300,000.00 -R 300,000.00 -R 300,000.00 -R 300,000.00
WEAR AND TEAR TAX SAVINGS @
R 2,000,000.00 X 0.25 X 0.3 R 150,000.00 R 150,000.00 R 150,000.00 R 150,000.00
SALE OF MACHINE R 120,000.00
TAX ON SALE OF MACHINE 0.30 -R 36,000.00

TOTALS -R 2,000,000.00 R 850,000.00 R 850,000.00 R 850,000.00 R 934,000.00

17. Answer is (c)


1 SHIFT P/YR – This will set the calculator to 1 payment per year
2000000 = +/-CFj0
8500000 = CFj1
8500000 = CFj2
8500000 = CFj3
9340000 = CFj4
1484000 = NPV
26.15 = IRR

18. Answer is (a)


1 SHIFT P/YR – This will set the calculator to 1 payment per year
100000000 = +/-PV
50 = N
10 = I/YR
10085917.40 = PMT
10000000 = Interest per year
= 10085917.40 + 10000000
= 20085917.40 Cost per Year
= 2000000 Units per Year
Therefore 20085917.40 / 2000000
= R 10.04 per Unit to cover the Cost per Year
= Breakeven Point

B. QUESTION 2

Financial Principles and Project Cost Management Assignment – EM / 059 Page 6


a.

1. Initial Investment

INITIAL COSTS

Initial Investment YR0


Purchase Price of new colour press -R 800,000.00
Installation cost of press -R 50,000.00
Increase in Working Capital R 120,000.00

TOTAL INITIAL COSTS -R 730,000.00

2. Net operating cash flows


NET OPERATING CASH FLOW ANALYSIS

PERIOD 0 1 2 3 4
Purchase Price of new colour press -R 800,000.00
Installation cost of press -R 50,000.00
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00 R 44,800.00 R 44,800.00 R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00
Profits R 250,000.00 R 270,000.00 R 300,000.00 R 330,000.00
Tax on Profits -R 70,000.00 -R 75,600.00 -R 84,000.00 -R 92,400.00
TOTALS -R 730,000.00 R 344,800.00 R 359,200.00 R 380,800.00 R 702,400.00

3. Terminal Cash Flows


TERMINAL CASH FLOW

PERIOD YR0
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00
Profits R 330,000.00
Tax on Profits -R 92,400.00
TOTALS R 702,400.00

b.
CASH FLOW ANALYSIS

Financial Principles and Project Cost Management Assignment – EM / 059 Page 7


NET OPERATING CASH FLOW ANALYSIS

PERIOD 0 1 2 3 4
Purchase Price of new colour press -R 800,000.00
Installation cost of press -R 50,000.00
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00 R 44,800.00 R 44,800.00 R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00
Profits R 250,000.00 R 270,000.00 R 300,000.00 R 330,000.00
Tax on Profits -R 70,000.00 -R 75,600.00 -R 84,000.00 -R 92,400.00
TOTALS -R 730,000.00 R 344,800.00 R 359,200.00 R 380,800.00 R 702,400.00

c.

1. NPV

1 SHIFT P/YR – This will set the calculator to 1 payment per year
730000 = +/-CFj0
344800 = CFj1
359200 = CFj2
380800 = CFj3
702400 = CFj4
1057200 = NPV

2. IRR

41.72 = IRR

3. Payback Period

PP = 2 (730000-704000)/380800

= 2 (26000)/380800

= 2 (0.68)

= 2.68

d. Based on the above calculations I would recommend the new press be acquired

C. QUESTION 3

Financial Principles and Project Cost Management Assignment – EM / 059 Page 8


a. Breakeven Sales Units per year
Selling Price per Unit (SP) = R900
Variable Cost per Unit (VC) = R300
Contribution (CON) = R600

Fixed Costs per Year (FC) = R 18 000 (thousands)


Current Sales Volume/Units (CS) = R 35 (thousands)

Sales (SP) = VC + FC + Profit (for breakeven use profit of zero)


900x = 300x+18000+0
600x = 18000
x = 18000/600
x = 30000 Units (BES)
Therefore the Breakeven Point is 30,000 Units

b. Margin of Safety
Margin of Safety (MOS) = (CS – BES) / CS
MOS = (35 – 30) / 35
MOS = 5/35
MOS = 0.14
MOS x 100 = 14.29%
This is the % by which current sales can drop before you start making a loss

c. Current Profit
Current Profit = CS x CON – FC
= 35 x R600 – 18000
= 21000 – 18000
= 3000
Therefore = R 3,000,000.00

How many units must be sold for operating profit of R6 million


Sales = VC + FC + Profit
900x = 300x + 18000 + 6000

Financial Principles and Project Cost Management Assignment – EM / 059 Page 9


600x = 24000
x = 24000/600
x = 40
Therefore = 40,000 Units

d. As per the above calculation in c. the Current Sales Profit is R3,000,000.00


To increase operating profit by 25% means that Current Profit should be
R3,750,000.00
How many units must be sold for operating profit of R3,750,000.00
Sales = VC + FC + Profit
900x = 300x + 18000 + 3750
600x = 21750
x = 21750/600
x = 36.25
Therefore = 36,250 Units is required to be sold

Financial Principles and Project Cost Management Assignment – EM / 059 Page 10

You might also like