Professional Documents
Culture Documents
Arb 326 2022 29 01 2024 Interim Order
Arb 326 2022 29 01 2024 Interim Order
Arb 326 2022 29 01 2024 Interim Order
ARB-326-2022 1
ARB-326-2022
Reserved on 19.01.2024
Pronounced on 29.01.2024
ITD Cementation India Ltd.
vs.
Central Public Works Department, Govt. Of India
the Arbitration and Conciliation Act, 1996 (for short ‘the Act 1996’) read
Punjab and Haryana High Court, 2003, as per agreement dated 10.11.2014
(Annexure P-1).
2. The facts, in brief, are that the petitioner vide its letter dated
appoint a Sole Arbitrator to adjudicate the disputes between the parties. The
petitioner submitted its final bill vide letters dated 31.07.2020 (P-3). On
01.01.2021, the Contractor received part payment and vide letter dated
the petitioner found that there were certain items that are either uncertified
Project Manager (CPM) of the respondent for its decision in terms of Clause
1 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 2
25 of the Clauses of Contract. In the said letter, it was informed that as per
clause 25 of the Contract, in case the petitioenr is not satisfied with the
decision of the CPM of the respondent it shall pursue the matter in DRC.
The petitioner was then informed by the CPM of the respondent, vide letter
lakhs, however, the request of the petitioner for referring the matter to DRC
Executive Engineer to the effect that there shall not be any compensation
3. The CPM of the respondent vide letter dated 12.04.2022 informed the
23.06.2022 for solving the disputes between the parties. However, the DRC
failed to resolve the disputes between the parties. Vide letter dated
and requested the respondent to appoint an arbitrator for settling the disputes
between the parties. The respondent vide letter dated 04.08.2022 directed the
days from the date of issuance of the letter. In response to the above letter,
the petitioner vide letter dated 19.08.2022 informed the respondent that it is
not in agreement with the names suggested by the respondent through its
Hon’ble the Supreme Court in Perkins Eastman Architects DPC and anr
2 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 3
filed on behalf of the respondent and a preliminary objection has been taken
to the effect that the Arbitration Clause which the petitioner is using here to
have an access to legal recourse of filling this petition says that “It is also a
Arbitrator and if for any reason that is not possible, the matter shall not
In the reply, it has been stated that the petitioner applied vide
claimed before DRC that is why the petitioner was asked to stick to the
petitioner was communicated vide letter dated 17.08.2022 (P-31) THAT “As
per contract clause 25, disputes those are referred, with amount and are
disputed amount only and withdraw additional amount claim which was
never a dispute with department till date. The respondent sought editing in
the amount claimed vide letter dated 10.08.2022 (P-25) as per agreed terms
term of this contract that the party invoking arbitration shall give a list of
disputes with amounts claimed in respect of each such dispute along with the
3 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 4
Clause 25 of the agreement. The petitioner was provided with list of five
for one of the Arbitrator out of list of 05 Arbitrators for appointment of fair
chosing one Arbitrator out of the list provided. This information was
supplied by the respondent vide ltter dated 12.08.2022 (P-28) like DOB,
Address, Email, Mob No and validity. The petitioner, thereafter, asked more
Qualification. (d) Organization they served and last designation held in the
Organization. The respondent again provided the details vide letter dated
17.08.2022 and requested to send the consent before due date as per Clause
(P-32), the petitioner refused to select any Arbitrator from the list provided
consent till 22.08.2022 and taken decision to appoint sole Arbitrator from
The appointment of Sh. S.P. Singh conveyed to the petitioner, vide letter
filed the petition on 20.08.2022 and the petitioner also informed Sh. S.P.
4 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 5
Whereas, as per clause 25 of the agreement, the petitioner could have chose
any one Arbitrator from the list of 5 Arbitrators given by the respondents.
The appointment of the sole arbitrator was made on 22.08.2022 as per clause
25 of the agreement within one month after receiving the request from the
Arbtirators, the petitioner ought to have chosen the Arbitrator and there was
between the parties was not stamped and on this ground, the matter cannot
Heard.
this stage can be made to a judgment of Hon’ble the Supreme Court of India
in a case of Grasim Industries Ltd. vs. State of Kerala, 2018 (14) SCC 265,
5 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 6
Court found that the claim raised by the appellant was even beyond
the period postulated under Article 137 of the Limitation Act. In this
within three years from the date when the cause of action to
Hon’ble the Supreme Court of India in a case of BSNL and another vs.
Nortel Networks India Pvt. Ltd, 2021 (5) SCC 738 wherein it has been held
issue or at the final stage after evidence is led by the parties. However, while
exercising jurisdiction under Section 11 as the judicial forum, the Court may
exercise the prima facie test to tscreen and knockdown ex facie meritless,
6 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 7
frivolous and dishonest litigation. At the referral stage, the Court can
interfere only when it is manifest that the claims are ex facie time-barred and
barred or not. The only question for consideration is that whether as per
Section 25 of the Terms of the Contract, once the list of 05 Arbitrators had
been given to the petitioner and the petitioner chose not to finalise out of 05
India in cases of Perkins Eastman Architects DPC and another vs. HSCC
(India) Ltd, 2020 (20) SCC 760, Indian Oil Corporation Ltd and others vs.
Raja Transport Pvt. Ltd, 2009(8) SCC 520 and ICOMM Tele Ltd vs.
Punjab State Water Supply and Sewerage Board and another, 2019 (4)
SCC 401.
Electricals Ltd, 2023 SCC Online Del 7575, it has been held as under:-
7 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::
Neutral Citation No:=
ARB-326-2022 8
and Perkins (supra). The later part of the arbitration clause, that if
for any reason the person appointed by the respondent cannot act
technicalities."
Kishan Kaul, a former Judge of the Supreme Court, as the sole Arbitrator.
Court.
List on 16.02.2024.
(RITU BAHRI)
29.01.2024 ACTING CHIEF JUSTICE
G Arora
8 of 8
::: Downloaded on - 06-02-2024 16:47:58 :::