Professional Documents
Culture Documents
Financial Principles and Project Cost Management Assignment - Assignment
Financial Principles and Project Cost Management Assignment - Assignment
Financial Principles and Project Cost Management Assignment - Assignment
A. QUESTION 1
1. Answer is (b)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
150000.00 = +/- PV
12 = I/YR
50 = N
3826.91 = PMT
2. Answer is (e)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
15 = I/YR
20 = N
650 = +/- PMT
11439.56 = PV
3. Answer is (d)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
10 = I/YR
0 = CFj
200+/- = CFj
400 = CFj
600 = CFj
800+/- = CFj
400 = CFj
800 = CFj
SHIFT NPV = 753.09
4. Answer is (b)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
1500.00 = +/- PV
7 = I/YR
5. Answer is (a)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
INVESTMENT A
18000.00 = +/- PV
30000.00 = FV
5=N
10.76 = I/YR
INVESTMENT B
600.00 = +/- PV
3000.00 = FV
20 = N
8.38 = I/YR
INVESTMENT C
3400.00 = +/- PV
10000.00 = FV
10 = N
11.39 = I/YR
ALTERNATIVE INVESTMENT = 11%
THERFORE INVESTMENT C HAS HIGHER INTEREST
6. Answer is (d)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
2400.00 = +/- PMT
5=N
14 = I/YR
15864.25 = FV
15864.25 – 5000.00
7. Answer is (d)
12 SHIFT P/YR – This will set the calculator to 12 payments per year
1000000.00 X 0.75 = 750000.00
750000.00 = +/-PV
12 = I/YR
20 = SHIFT x P/YR
8258.15 = PMT
8. Answer is (a)
1 SHIFT P/YR – This will set the calculator to 1 payment per year
50000.00 = +/-CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
12000.00 = CFj
30520.98 = NPV
20.18 = IRR
9. Answer is (d)
If NPV is greater than zero then the IRR has to be greater than the cost of Capital
Therefore if Cost of Capital is 20% then the IRR rate has to be greater than 20%
PERIOD 0 1 2 3 4 5
COST OF ASSET -R 100,000.00
WEAR AND TEAR TAX
SAVINGS @ R 100,000.00 X
0.25 X 0.3 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00 R 6,000.00
PERIOD 0 1 2 3 4
COST OF NEW MACHINE -R 2,000,000.00
SAVING IN OPERATIONAL COSTS R 1,000,000.00 R 1,000,000.00 R 1,000,000.00 R 1,000,000.00
TAX ON SAVINGS @ 0.30 -R 300,000.00 -R 300,000.00 -R 300,000.00 -R 300,000.00
WEAR AND TEAR TAX SAVINGS @
R 2,000,000.00 X 0.25 X 0.3 R 150,000.00 R 150,000.00 R 150,000.00 R 150,000.00
SALE OF MACHINE R 120,000.00
TAX ON SALE OF MACHINE 0.30 -R 36,000.00
B. QUESTION 2
1. Initial Investment
INITIAL COSTS
PERIOD 0 1 2 3 4
Purchase Price of new colour press -R 800,000.00
Installation cost of press -R 50,000.00
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00 R 44,800.00 R 44,800.00 R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00
Profits R 250,000.00 R 270,000.00 R 300,000.00 R 330,000.00
Tax on Profits -R 70,000.00 -R 75,600.00 -R 84,000.00 -R 92,400.00
TOTALS -R 730,000.00 R 344,800.00 R 359,200.00 R 380,800.00 R 702,400.00
PERIOD YR0
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00
Profits R 330,000.00
Tax on Profits -R 92,400.00
TOTALS R 702,400.00
b.
CASH FLOW ANALYSIS
PERIOD 0 1 2 3 4
Purchase Price of new colour press -R 800,000.00
Installation cost of press -R 50,000.00
Decpreciation Costs - Wear and Tear @
800000 x 0.20 x 0.28% R 44,800.00 R 44,800.00 R 44,800.00 R 44,800.00
Sale of Press R 300,000.00
Increase in Working Capital R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00 R 120,000.00
Profits R 250,000.00 R 270,000.00 R 300,000.00 R 330,000.00
Tax on Profits -R 70,000.00 -R 75,600.00 -R 84,000.00 -R 92,400.00
TOTALS -R 730,000.00 R 344,800.00 R 359,200.00 R 380,800.00 R 702,400.00
c.
1. NPV
1 SHIFT P/YR – This will set the calculator to 1 payment per year
730000 = +/-CFj0
344800 = CFj1
359200 = CFj2
380800 = CFj3
702400 = CFj4
1057200 = NPV
2. IRR
41.72 = IRR
3. Payback Period
PP = 2 (730000-704000)/380800
= 2 (26000)/380800
= 2 (0.68)
= 2.68
d. Based on the above calculations I would recommend the new press be acquired
C. QUESTION 3
b. Margin of Safety
Margin of Safety (MOS) = (CS – BES) / CS
MOS = (35 – 30) / 35
MOS = 5/35
MOS = 0.14
MOS x 100 = 14.29%
This is the % by which current sales can drop before you start making a loss
c. Current Profit
Current Profit = CS x CON – FC
= 35 x R600 – 18000
= 21000 – 18000
= 3000
Therefore = R 3,000,000.00