Professional Documents
Culture Documents
06 - Project Schedule Management
06 - Project Schedule Management
06 - Project Schedule Management
6TH EDITION
BY:MAZEN ALSAYED
Chapter 6
PROJECT Schedule
MANAGEMENT
PMBOK-6th Page 173 to 230
Process Group
Knowledge Area
Initiating Planning Executing Monitoring & Controlling Closing
4.5. Monitor & Control
4.3.Direct & Manage Project 4.7. Close
4. Project Integration 4.1. Develop project 4.2. Develop project management Project Work
Work Project or
Management charter plan 4.6. Perform Integrated
4.4.Manage Project Knowledge Phase
Change Control
5.1. Plan Scope Management
5.Project Scope 5.2. Collect Requirements 5.5. Validate Scope
Management 5.3. Define Scope 5.6. Control Scope
5.4. Create WBS
2 24 10 12 1
mohossamaraslan@icloud.com 2
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Lecture 03 : Project Schedule Management
Contents
2 Define Activities
5 Develop Schedule
Schedule
Management
• Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and
controlling the project schedule.
• ه العملية الت تحدد السياسات واإلجراءات والوثائق المستخدمة ف تخطيط الجدول الزمت ر
.للمشوع وتطويره وإدارته وتنفيذه ومراقبته ي ي ي ي
✓ Provides guidance and direction on how the project schedule will be managed throughout the project.
للمشوع عىل مدار ر
.المشوع ✓ توفر اإلرشاد والتوجيه بشأن كيفية إدارة الجدول الزمت ر
ي
✓ Development approach. will help define the scheduling approach, estimating techniques, scheduling tools, and
techniques for controlling the schedule.
Expertise should be considered from individuals or groups with specialized knowledge or training in previous, similar projects:
• Schedule development, management, and control;
• Scheduling methodologies (e.g., predictive or adaptive life cycle);
• Scheduling software The specific industry for which the project is developed.
2- DATA ANALYSIS
Alternatives analysis ﺗﺤﻠﯿﻞ اﻟﺒﺪاﺋﻞ
Can include determining which schedule methodology to use, or It can also include determining how detailed the schedule
needs to be, the duration of waves for rolling wave planning, and how often it should be reviewed and updated.
3- MEETINGS
Project teams may hold planning meetings to develop the schedule management plan. Participants at these meetings
may include the project manager, the project sponsor, selected project team members, selected stakeholders, anyone
with responsibility for schedule planning or execution, and others as needed.
✓ Project schedule model development (Methodology - Scheduling tool) منهجية وأداة الجدولة
اﻟﻤﺴﺘﻮى اﻟﻤﻘﺒﻮل
✓ Level of accuracy (acceptable range used in determining realistic activity duration estimates)
✓ Units of measure (such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers,
or cubic yards for quantity measures)
اﻟﺤﺪ اﻟﻤﺴﻤﻮح ﻓﯿﮫ
Schedule
Management
• Identifying and documenting the specific actions to be performed to produce the project deliverables.
َّ ُ
نفذ ك يتم إنتاج مخرجات ر
.المشوع ي • ي
ه عملية تحديد وتوثيق إجراءات معينة ت
✓ Decomposes work packages into schedule activities that provide a basis for estimating, scheduling,
executing, monitoring, and controlling the project work.
ً ✓ تجزئة مجموعات العمل إىل أنشطة للجدول الزمت توفر
أساسا لتقييم عمل ر
. ومراقبته والتحكم فيه، وتنفيذه، وجدولته،المشوع ي
( 2 ) Define Activities
Tools &
Input Techniques Outputs
✓ Each work package within the WBS is decomposed into the activities required to produce the work package deliverables.
.✓ ويجري تجزئة كل حزمة عمل داخل هيكل تجزئة العمل إىل األنشطة الالزمة إلنتاج تسليمات حزمة العمل
• an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work
further in the future is planned at a higher level.
• It is a form of progressive elaboration. فهو أحد أشكال االتضاح المتدرج
َّ
هو أسلوب التخطيط التكراري الذي فيه ُيخطط العمل الذي •
ً ً
يينما،تفصيليا سيتم إنجازه عىل المدى القريب تخطيطا
ُيخطط العمل يف المستقبل عىل مستوى أعىل
• Includes the schedule activities required on the project. تشمل قائمة األنشطة أنشطة الجدول الزمت المطلوبة ف ر
.المشوع ي ي
• Includes an activity identifier and a scope of work description for each activity in sufficient detail
to ensure that project team members understand what work is required to be completed.
وتضم قائمة األنشطة محدد النشاط ووصف لنطاق العمل لكل نشاط يتفاصيل كافية لضمان فهم أفراد فريق ر
المشوع للعمل
.المطلوب إنجازه
• Activity name
• Activity description
• Predecessor and successor activities
• Logical relationships
• Leads and lags
• Imposed dates
• Constraints
• Assumptions
• Resource requirements and skill levels
• Location of performance
• Type of effort
BY: EL-Sayed Mohsen , PMP®, PMI- RMP®, PMI-SP
Lecture 03 : Project Schedule Management
2. Define Activities (Planning)
Outputs ❑ Milestone List قائمة المعالم
Once the project has been baselined, the progressive elaboration of deliverables into activities may
reveal work that was not initially part of the project baselines. This may result in a change request.
ً مبدئيا
جزءا من ً عند إرساء الخط المرجع ر
فإن االتضاح المتدرج للتسليمات يف األنشطة يمكنه أن يكشف عن العمل الذي لم يكن،للمشوع ي
.التغيي
ر الخطوط المرجعية ر
ويمكن أن ينجم عن ذلك طلب،للمشوع
Schedule
Management
✓Defines the logical sequence of work to obtain the greatest efficiency given all project
constraints. أكي قدر من الكفاءة ف ضوء جميع قيود ا ر
.لمشوع ي المنطق للعمل للحصول عىل ر
ي ✓ تحدد التسلسل
( 3 ) Sequence Activities
Tools &
Input Techniques Outputs
1- Finish-to-Start: a successor activity cannot start until a predecessor activity has finished.
) صب الخرسانة و المعالجة:الثان اال بعد انتهاء النشاط األول (مثال
ال يبدأ النشاط ي
2- Finish-to-Finish: a successor activity cannot finish until a predecessor activity has finished
) التسليم و اعمال النظافة:الثان اال بعد نهاية النشاط األول (مثال
ال ينته النشاط ي
3- Start-to-Start: a successor activity cannot start until a predecessor activity has started.
)مواسي الكهرباء
ر اللياسة بعد:الثان اال بعد بداية النشاط األول (مثال
ال يبدأ النشاط ي
4- Start-to-Finish: a successor activity cannot finish until a predecessor activity has started.
)تغيي وردية
ر:الثان اال بعد بداية النشاط األول (مثال
ينته النشاط ي
ي ال
✓ Sometimes referred to as preferred logic, or soft logic. المنطق المفضل او المنطق السهل
ﺑﻨﺎءا ﻋﻠﻰ اﻟﺨﺒﺮات
✓ Established based on knowledge of best practices within a particular application area.
✓ During construction, the electrical work should start after finishing the plumbing work. This order is not
mandatory and both activities may occur at the same time.
✓ External dependencies involve a relationship between project activities and non project activities.
.غي المرتبطة بالمشاري ع
تنطوي االعتماديات الخارجية عىل عالقة ريي أنشطة المشاري ع واألنشطة ر
✓ a precedence relationship between project activities and are generally inside the project team’s control.
المشوع وعادة ما تكون تحت سيطرة فريق ر
.المشوع عالقة أسبقية ريي أنشطة ر
✓ For example, if the team cannot test a machine until they assemble it, there is an internal mandatory dependency.
. فهناك اعتمادية إلزامية داخلية،غي قادر عىل اختبار آلة حت يجمعونها
إذا كان الفريق ر
Lead: Is the amount of time a successor activity can be advanced with respect to a predecessor activity.
( Starting the activity before completing its predecessor )
) الت يها يمكن تقديم نشاط الحق بالنسبة لنشاط سايق ( بدء النشاط قبل انهاء النشاط السايق له
ه مقدار الفية الزمنية ي
ي
Lag: Is the amount of time a successor activity will be delayed with respect to a predecessor activity.
( Waiting time between activities)
) المتتاليي
ر النشاطي
ر تأخي نشاط الحق فيما يخص نشاط سايق ( عبارة عن ازمنة انتظار ريي
ه مقدار الوقت الذي يواسطته سيتم ر
ي
Schedule
Management
• Estimating the number of work periods needed to complete individual activities with estimated resources.
• عملية تقدير عدد فيات العمل الالزمة إلكمال األنشطة المنفردة باستخدام الموارد ي
.الت تم تقديرها
✓ It provides the amount of time each activity will take to complete. .✓ توفر مقدار الوقت الالزم لكل نشاط يك يكتمل
Tools &
Input Techniques Outputs
mohossamaraslan@icloud.com 38
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Lecture 03 : Project Schedule Management
4. Estimate Activity Duration (Planning)
TT ❑ Analogous Estimate التقدير التناظري
✓ Using historical data from a similar activity or project. .باستخدام ييانات من مشاري ع سابقة
✓ Used when there is a limited amount of detailed information. عند وجود قدر محدود من المعلومات
✓ Less costly and less time-consuming but less accurate. .األقل يف التكلفة والوقت و لكن االقل دقة
(e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget,
and duration.
✓ The accuracy of single-point duration estimates may be improved by considering estimation uncertainty and risk.
ًالزمن األفضل ( الزمن المعتاد و ر
M : Most likely duration ) األكي حدوثا
O : Optimistic duration ) الزمن المتفائل ( أقل زمن تم انجاز النشاط فيه
P : Pessimistic duration ) أكي زمن تم انجاز النشاط فيه
الزمن المتشائم ( ر
E = (O + M + P) / 3
Triangular distribution is used when there is insufficient historical data.
ر َ
الثالن حينما ال تكون البيانات السابقة كافية
ي ع التوزي ميستخد
✓ A method of estimating project duration or cost by aggregating the estimates of the lower level components
of the WBS. ه طريقة لتقدير مدة ر
.المشوع أو تكاليفه من خالل تجميع التقديرات للمكونات ذات المستوى األدن من هيكل تجزئة العمل ي
✓ When an activity’s duration cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail. The detail durations are estimated. These estimates are then
aggregated into a total quantity for each of the activity’s durations.
ُ
ثم يتم تجميع هذه، وتقدر مدد التفاصيل. يتم تجزئة العمل داخل النشاط بمزيد من التفاصيل،وعندما ال يمكن تقدير مدة أحد األنشطة بدرجة معقولة من الثقة
. إجماىل لكل مدة من مدد النشاط
ي التقديرات يف رقم
TT ❑ Data analysis
Alternatives analysis: تحليل البدائل
✓ Compare various levels of resource capability or skills. لمقارنة مستويات عديدة من إمكانيات الموارد أو مهاراتهم
✓ Comparing (manual versus automated) and make, rent, or buy decisions regarding the resources.
✓ This allows the team to weigh resource, cost, and duration variables to determine an optimal approach for accomplishing
يسمح ذلك للفريق لتحديد األسلوب األمثل إلنجاز عمل ر
.المشوع
project work.
Reserve Analysis: تحليل االحتياط
✓ Used to determine the amount of contingency and management reserve needed for the project.
✓ Duration estimates may include contingency reserves:اﻟﺰﻣﻨﻲ اﻟﺸﻚ واﻟﻐﻤﻮض ﻓﻲ اﻟﺠﺪول
TT ❑ Data analysis
Reserve Analysis: تحليل االحتياط
• for management control purposes and are reserved for unforeseen work that is within scope of the project.
• Management reserve is not included in the schedule baseline, but it is part of the overall project duration requirements.
Voting:
✓ One variation of the voting method that is often used in agile-based projects is called the fist of five.
✓ The project manager asks the team to show their level of support for a decision by holding up a closed
fist (indicating no support) up to five fingers (indicating full support).
✓ If a team member holds up fewer than three fingers, the team member is given the opportunity to discuss
any objections with the team.
✓ The project manager continues the fist-of-five process until the team achieves consensus (everyone
holds up three or more fingers) or agrees to move on to the next decision.
✓ Duration estimates are quantitative assessments of the likely number of time periods that are required to
✓ The amount and type of additional details supporting the duration estimate vary by application area
Schedule
Management
• Analyzing activity sequences, durations, resource requirements, and schedule constraints to create a
schedule model for project execution and monitoring and controlling.
• عملية تحليل تسلسل األنشطة وفياتها الزمنية ومتطلبات الموارد والقيود عىل الجدول الزمت إلنشاء نموذج الجدول الزمت لتنفيذ ر
.المشوع ومراقبته والتحكم فيه ي ي
✓ Generates a schedule model with planned dates for completing project activities
✓ تصدر نموذج للجدول الزمت يتواري خ مخططة الستكمال أنشطة ر
.المشوع ي
( 5 ) Develop Schedule
Tools &
Input Techniques Outputs
• Technique used to generate the project schedule model. توليد نموذج الجدول الزمت ر
للمشوع ي
• It employs several other techniques such as critical path method, resource optimization techniques and
modeling techniques.
• Used to estimate the minimum project duration. لتقدير الحد األدن لمدة ر
المشوع
• Calculates the early start, early finish, late start, and late finish dates for all activities without regard for any resource
limitations by performing a forward and backward pass analysis
• The critical path is the sequence of activities that represents the longest path through a project
• A critical path is normally characterized by zero total float on the critical path.
االنشطة عىل المسار الحرج عادة لها فية سماح اجمالية تساوي صفر
A B C
Finish
Start
mohossamaraslan@icloud.com 45
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Critical Path
In a project network diagram, the series of activities that determine the earliest completion of the
project.
Will change as activities are completed ahead of or behind schedule. Although normally
calculated for entire project, may also be determined for a milestone or subproject .
Often defined as those activities with float less than or equal to a specified value, often zero
mohossamaraslan@icloud.com 46
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Critical Path Method - CPM
• Network analysis tech. used to predict project duration by analyzing the sequence of
activities(path) that has the least amount of scheduling flexibility (least amount of float).
• Early dates are calculated by a forward pass using specified start date.
• Late dates are calculated by a backward pass starting from a completion date
mohossamaraslan@icloud.com 47
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Lecture 03 : Project Schedule Management
5. Develop Schedule (Planning)
0 2
A
0 Start Early Start Date =
0 2 Days Early Start Box + 1 Day
D
6 Days
mohossamaraslan@icloud.com 49
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Critical Path Method (PDM), Forward Pass
0 2 2 14 14 19
A B C
2 Days 12 Days 5 Days 19 19
0 0
Start Finish
0 6 6 13 13 16
D E F
6 Days 7 Days 3 Days
mohossamaraslan@icloud.com 50
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Backward Pass
5 Days
14 19
Late Start Date = C
Late Start Box + 1 Day 19 19
14 19
Finish
19 19
Late Finish Date = 3 Days
Late Finish Box
13 16
F
Late Start 16 19 Late Finish
Box Box
mohossamaraslan@icloud.com 51
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Critical Path Method (PDM), Backward Pass
Late Finish =
Lowest of successor’s Late Start Times
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
Start Finish
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16
D E F
3 9 9 16 16 19
mohossamaraslan@icloud.com 52
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Float
The amount of time a task can be delayed without delaying the end date of the
project.
The difference between either the Late and Early Start or the Late and Early
Finish.
2 Days 12 Days 5 Days
0 2 2 14 14 19
A B C
0 2 2 14 14 19
0 0 19 19
(0) (0) (0) Finish
Start
6 Days 7 Days 3 Days 19 19
0 0
0 6 6 13 13 16 (0)
Float = (0)
D E F
3 9 9 16 16 19
mohossamaraslan@icloud.com 53
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Lecture 03 : Project Schedule Management
5. Develop Schedule (Planning)
Critical Path Method
ES : Early Start البداية المبكرة EF: Early Finish النهاية المبكرة
LS : Late Start البداية المتأخرة LF : Late Finish النهاية المتأخرة
Total Float: amount of time that a schedule activity can be delayed without delaying the project finish date.
فية السماح الكلية ( الت يمكن للنشاط ان يتأخرها دون تأخر ر
) المشوع ي
TF= ( LF – EF ) = ( LS – ES )
Free Float: amount of time that a schedule activity can be delayed without delaying the early start date of any successor.
) التاىل
ي فية السماح الحر (يمكن ان يتأخرها النشاط دون تأخر البداية المبكرة للنشاط
FF = ESE - EFB
ES D EF 0 4 4 5 6 11
B E
Activity Name
1 1 5 5 0 11
LS TF LF
Activity
D
Dependency Critical Path Method (Example)
(Days)
A 5 Start
B 4 Start
0 5 5 5 3 8 8 9 17
C 3 Start
A D G
D 3 A 0 0 5 6 1 9 9 1 18
E 6 A, B
F 4 C 0 18
0 4 4 5 6 11 11 7 18
G 9 D
Start B E H End
H 7 D, E 1 1 5 5 0 11 11 0 18
0 18
Consider all relationships are FS=0
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure Z
mohossamaraslan@icloud.com 57
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
10 1 4
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure Z
Using figure Z, a new task R with a duration of five is added to this
project. Task R has a predecessor of task A and a successor of task B.
How long will the project now take?
A. 49
B. 48
C. 38
D. 52
mohossamaraslan@icloud.com 58
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
10 1 4
C D E
6 7 9 8 4 6 3
A B F G H J K
11
Figure Z
Based on the network diagram in figure Z, the resource working on task
G is replaced with another resource with 50% of the productivity of
the previous resource. How long will this project take?
A. 44
B. 40
C. 52
D. 48
mohossamaraslan@icloud.com 59
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
You have a project with the following tasks: Task 1 can start immediately and has an
estimated duration of four. Task 2 can start after Task 1 is completed and has an
estimated duration of eight. Task 3 can start after Task 2 is completed and has an
estimated duration of five. Task 4 can start after Task 1 is completed and has an
estimated duration of eight. Task 5 has an estimated duration of three and must
take place concurrently with Task 3. It can start after Tasks 4 and 2. What is the
A. 15.
B. 18.
C. 17.
D. 12.
mohossamaraslan@icloud.com 60
Eng. Mohamed Raslan, PMP
+2-0100-535-4327
Lecture 03 : Project Schedule Management
5. Develop Schedule (Planning)
Resource Optimization
Resource Resource
leveling. Smoothing
✓ Can be used when a resource has been assigned to two or more activities during the same time period.
عندما يتم تعيي مورد لنشاطي أو ر
.أكي خالل نفس الفية الزمنية ر ر
✓ Resource leveling can often cause the original critical path to change.
.األصىل
ي تغيي المسار الحرج
كثي من األحيان ر
المساواة ريي الموارد يمكن أن تسبب يف ر
✓ Resource smoothing, as opposed to resource leveling, the project’s critical path is not changed and
the completion date may not be delayed.
✓ Activities may only be delayed within their free and total float.
✓ The project’s critical path is not changed and the completion date may not be delayed.
للمشوع وقد ال يتأخر تاري خ االنتهاء ر
للمشوع تغيي المسار الحرج ر
ال يتم ر
TT ❑ Data Analysis
ر
➢ What-if scenario analysis .االفتاض تحليل الخيارات
• Is the process of evaluating scenarios in order to predict their effect, positive or negative, on project
objectives. ex ( a Strike ) االضاب
عىل اهداف ر،السلت
.المشوع اإليجان أو ،يتأثيها
هو عملية تقييم السيناريوهات من أجل التنبؤ ر
ري ري
➢ Simulation محاكاة
• Simulation models the combined effects of individual project risks and other sources of uncertainty to evaluate
their potential impact on achieving project objectives.
تأثيها المحتمل عىل تحقيق أهداف ر
المشوع وغيها من مصادر الشك لتقييم ر التأثيات لمخاطر ر
المشوع الفردية ر ر مجموعة من
• Schedule compression techniques are used to shorten or accelerate the schedule duration without reducing
the project scope. لتقصي أو تعجيل مدة الجدول الزمت دون التقليل من نطاق ر
.المشوع ر الزمت تستخدم أساليب ضغط الجدول
ي ي
❑ Fast tracking: Activities are performed in parallel. تنفذ األنشطة عىل التوازي
• An example is constructing the foundation for a building before completing all of the architectural drawings.
مثال ذلك يناء األساس لمبت قبل إتمام كافة الرسومات المعمارية
• Fast tracking may result in rework and increased risk. إعادة تنفيذ العمل وزيادة المخاطر
1 2 3 4 5
6 7 8 9 10
11 12 13 14 15
Normal
1 2 3 4 5
4 5 6 7 8
Fast Tracking 7 8 9 10 11
High Risk
1 2 3
4 5 6 7
Crashing 8 9 10
High Cost
• Is the approved version of a schedule model that can be changed only through formal change control procedures.
الزمت
ي هو اإلصدار المعتمد لنموذج الجدول
• Used as a basis for comparison to actual results. يستخدم كأساس للمقارنة مع النتائج الفعلية
• During monitoring and controlling, the approved baseline dates are compared to the actual start and
finish dates to determine if variances have occurred.
المرجع المعتمدة يتواري خ البدء واالنتهاء الفعلية لتحديد ما إذا وجدت هذه الفروق
ي يتم مقارنة تواري خ الخط،أثناء المراقبة والتحكم
Bar charts
• Also known as Gantt charts, bar charts
Milestone charts
• Only identify the scheduled start or completion of major deliverables and key external interfaces
.الزمت أو استكمال التسليمات الرئيسية والواجهات الخارجية الرئيسية
ي تحدد فقط بداية الجدول
O ❑ Change Request
• Modifications to the project scope or project schedule may result in change requests to the scope
baseline, and/or other components of the project management plan.
وغيها من مكونات
المرجع للنطاق ر تغيي عىل الخط المشوع أو الجدول الزمت ر
للمشوع طلبات ر من الممكن أن ينتج عن إجراء تعديالت عىل نطاق ر
ي ي
خطة إدارة ر
المشوع
Schedule
Management
• Monitoring the status of the project to update the project schedule and managing changes to the
schedule baseline.
.الزمت المرجع للجدول الت تطرأ عىل الخط المشوع من أجل تحديث الجدول الزمت ر
• عملية مراقبة حالة ر
ي ي التغييات ي
ر للمشوع وإدارة ي
( 6 ) Control Schedule
Tools &
Input Techniques Outputs
TT ❑ Data analysis
Measure, compare, and analyze schedule performance against the schedule baseline such as actual
start and finish dates, percent complete, and remaining duration for work in progress.
والنسبة المئوية،الزمت مثل التواري خ الفعلية للبدء واالنتهاء
ي المرجع للجدول
ي الزمت مقابل الخط
ي قياس ومقارنة وتحليل أداء الجدول
والفية المتبقية للعمل الجاري،لالكتمال
❑ Trend analysis تحليل االتجاه
Examines project performance over time to determine whether performance is improving or deteriorating.
يفحص تحليل االتجاه أداء ر
المشوع بمرور الوقت لتحديد ما إذا كان األداء يتحسن أم ينحدر
A- Decomposition
C- Expert judgment
D- Deconstruction
Q1) You are the project manager of a project. As part of the planning process, you
use a planning technique to subdivide the project scope and deliverables into
smaller, more manageable components. What is this technique called?
A- Decomposition
C- Expert judgment
D- Deconstruction
PMBOK 158
Correct answer is ( A ). Decomposition is the process of
subdividing the project scope and deliverables into smaller,
more manageable components. [PMBOK 6th edition, Page 158]
VERY IMPORTANT
Q3) You are completing the sequence of activities and note that one of your
activities can not proceed until consent is granted by the local government agency.
This is an example of what sort of dependency?
A- Discretionary
B- External
C- Environmental
D- Mandatory
Q3) You are completing the sequence of activities and note that one of your
activities can not proceed until consent is granted by the local government agency.
This is an example of what sort of dependency?
A- Discretionary
B- External
C- Environmental
D- Mandatory
PMBOK 192
Correct answer is ( B ). External dependencies involve a
relationship between project activities and nonproject
activities. These dependencies are usually outside of the
project team’s control. [PMBOK 6th edition, Page 192]
A- Lead
B- Free Float
C- Lag
D- Total Float
Q4) The amount of time an activity can be delayed without delaying any successor
activity, is known as:
A- Lead
B- Free Float
C- Lag
D- Total Float
PMBOK 210
Correct answer is ( B ). Free Float is the amount of time that a
schedule activity can be delayed without delaying the early
start date of any successor or violating a schedule constraint.
PMBOK® Guide, 6th Ed; Ch 6, Pg 210
A- Expert Judgment
B- Bottom-Up Estimating
C- Alternative Analysis
A- Expert Judgment
B- Bottom-Up Estimating
PMBOK 202
Correct answer is ( B ). Think about which of the answer
C- Alternative Analysis choices enables the highest degree of activity decomposition.
The duration cannot be estimated because the activities are
D- Published Estimating Data complex. Therefore, the best way is to further decompose the
activities into smaller parts to develop a better estimate. This
technique is called Bottom-Up Estimating.
A- Lead time
B- Project float
C- Constraint
D- Lag
Q7) You are the project manager of a construction company. You know that the
builders start painting the walls 30 days after they start installing the drywall. This
waiting time can also be referred to as:
A- Lead time
B- Project float
PMBOK 190
PMBOK 215
PMBOK 200
12+8+10 / 3 = 10
C- Parametric estimating
C- Parametric estimating
A- Define Activities
B- Decomposition
C- Define Scope
D- Sequence Activities
Q21) In any project there are deliverables that need to be produced. These
deliverables are produced during the executing phase as the team carries out their
assigned activities. During the planning phase, you wish to identify and document the
specific actions to be performed to produce the deliverables. This is done as part of:
A- Define Activities
B- Decomposition
C- Define Scope
PMBOK 183
D- Sequence Activities Correct answer is ( A ). Define Activities is the process of
identifying and documenting the specific actions to be
performed to produce the project deliverables. [PMBOK 6th
edition, Page 183]
A- Fast track the project to ensure that the project schedule is not delayed
B- Increase risk
C- Ensure activities are done in parallel, which would normally be done in sequence
D- Help shorten the project schedule without changing the project scope
Q23) Your project SPI is 0.86, and the management has recommended that you
should fast track the project. You agree with the management, but caution them that
fast-tracking could:
B- Increase risk
C- Ensure activities are done in parallel, which would normally be done in sequence
D- Help shorten the project schedule without changing the project scope
PMBOK 215
Correct answer is ( B ). Fast-tracking may result in rework and
increased risk. [PMBOK 6th edition, Page 215]