Professional Documents
Culture Documents
As 7718-2017
As 7718-2017
This Australian Standard® AS 7718 Signal Design Process Management was prepared by a RISSB Development
Group consisting of representatives from the following organisations:
ARTC ASA AECOM
Brookfield Rail Rio Tinto QR
ARTC
The Standard was approved by the Development Group and the Train Control Standing Committee in December,
2016. On January 25, 2017 the RISSB Board approved the Standard for release.
This standard was issued for public consultation and was independently validated before being approved.
Development of the standard was undertaken in accordance with RISSB’s accredited process. As part of the
approval process, the Standing Committee verified that proper process was followed in developing the standard.
RISSB wishes to acknowledge the positive contribution of subject matter experts in the development of this standard.
Their efforts ranged from membership of the Development Group through to individuals providing comment on a draft
of the standard during the open review.
I commend this standard to the Australasian Rail Industry as it represents industry good practice and has been
developed through a rigorous process.
Paul Daly
Chief Executive Officer
Rail Industry Safety and Standards Board
AS 7718:2017
Document Details
First published as: AS 7718:2017 Signal Design Process Management
ISBN 978-1-76035-852-5
Published by Rail Industry Safety and Standards Board (RISSB) ABN: 58 105 001 465
PO Box 4271, Kingston, ACT, Australia 2604
Copyright
©RISSB
All rights are reserved. No part of this work may be reproduced or copied in any form or by any means, electronic or
mechanical, including photocopying, without the written permission of RISSB, unless otherwise permitted under the
Copyright Act 1968.
Notice to Users
This RISSB product has been developed using input from rail experts from across the rail industry and represents
good practice for the industry. The reliance upon or manner of use of this RISSB product is the sole responsibility of
the user who is to assess whether it meets their organisation’s operational environment and risk profile.
Document Control
Identification
Document Title
Document History
Publication Version Effective Date Reason for and Extent of Change(s)
Approval
Name Date
Contents
1 Introduction......................................................................................................................7
1.1 Purpose .............................................................................................................7
1.2 Scope ................................................................................................................7
1.3 Exclusions .........................................................................................................7
1.4 Compliance........................................................................................................7
1.5 Referenced documents .....................................................................................8
1.6 Definitions ..........................................................................................................8
2 Stakeholder requirements definition ..............................................................................10
2.1 Purpose ...........................................................................................................10
2.2 Outcomes/deliverables ....................................................................................10
2.3 Activities and tasks ..........................................................................................11
2.4 Stakeholder requirements report .....................................................................12
3 Requirements analysis process ....................................................................................12
3.1 Purpose ...........................................................................................................12
3.2 Outcomes/deliverables ....................................................................................12
3.3 Activities and tasks ..........................................................................................13
4 Concept design process ................................................................................................13
4.1 Purpose ...........................................................................................................13
4.2 Outcomes/deliverables ....................................................................................14
4.3 Activities and tasks ..........................................................................................15
5 Detailed design process ................................................................................................16
5.1 Purpose ...........................................................................................................16
5.1.1 The detailed design process............................................................................16
5.1.2 Base design .....................................................................................................17
5.1.3 System requirements specification ..................................................................17
5.2 Outcomes/deliverables ....................................................................................18
5.2.1 The detailed design process (implementation) ................................................18
5.2.2 Interfaces .........................................................................................................18
5.2.3 The detailed design process............................................................................18
5.2.4 Procedures and manuals.................................................................................18
5.2.5 Design management plan................................................................................19
5.3 Activities and tasks ..........................................................................................19
5.3.1 Detailed design process ..................................................................................19
5.3.2 Parallel processes ...........................................................................................20
5.3.3 Parallel alterations ...........................................................................................21
5.3.4 Design management plan................................................................................21
5.3.5 Checking inputs ...............................................................................................21
5.3.6 Design deliverable plan ...................................................................................21
5.3.7 Design considerations .....................................................................................21
Appendix Contents
Appendix A System design process overview ....................................................................29
Appendix B Signaling design management standard lifecycle ...........................................30
Appendix C Safety in design ...............................................................................................31
C.1 Purpose ...........................................................................................................31
C.2 Outcomes/deliverables ....................................................................................31
C.3 Activities and tasks ..........................................................................................31
1 Introduction
1.1 Purpose
The objective of this standard is to provide the Australian rail industry with a set of mandatory
and recommended requirements for the signalling design management process. The main
purpose is to promote a consistent approach to the signalling design process across the
Australian rail industry.
This comprehensive process, if well implemented will substantially reduce the issues when
developing the design as all aspects are considered in this process which will lead to –
(a) shortening of the implementation period;
(b) reduce the need for redesign;
(c) enable transferability of people;
(d) having a standard process;
(e) reduction in errors;
(f) potential reduction in costs.
The standard is intended to –
(a) provide a uniform basis for compliance with AS 7702 Railway Safety
Management;
(b) be able to cover differing rail operations across Australia;
(c) identify the risks (hazards) being controlled;
(d) ensure that the standards survive a change in RIM.
1.2 Scope
This Standard specifies the process for the production of signalling designs for use on the rail
networks. This document describes the process for complete signalling system design from
concept through detailed design, construction, installation, test and commissioning and final as-
built documentation. It describes a process which can be part of a wider engineering project, or
which can be implemented as a stand-alone signalling engineering activity.
An overview of the system design process is provided in Appendix A.
This Standard is intended to be used by Infrastructure Managers, Operators and Suppliers of
railway systems.
1.3 Exclusions
The standard includes all processes although some projects will not require every process. This
will be subject to agreement between RIM, client and standards authority.
1.4 Compliance
There are two types of control contained within RISSB Standards:
(a) Mandatory requirements.
(b) Recommended requirements.
Each of these types of control address hazards that are deemed to require controls on the basis
of existing Australian and international Codes of Practice and Standards.
A mandatory requirement is a requirement that the standard provides as the only way of
treating the hazard.
Mandatory requirements are identified within the text by the term shall.
A recommended requirement is one where the standard recognises that there are limitations to
the universal application of the requirement and that there may be circumstances where the
control cannot be applied or that other controls may be appropriate or satisfactory, subject to
agreement with the Rolling Stock Operator, Rail Infrastructure Manager and/or Rail Safety
Regulator.
Recommended clauses are mandatory unless the RIM or RSO can demonstrate a better
method of controlling the risk.
Recommended requirements are to be considered when compliance with the standards is being
assessed.
Recommended requirements are identified within the text by the term should.
Hazards addressed by this standard are included in an appendix. Refer to the RISSB website
for the latest Hazard Register Guideline: www.rissb.com.au
ISO 9241-11 Ergonomic requirements for office work with visual display terminals (vdts) — Part
11: Guidance on usability
ISO 13407 Ergonomics — Ergonomics of human-system interaction — Human-centred design
process for interactive systems.
AS 7702 Rail Equipment Type Approval
EN50126 Railway Applications - The specification and Demonstration of Reliability, Availability,
Maintainability and Safety (RAMS)
EN50128 Railway Applications - Communication, Signalling and Processing Systems - Software
for Railway Control and Protection Systems
EN50129 Railway Applications Communication, Signalling and Processing Systems - Safety
Related Electronic Systems for Signalling
1.6 Definitions
As-built drawings: a revised set of drawings and design documentation including system data
submitted by the constructor upon completion of a particular design job. They reflect all changes
undertaken during the implementation. These should also reference existing drawings that were
not changed.
Derogation: Concession; waiver.
Design Authority: Any organisation with the authority to undertake design, testing,
commissioning, construction, maintenance of signalling plans.
Design Checker: A suitably experienced and competent Signalling Designer who is
responsible for checking that the prepared signalling design is safe and reliable and in
accordance with standard signalling principles and practices, and is operationally functional as
specified. Also, referred to as Design Reviewer.
Design Management Plan (DMP): (Design Development Plan; Design Package Brief; Detailed
Design Plan) A DMP is be used to co-ordinate, monitor and control design activities such as
design responsibility, schedule of drawings, design program, design estimate, procedures for
design changes.
Designer: A suitably experienced and competent person who is responsible for preparing
signalling design that is safe, reliable and in accordance with standard signalling principles and
practices and operationally functional as specified.
Drawings: Drawings shall be defined in this context as site specific or standard documented
layouts, plans, diagrams, tables, schematics, final arrangements and the like that set out the
design and/or configuration of signalling infrastructure assets (e.g. Physical dimensions and
compositions, temporal and/or spatial arrangements, physical and/or logical interconnections)
either existing, pre-existing, or proposed.
Overlapping Design or Alteration: A special case of parallel design, involving activities
relating to more than one alteration or design group. This is only permitted where one engineer
is identified as having overall responsibility for the interface between the successive design
alterations.
Parallel Design: Design, in which activities that would usually be undertaken sequentially, are
undertaken concurrently - (Also see Overlapping Design) or Design undertaken in a
compressed timescale such that activities relating to the same alteration which would usually be
undertaken sequentially are undertaken concurrently.
Project Manager: Is the person who is responsible for planning and monitoring, administration
and control of a project works.
RAM: Reliability, Availability, Maintainability and Safety
Signalling Plan: A longitudinally scaled or dimensioned track layout plan showing the Signalling
Functions with their identities. It generally relates to a specific Interlocking control area(s). May
also be known as a Signalling Arrangement Plan.
SFAIRP: So far As Is Reasonably Practicable
System Requirements Specification: (Term used for Signalling Requirements Specification or
Signalling Functional Specification or Scope of Works) shall specify track infrastructure, train
operations, Maintenance Requirements, Speed Signs, Signalling Equipment, Signalling
Configuration, ATP Systems (if any), Headway analysis, Power reticulation and AIR systems
etc.
The Rail Safety National Law: A National Rail Safety Legislation administered by the Office of
the National Rail Safety Regulator
Train Control System: One or more microprocessor based operator interface stations with the
processing capacity to handle route setting, automatic route setting, train tracking, train
describing, train reporting, event logging and all similar functionality.
Validation: Validation is a process. It uses objective evidence to confirm that the system
operational performance meets the user requirements specified. Whenever the specified
requirements have been met, a verified status is achieved.
Verification: Verification is a process. It uses objective evidence to confirm that the system
design meets the scope and design inputs specified. Whenever the specified requirements have
been met, a verified status is achieved.
WHS: Work Health and Safety
2.2 Outcomes/deliverables
The stakeholder requirements definition shall –
(a) define the scope of the hazard analysis;
(b) establish the RAMS policy for the system;
(c) establish the safety plan for the system;
(d) specify required characteristics and context of use of train services,
operational concepts and dependability;
(e) define the constraints on a system solution;
(f) ensure all requirements can be traced to at least one stakeholder, and
(g) define stakeholder requirements (including validation).
Stakeholder requirements shall clearly define what the system should do and avoid.
So far as is possible, stakeholder requirements should define how those requirements are to be
achieved
The stakeholder requirements definition shall specify –
(a) operations relating to human factors;
(b) method of train operations;
(c) traffic levels at time of commissioning;
(d) future changes to traffic levels;
(e) train types;
(f) track design parameters;
(g) special /exceptional /out of course train operations;
(h) level crossings (for each level crossing);
(i) train / wagon stabling;
(j) staging of construction and commissioning;
(k) infrastructure;
(l) specific train operation hazards (e.g. flammable loads);
(m) specific infrastructure hazards (e.g. Gas pipeline);
(n) environmental;
(o) WHS.
The stakeholder requirements shall stipulate the assurance of competent and adequately
resourced personnel.
The stakeholder requirements shall define the relationships between design authorities, as well
as interfaces with other authorities, disciplines, functions and RIMs.
The stakeholder requirements shall define the responsibilities for collating documentation to be
submitted for RIM approval and statutory approval.
The RIM shall mandate the process for assessment and approval of proposed changes to the
stakeholder requirements such as to assure that all safety, delivery and cost impacts are
identified.
The stakeholder requirements should state if the system has any direct or indirect interfaces
with existing operating systems
3.2 Outcomes/deliverables
The successful implementation of the requirements analysis process shall -
(a) define a system requirements specification;
(b) specify constraints that will affect the concept design of a system and the
means to realize those constraints;
(c) achieve the integrity and traceability of system requirements to the
stakeholder requirements report;
(d) Define the criteria for acceptance of a requirement
The requirements analysis shall include requirements associated with –
(a) intended use;
(b) self-testing and diagnosis;
(c) all interfaces;
The system element is constructed or adapted by processing the information appropriate to the
selected implementation technology and by employing appropriate technical specialties or
disciplines.
The concept design process will ensure that the integrity and traceability of the RAMS
requirements in the design are managed in accordance with the assurance processes defined
in en50126, en50128 and en50129.
4.2 Outcomes/deliverables
The concept design process shall be developed from a defined and agreed set of system
requirements.
The concept design process shall deliver the following:
(a) An agreed concept design baseline.
(b) The set of system element descriptions.
(c) The interface requirements to external systems.
(d) Traceability of concept design to system requirements.
(e) A basis for verifying the system elements.
(f) A basis for the integration of system elements.
The design should capture a trigger point for concept design completion (%).
The concept design process shall –
(a) provide clear, accurate, consistent and unambiguous presentation;
(b) comply with the referenced standards;
(c) comply with the client’s requirements, as reflected in the system requirements
specification;
(d) specify an appropriate level of safety;
(e) confirm that the system design will realise the complete set of all allocated
requirements;
(f) facilitate construction (including stagework) and testing;
(g) develop a functional design that is fit for purpose.
In providing the concept design the design authority shall –
(a) be competent and hold engineering competencies relevant to the RIM;
(b) prepare, supervise and manage the design in accordance with the RIM
signalling standards and procedures;
(c) prepare, review and verify the design;
(d) independently check the concept design against the SRS in accordance with
the RIM standards and procedures, and
(e) produce all design information, data, drawings and other documentation in
accordance with the RIM's standards and procedures.
The concept design process shall deliver the signalling plan.
Where sequential commissionings are required, derivative staged signalling plans shall be
produced.
The signalling plan produced shall demonstrate that allocated requirements have been
addressed and the plan is readily understood by operations, signalling and other stakeholders.
Where required, the concept design process should deliver a signalling equipment system
configuration.
The process will support development of a detailed design that is completely compliant with
agreed system requirements and that all requirements are verified as being traced from the
previous phase and all functionality and performance is validated.
Designs will be in accordance with the RIM’s standards and procedures to assure that the
safety integrity is achieved. Alternatively, for novel designs that are not covered by existing RIM
standards, the design may consider the requirements of EN50126, EN50128 and EN50129 to
ensure that the safety integrity is defined and achieved.
This process combines system elements to form complete or partial system configurations in
order to create a product specified in the system requirements.
The development of the signalling plan fulfils the following purposes, as necessary:
(a) Submission for approval in principle by the RIM.
(b) Checking interdisciplinary details associated with train operating, permanent
way, civil engineering, electrification infrastructure, plant and
telecommunications requirements.
(c) Estimating and contract tendering, where applicable.
(d) Compiling control tables and other design details.
(e) Providing a derivative for the production of a signalling bonding plan.
(f) Deriving drivers diagrams, panel faceplates and VDU maps.
(g) Signal sighting.
(h) Control table testing.
(i) Layout of new equipment on site and identifying recoveries.
(j) In the case of multiple stage schemes, deriving stage signalling arrangement
plans for each commissioning.
5.2 Outcomes/deliverables
5.2.1 The detailed design process (implementation)
As a result of the successful implementation process —
(a) an implementation strategy shall be defined;
(b) implementation technology constraints on the design shall be identified;
(c) the design of a system element shall be completed with all supporting
documentation and under version control;
(d) a system element shall be packaged and stored in accordance with an
agreement for its supply;
(e) the deliverables (design outputs) shall be be detailed within the project
management plan and the design management plan;
(f) if required a safety case should be completed prior to the implementation
process.
5.2.2 Interfaces
All interfaces shall be identified from the system architecture and documented in an interface
control document. Each interface shall have a defined interface requirement specification to
ensure an effective interface is designed
For every design output where there is an interface with another discipline, eg civil, ole, track
there shall be an interdisciplinary design check to ensure that the interface does not have any
impact on the integrity of another rail system
There shall be no restriction on the creation of source records for new work, as distinct from
alterations to existing installations.
Implementation, updating and version control (also known as baselining detailed design) shall
be strictly applied –
(a) except where the implementation of a subsequent alteration is commenced as
soon as any common source records have been updated in anticipation of the
previous commissioning; and
(b) provided that the same responsible design engineer has been appointed to
oversee all overlapping alterations; and
(c) except where the implementation of a subsequent alteration is commenced as
soon as any common source records have been updated in anticipation of the
previous commissioning,
(d) security copies have been taken where necessary for record purposes.
Source records shall be updated as soon as an alteration has been checked, provided that the
same responsible design engineer has been appointed to oversee all overlapping alterations
and security copies have been taken where necessary for production purposes.
Design implementation showing new designs, alterations to existing designs and deletions of
existing systems shall clearly and unambiguously show: new works, deleted works and
amended works in accordance with the RIM requirements. This includes: drawings, system
data, design documents, design calculations and any other supporting documents for the
design.
Data approval form(s) shall be in accordance with the RIM guidelines designed to suit the types
of electronic data-driven equipment to be used on the project.
The responsible design engineer shall be appointed by the design authority before the design of
the first alteration is commenced.
If commissioning dates have not already been defined, the responsible signal designer shall
nominate an assumed order in which the commissionings are to be treated, with reference to
the draft staging and testing strategy, and tester in charge, if appointed.
Commissioning dates shall also be agreed between all affected disciplines and parties,
including the design authority and RIM.
If the nomination proves incorrect, each alteration shall be modified as necessary to allow for
the new commissioning order.
This process will be facilitated by arranging simple interfaces between each alteration and
agreeing the usage of spare fuses, cable cores and relay bases, etc.
and the actual design as functioning. If correlation is required, the condition of the asset to be
disturbed must be considered when defining the actions relating to confirming the accuracy of
the records.
Equipment likely to be affected by the proposed work shall be examined by a competent signal
engineer who shall make an assessment of any factors which might introduce special risks
during the execution of the work.
The design authority shall have the relevant competencies to undertake the task of managing
signalling works.
6.2 Outcomes/deliverables
The independent checking shall provide the verification evidence as required by the verification
and validation plan for the system:
(a) The design output shall conform to specified requirements.
(b) The design option chosen shall be feasible, fit for purpose and safe.
(c) The design of the signalling system shall meet all the dependability criteria.
(d) The system being designed shall be constructed, tested, commissioned,
operated and maintained efficiently and effectively.
(e) The design shall have taken in to account all applicable aspects listed in the
design checklists and/or the proceedings of a technical review, including test
results where appropriate.
(f) Supporting calculations and decisions for defined critical systems shall have
been independently checked and verified in accordance with RIM standards
and specifications.
(g) The requisite approvals shall have been obtained from regulatory authorities.
(h) The design shall have been documented as per each RIM requirements.
These documents and records shall form part of the evidence supporting
systems and safety assurance.
As a result of the successful implementation of the independent checking (verification)
process –
(a) a list of items for corrective actions shall be recorded; and
(b) confirmation design shall satisfy the system requirements and concept design.
If independent verification is required by the RIM, the independent checker shall issue to the
design authority —
(a) a signed copy of their check copy (including all mark ups) as a minimum
requirement for verification;
(b) an updated list providing information for corrective action is reported,
containing all errors and/or queries, and
(c) an updated independent checking record with all relevant fields filled out.
The independent checker shall review the specific design item in consideration of all other
design items even if they are not the independent checker for other items.
Individual people should be separately used to perform independent check for different design
items. One of the independent checkers should take overall responsibility for the complete
independent design check.
6.3.3 Rework
Errors found by the independent checker shall be returned to the designer for review and
correction. They resultant designs are then returned to the independent checker for checking.
The designer should respond to each error report stating their action including responses where
the item raised is confirmed as not an error, stating why so that it can be closed out.
7.2 Outcomes/deliverables
7.2.1 Design approval levels and definitions
The RIM shall define the level of approval for each design. The following levels of design
approval are applicable:
(a) Approved in principle: the design proposal is generally satisfactory but some
areas of the submission require correction, alteration or clarification. Design
proposal is generally consistent with scope, applicable standards and follow
the require processes.
(b) Approved for construction: the design output should be used for determining
bill of materials and for undertaking construction activities.
(c) Approved: complete design shall meet the agreed scope, applicable standards
and processes and safety in design obligations and is SFAIRP.
The RIM should define gateways for the design approval process to mitigate project risk and to
ensure the design will meet the applicable requirements to reduce the risk of not meeting final
approval.
All designs, drawings supporting documents shall be submitted to the RIM and acceptance
obtained before any work covered thereby is commissioned into service.
7.2.2 Responsibilities
The design authority shall be responsible for demonstration that all requirements allocated to
the signalling and system design have been met
Each RIM shall be satisfied that the design authority is competent and will allocate adequate
resources to perform its responsibilities.
Where the RIM does not have a specific requirement for competency for a design task, the
personnel shall be able to demonstrate that they have the competency to undertake the task.
Where there are legislative requirements for accreditation for engineering work or other tasks,
then these shall be addressed in the design management plan and personnel meeting the
requirements allocated accordingly.
Where permitted by the RIM competency requirements, a person without competency should
undertake tasks under supervision and mentorship of a competent person.
Records of the competence of personnel undertaking design tasks shall form part of the design
management plan.
Personnel undertaking supporting tasks for the design process shall also be competent and
have records of competence.
8.2 Responsibilities
The design authority should be responsible for managing the design process.
The manager of personnel undertaking design tasks should ensure that the personnel allocated
to a task are competent to perform the task.
The organisation applying this standard should have in place a quality system to ensure that the
design work is carried out in a planned and systematic way and that there is appropriate
documentation as evidence of this.
The quality system should be accredited to AS/NZS ISO 9001 - quality systems for
design/development, production, installation and servicing, or an equivalent acceptable to the
RIM
9.2 Outcomes/deliverables
The design authority shall have a RIM approved process in place for assessment and
management of change, this will ensure –
(a) the lifecycle change and the complexities associated with making that change
in the current stage are assessed and appropriate controls defined;
(b) unique identification of each modification to design drawings or documents;
(c) full traceability of each change;
(d) updating of affected records.
The design authority shall have in place a configuration management system that provides
traceability between all configuration items so that when it a change is approved for
implementation all affected configuration items can be identified and updated.
Any configuration item shall require preapproval if any change is made to that item outside of
the scope of the defined conditions of approval.
C.1 Purpose
Each RIM has statutory obligations under the rail safety national law, the relevant state rail
safety act and the WHS acts to ensure safety in design.
Risk assessment is an effective tool for determining which engineering control measures are
likely to give the greatest safety benefit in terms of the cost incurred, and demonstrating that
sufficient mitigation has been applied for the residual risk to be acceptable to each RIM.
Designing for safety requires identifying hazards and risks and eliminating or minimising risks to
SFAIRP through design.
ease of maintenance and low maintenance systems will maximise operational availability by
reducing recovery times after failure and minimise the lifecycle cost of the system.
C.2 Outcomes/deliverables
Systems of work necessary for the safe use of the asset.
Knowledge, training or skills necessary for persons installing, operating or maintaining the
asset.
Spares support requirements.
In the design of signalling systems, provision shall be made for the health and safety of
personnel at risk (e.g. Installers, testers, maintainers and operators) by means of a systematic
approach to task risk assessment.
The following categories of risk based safety analysis are applicable:
(a) Specific application safety argument (risk based) for the design and
implementation of a whole system at a particular installation.
(b) Generic application safety argument (risk based) for a particular architecture
of sub-systems with a wide application, for systems approval.
(c) Generic product risk based safety argument for a particular item of equipment
with a wide application, for type approval.
(b) General control by isolating from, or minimising the risk within the design
(c) Individual control by procedures, training and provision of personal protective
equipment.
Where risks cannot be eliminated at source, additional information shall be provided in health
and safety plans, and/or noted on design details to help staff manage the risks.
At appropriate phases of the design, the design authority shall contribute to a health and safety
plan and retained for the life of the installation.
The means of demonstrating safety shall be stated in the system specification, and shall include
the following processes:
When applying, or interfacing, established circuit and system principles in a manner which has
not been catered for in those circuits or systems, due note shall be taken of the effect.
Where the issues are sufficiently complex to warrant it, a risk assessment shall be undertaken
as per RIM standards.
Documentation (as per RIM standards) shall be prepared, recording these effects (with
supporting calculations, where necessary) which will provide an audit trail of the designer's
conversion of the plans (e.g. Signalling plan and control tables) into engineering details.
Risk assessment shall be preceded by a process of hazard identification that systematically
considers all possible system interactions (both internal and external) and is commensurate with
the degree to which the system has changed and with the degree to which the system is
already proven in operation.
Novel systems, applications or environments require a team-based approach, such as a hazard
and operability study (HAZOP).
Significant changes or modifications shall be controlled in a similar manner to the original
design, such as:
Non-significant changes need only follow a reduced process to be determined by the RIM.
Design features that assist preventive and corrective maintenance shall be considered with the
infrastructure controller, in conjunction with the forming of their future maintenance policy.
These features shall be addressed at the concept phase of the design.
PO Box 4271
Kingston ACT 2604