(1library - Net) Method Statement For Installation of Transformer
(1library - Net) Method Statement For Installation of Transformer
:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 1 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 2 of 20
Document No. :
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 3 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 4 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 5 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 6 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 7 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 8 of 20
TABLE OF CONTENTS
1 Purpose…………………………………………………………………………….. 11
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 9 of 20
2 Scope of Work…………………………………………………………………….. 12
3 Responsible Personnel on Site..……………………………………………… 12
4 Storage…………………………………………………………….………………. 13
5 Pre-Installation…………………………………………………………………… 4
6 Installation………………………………………………………………………… 5
7 Reference Documents…………………………………………………………. 5
8 Safety……………………………………………………………………………… 6
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 10 of 20
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 11 of 20
1. Purpose
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 12 of 20
This method of statement covers the on-site installations of Dry type Transformer as
defined in the General Specification.
2. Scope of Work
This procedure will define the method to off-loading and installation to be used to
ensure that the transformers are correct and acceptable and shall conform to the
Contract Documents and Specification.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 13 of 20
4.1 Use Fork Lifts or Mobile Crane to off-load the transformers. Make sure that the capacity
of the fork lifts or mobile crane can carry the weight of the transformers.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 14 of 20
4.2 Off load the transformer on the designated off loading area. Proper care must be
observed during off loading to prevent unnecessary damage or dents on the
transformers.
4.3 Ensure that the transformers are properly protected and covered with tarpaulin.
5. Pre-Installation
5.1 All materials and documentation relevant to this particular section of works shall be
checked by the Construction Department prior to the commencement of works ensuring
that these are correct and approved type.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 15 of 20
5.2 Before any permanent works will continue, pre-inspection on all materials, tools and
access for installation to be carried out..
6. Installation
It has been presumed that all related civil works has been completed prior to transformer
installation.
6.1 Before the transformer will be delivered to site, ensure that the transformer railing is
fixed as per approved drawings and comply on municipality requirement.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 16 of 20
6.2 Move the transformers from the designated off-loading area or storage area using fork
lift and set them in position near to the transformer room. Make sure that the orientation
of the transformer with regards to the position of cable entries is correct.
6.3 Push in the transformers inside the transformer room. Set the transformer on their final
positions and make sure that they are properly secured and protected.
6.5 Conduct on site test for the transformer. Test shall include winding insulation resistance
test and shall conform to manufacturer’s recommendation and specification. All tests
must be recorded and conducted in the presence of Consultant by manufacturer testing
engineer.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 17 of 20
6.6 Dress and terminate the incoming and outgoing cables on the transformers. Ensure
that the cables were supported properly. Cable glands, lugs and termination kits shall
be approved type.
6.7 After termination works has been completed, clean the transformer cable box and
ensure that it is free from foreign materials and excess openings must be sealed off
and ensure that all the connections are properly tight and torque.
6.8 Raise Request for Inspection for the cable terminations and dressing.
6.9 Cover the cable boxes. Bolts and nuts must be tightened properly. Make sure that the
transformer room is clean and free from foreign materials.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 18 of 20
7. Reference Documents
8. Safety
`Brought you by udistinguish.com Contact us @ airgil@udistinguish.com
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 19 of 20
8.1 All safety precautions shall be followed as per approved safety plan & procedure.
Ensure all involved persons are aware of the same.
8.2 Ensure that tradesman will keep their working places clean and tidy.
PROJECT MANAGER
Doc. No.:
*INSERT CLIENT NAME HERE
REV.
*INSERT LOGO HERE *INSERT PROJECT NAME HERE Date: 03 -31- 2008
0
METHOD STATEMENT FOR INSTALLATION
OF TRANSFORMER Page No. : 20 of 20
PROJECT MANAGER