No. Kontrak 06.

A/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS
PEKERJAAN PERIODIC INSPECTION (PI) 1 TAHUN
Workscope
AND TROUBLESHOOTING BO-105 HR-1524
Progress Status 5,66%
Duration 120 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

5,66%
20,00%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)

No. Description Load


DAYS START FINISH SCHEDULE %
(%)

A/C Preliminary Check &


1 0,27% 1 10 Jun 2024 10 Jun 2024 Plan 0,27%
Document Check
13 Jun 2024 13 Jun 2024 Actual 0,27%
2 A/C Shipment / ferry out 1,09% 4 4 Jun 2024 7 Jun 2024 Plan 1,09%
10 Jun 2024 12 Jun 2024 Actual 1,09%
3 Purchasing Process (42 Items) 21,04% 77 4 Jun 2024 20 Aug 2024 Plan 21,04%
4 Jun 2024 Actual 4,29%
Periodical Inspection
4 22,68% 83 10 Jun 2024 31 Aug 2024 Plan 22,68%
1 Year
Actual 0,00%
5 Troubleshooting Phase 16,12% 59 18 Jun 2024 15 Aug 2024 Plan 16,12%
Actual 0,00%
Installation and rewiring engine
6 18,85% 69 24 Jun 2024 31 Aug 2024 Plan 18,85%
fire extinguisher
Actual 0,00%
Aircraft repainting +
7 8,47% 31 1 Aug 2024 31 Aug 2024 Plan 8,47%
Reweighing
Actual 0,00%
8 Functional Test on Ground 2,19% 8 4 Sep 2024 11 Sep 2024 Plan 2,19%
Actual 0,00%
Ground Run Maintenance
9 2,19% 8 11 Sep 2024 18 Sep 2024 Plan 2,19%
Flight Certification
Actual 0,00%
10 Maintenance Test Flight 2,19% 8 18 Sep 2024 25 Sep 2024 Plan 2,19%
Actual 0,00%
11 Track & Balance 4,10% 15 11 Sep 2024 25 Sep 2024 Plan 4,10%
Actual 0,00%
12 Certification 0,82% 3 25 Sep 2024 27 Sep 2024 Plan 0,82%
Actual 0,00%
No. Kontrak 06.E/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS

Workscope TROUBLESHOOTING BO-105 HR-1518

Progress Status 5,43%


Duration 180 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

20,00% 5,43%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)

No. Description Load


DAYS START FINISH Schedule %
(%)

A/C Preliminary Check &


1 0,24% 1 10 Jun 2024 10 Jun 2024 Plan 0,24%
Document Check
13 Jun 2024 13 Jun 2024 Actual 0,24%
2 A/C Shipment / ferry out 0,96% 4 4 Jun 2024 7 Jun 2024 Plan 0,96%
10 Jun 2024 12 Jun 2024 Actual 0,96%
Purchasing Process
3 24,46% 102 4 Jun 2024 13 Sep 2024 Plan 24,46%
(Qty, 19 Items)
4 Jun 2024 Actual 4,23%
4 Troubleshooting Phase 24,46% 102 18 Jun 2024 27 Sep 2024 Plan 24,46%
Actual 0,00%
Installation and rewiring
5 30,70% 128 26 Jun 2024 31 Oct 2024 Plan 30,70%
engine fire extinguisher
Actual 0,00%
Aircraft repainting +
6 7,43% 31 1 Oct 2024 31 Oct 2024 Plan 7,43%
Reweighing
Actual 0,00%
7 Functional Test on Ground 3,12% 13 1 Nov 2024 13 Nov 2024 Plan 3,12%
Actual 0,00%
Ground Run Maintenance
8 1,92% 8 13 Nov 2024 20 Nov 2024 Plan 1,92%
Flight Certification
Actual 0,00%
9 Maintenance Test Flight 2,16% 9 20 Nov 2024 28 Nov 2024 Plan 2,16%
Actual 0,00%
10 Track & Balance 3,84% 16 13 Nov 2024 28 Nov 2024 Plan 3,84%
Actual 0,00%
11 Certification 0,72% 3 28 Nov 2024 30 Nov 2024 Plan 0,72%
Actual 0,00%
No. Kontrak 06.D/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS

Workscope TROUBLESHOOTING BO-105 HR-1517

Progress Status 4,95%


Duration 120 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

20,00% 4,95%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)
1

NO. Description Load


DAYS START FINISH SCHEDULE %
(%)

A/C Preliminary Check &


1 0,28% 1 10 Jun 2024 10 Jun 2024 Plan 0,28%
Document Check
Actual 0,00%
2 A/C Shipment / ferry out 1,13% 4 4 Jun 2024 7 Jun 2024
Plan 1,13%
Actual 0,00%
3 Purchasing Process (10 Items) 28,90% 102 4 Jun 2024 13 Sep 2024 Plan 28,90%
4 Jun 2024 Actual 4,95%
Periodical Inspection
4 23,51% 83 10 Jun 2024 31 Aug 2024 Plan 23,51%
25 Fh
Actual 0,00%
5 Troubleshooting Phase 7,08% 25 18 Jun 2024 12 Jul 2024 Plan 7,08%
Actual 0,00%
Installation and rewiring engine
6 20,68% 73 26 Jun 2024 6 Sep 2024 Plan 20,68%
fire extinguisher
Actual 0,00%
7 Aircraft repainting + Reweighing 8,78% 31 1 Jul 2024 31 Jul 2024 Plan 8,78%
Actual 0,00%
8 Functional Test on Ground 2,55% 9 9 Sep 2024 17 Sep 2024 Plan 2,55%
Actual 0,00%
Ground Run Maintenance Flight
9 1,98% 7 17 Sep 2024 23 Sep 2024 Plan 1,98%
Certification
Actual 0,00%
10 Maintenance Test Flight 1,42% 5 23 Sep 2024 27 Sep 2024 Plan 1,42%
Actual 0,00%
11 Track & Balance 3,12% 11 17 Sep 2024 27 Sep 2024 Plan 3,12%
Actual 0,00%
12 Certification 0,57% 2 30 Sep 2024 1 Oct 2024 Plan 0,57%
Actual 0,00%
No. Kontrak 06.C/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS
PERIODIC INSPECTION (PI) 4 TAHUN BO-105
Workscope
HR-1522
Progress Status 4,89%
Duration 150 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

20,00% 4,89%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)

No. Description Load


DAYS START FINISH SCHEDULE %
(%)

1 A/C Shipment / ferry out 4,53% 19 3 Jun 2024 21 Jun 2024 Plan 4,53%
10 Jun 2024 Actual 0,36%
A/C Preliminary Check &
2 0,24% 1 24 Jun 2024 24 Jun 2024 Plan 0,24%
Document Check
Actual 0,00%
Purchasing Process
3 24,34% 102 3 Jun 2024 12 Sep 2024 Plan 24,34%
(Qty. 106 Items)
3 Jun 2024 Actual 4,53%
Periodical 4 Year Inspection
4 21,96% 92 1 Jul 2024 30 Sep 2024 Plan 21,96%
Phase
Actual 0,00%
Engine 500 FH/1 Thn
5 16,23% 68 1 Jul 2024 6 Sep 2024 Plan 16,23%
Inspecyion Phase
Actual 0,00%
6 Troubleshooting Phase 16,23% 68 15 Jul 2024 20 Sep 2024 Plan 16,23%
Actual 0,00%
7 Paint Stripping 5,73% 24 12 Aug 2024 4 Sep 2024 Plan 5,73%
Actual 0,00%
8 Weight & Balance 0,24% 1 1 Oct 2024 1 Oct 2024 Plan 0,24%
Actual 0,00%
9 Functional Test on Ground 1,91% 8 2 Oct 2024 9 Oct 2024 Plan 1,91%
Actual 0,00%
10 Track & Balance 3,58% 15 9 Oct 2024 23 Oct 2024 Plan 3,58%
Actual 0,00%
Ground Run Maintenance
11 1,91% 8 9 Oct 2024 16 Oct 2024 Plan 1,91%
Flight Certification
Actual 0,00%
12 Maintenance Test Flight 1,91% 8 16 Oct 2024 23 Oct 2024 Plan 1,91%
Actual 0,00%
13 Certification 1,19% 5 23 Oct 2024 27 Oct 2024 Plan 1,19%
Actual 0,00%
No. Kontrak 06.B/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS
PERIODIC INSPECTION (PI) 4 TAHUN
Workscope
BO-105 HR-1521
Progress Status 4,74%
Duration 170 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

20,00% 4,74%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress
(Anwar Al Irsyad)

No. Description Load


DAYS START FINISH SCHEDULE %
(%)

1 A/C Shipment / ferry out 3,65% 19 3 Jun 2024 21 Jun 2024 Plan 3,65%
Actual 0,00%
A/C Preliminary Check &
2 0,19% 1 24 Jun 2024 24 Jun 2024 Plan 0,19%
Document Check
Actual 0,00%
Purchasing Process
3 26,49% 138 3 Jun 2024 18 Oct 2024 Plan 26,49%
( Qty. 119 Items)
3 Jun 2024 Actual 4,74%
Periodical 4 Year Inspection
4 22,84% 119 1 Jul 2024 27 Oct 2024 Plan 22,84%
Phase
Actual 0,00%
Engine 500 FH/1 Thn
5 14,40% 75 1 Jul 2024 13 Sep 2024 Plan 14,40%
Inspecyion Phase
Actual 0,00%
6 Troubleshooting Phase 20,15% 105 15 Jul 2024 27 Oct 2024 Plan 20,15%
Actual 0,00%
7 Aircraft Painting 4,99% 26 9 Sep 2024 4 Oct 2024 Plan 4,99%
Actual 0,00%
8 Weight & Balance 0,19% 1 28 Oct 2024 28 Oct 2024 Plan 0,19%
Actual 0,00%
9 Functional Test on Ground 0,96% 5 28 Oct 2024 1 Nov 2024 Plan 0,96%
Actual 0,00%
10 Track & Balance 2,69% 14 1 Nov 2024 14 Nov 2024 Plan 2,69%
Actual 0,00%
Ground Run Maintenance
11 1,34% 7 1 Nov 2024 7 Nov 2024 Plan 1,34%
Flight Certification
Actual 0,00%
12 Maintenance Test Flight 1,54% 8 7 Nov 2024 14 Nov 2024 Plan 1,54%
Actual 0,00%
13 Certification 0,58% 3 14 Nov 2024 16 Nov 2024 Plan 0,58%
Actual 0,00%
No. Kontrak 04.B/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS
PENGADAAN SPARE PART TROUBLESHOOTING
Workscope
AW-139 HR-1301
Progress Status 52,38%
Duration 90 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
52,38%
PERCENTAGE

40,00%

20,00%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)

No. Description Load


DAYS START FINISH SCHEDULE %
(%)

Pengadaan Spare Parts

1 Component (Qty. 12 Ea) 100,00% 90 31 May 2024 28 Aug 2024 Plan 100,00%

31 May 2024 Actual 52,38%


No. Kontrak 04.C/PPK-04/SP-P/V/DSP-2024
Customer BASARNAS
PERIODIC INSPECTION (PI) 8 TAHUN
Workscope
AW-139 HR-1301
Progress Status 3,44%
Duration 180 Days
Status as of 13 June 2024

100,00%
100,00%

80,00%

60,00%
PERCENTAGE

40,00%

20,00% 3,44%

0,00%
Prepare By.

DATE
Plan Cumm. Progress Actual Cumm. Progress (Anwar Al Irsyad)

No. Description Load


DAYS START FINISH SCHEDULE %
(%)

A/C Preliminary Check &


1 0,24% 1 10 Jun 2024 10 Jun 2024 Plan 0,24%
Document Check
Actual 0,00%
2 A/C Shipment / ferry out 0,96% 4 4 Jun 2024 7 Jun 2024 Plan 0,96%
Actual 0,00%
Purchasing Process
3 24,46% 102 4 Jun 2024 13 Sep 2024 Plan 24,46%
( Qty. 61 Items)
4 Jun 2024 Actual 3,44%
4 Troubleshooting Phase 24,46% 102 18 Jun 2024 27 Sep 2024 Plan 24,46%
Actual 0,00%
Installation and rewiring
5 30,70% 128 26 Jun 2024 31 Oct 2024 Plan 30,70%
engine fire extinguisher
Actual 0,00%
Aircraft repainting +
6 7,43% 31 1 Oct 2024 31 Oct 2024 Plan 7,43%
Reweighing
Actual 0,00%
7 Functional Test on Ground 3,12% 13 1 Nov 2024 13 Nov 2024 Plan 3,12%
Actual 0,00%
Ground Run Maintenance
8 1,92% 8 13 Nov 2024 20 Nov 2024 Plan 1,92%
Flight Certification
Actual 0,00%
9 Maintenance Test Flight 2,16% 9 20 Nov 2024 28 Nov 2024 Plan 2,16%
Actual 0,00%
10 Track & Balance 3,84% 16 13 Nov 2024 28 Nov 2024 Plan 3,84%
Actual 0,00%
11 Certification 0,72% 3 28 Nov 2024 30 Nov 2024 Plan 0,72%
Actual 0,00%