Professional Documents
Culture Documents
23 01 67 คุณชนวิช การบริหารโครงการในมุมมองของผู้รับเหมา
23 01 67 คุณชนวิช การบริหารโครงการในมุมมองของผู้รับเหมา
3.
Central expenses
(Overhead Cost)
Construction Planning
1 ( )
2
3
Planning before start construction working 4
Planning for the contribution
(Must be done on estimation process) Planning during construction Planning for Hand-Over insurance period.
1) 4)4)
2) 3)
( )
q q Quality Manual q As-Built Drawing q Inspection Schedule
w w Worker Training Programe w Structure Design Drawing w 6 month Check
w Photo Site Survey Report w Work Method Statement w Architectural Design Drawing w Final Check
q (Spec. & Design Dwg.) w Work Instruction w As-Built Shop Drawing q Request Maintainance Bond
w Project Outline w Check List Form q Testing & Commisioning Report
w , (TOR.) w Inspection & Test Plan(ITP) q Training Program of M/E Work to Owner
w q Safety Manual ,Regulation and Safety Laws q Defect and Inspection Check List
, , , q Review Master Schedule q Hand Over Schedule
q Monthly Schedule & Report q Handover Document
q q Weekly Schedule & Report w Inspection Check List
q (Temporary Work Planning Drawing) q , w Key List,keys and Key Box
w Construction Method Statement q Shop Drawing Schedule w Manual of Operation
q w Photo Completion Work
- q w Remaining Material List
- q Preventive Plan w Supplier List
- q Corrective Plan w List of Warrantly Letters
w (Temp. layout plan) q Variation Order Work q Submit Maintainance Bond
,Store, q Request Payment q
w (Under Ground WorK) q Budget Control
w (Super Structure Work) q (Feed back,Evaluate Data)
w Special Structure Work
w (Safety Plan)( , , )
w (Temp. Electric)
w (Temp. Pumbling)
w (Labour Camp)
q
q (Master Schedule)
q (Organization Project Chart)
Planning before start construction working
Construction Planning
Spec.&Design Dwg.)
Project Outline
Quantity Survey based on the drawing such as Concrete, Formwork, Steel bar ,
Steel skeleton, decorative materials.
Building Design Drawing
Lay-out
Section
Underground
Planning before start construction working
(Temporary Work Planning Drawing)
Engineering Based On
Schedule Time
Budget Control
Construction Safety work to be careful
Personal Safety
Environmental Safety
THE Sample PROJECT
BANGKOK THAILAND
Deputy manager
Chief foreman Chief foreman Survey Chief Eng. Chief M&E Material
Material
Engineer
Shop drawing
Engineer Engineer Foreman Clerk
Clerk
division
Foreman Foreman
- Entertainment and
- Spa, Suite and Survey work - Temporary work Mechanical
Retail building Procurement
Procurement
Massage building - Quanlity control &
- Swimming Pool &
&
- External work - Safety control Electrical
- Porte cochere Administration
Administration
- Quantity survey Shop drawing Co-ordinate
- External work
- Quantity survey
Planning during construction
Quality Manual
Safety Manual , Regulation and Safety Preparing the procurement plan.
Laws
Review Master Schedule Permission for electricity and
water supply from government
Monthly Schedule & Report
Preventive Plan
Weekly Schedule & Report
Corrective Plan
Variation Order Work
Request Payment
Access to and delivery of area, Budget Control
Confirm the official pin .
Project Evaluate
Shop Drawing Schedule Feed back,Evaluate Data)
Quality Manual
Inspection Schedule
6 Month check
Final check
Request Maintenance Bond