Model :- 18M TOWER FOR 4NOs.

10m3 PLASTIC TANK


Phase name Qty
Phase 1 4

2 391

TNK1
2 391

2 570
Top View
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 4 parts named '1000LTRS PLASTIC TANK' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
TNK1 Object-9 COMPONENT 2391 33.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE 1000LTRS PLASTIC ***


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 4 parts 9564 132.2 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:15 Workshop Drawing Rev
Revised:
4 required for 4 '1000LTRS PLASTIC TANK' marked TNK1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [TNK.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 3

30 °
57.8

57.8
° 30

100 100

87 87
0

87

1 099

1 186
Top View

1 186

TB2

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 3 parts named 'tie beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
TB2 SHS50*50*3.0 S275. 1186 0.2 5.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE tie beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 3 parts 3557 0.7 14.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
3 required for 3 'Rafter' marked R1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [TB.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 4

TB1

1 425

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 4 parts named 'tie beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
TB1 SHS50*50*3.0 S275. 1425 0.3 6.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE tie beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 4 parts 5700 1.1 23.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
4 required for 4 'tie beam' marked TB1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [TB.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

32
2 ~Ø 14 2 ~Ø 14

30 60 126 60

30

90

216

276
Top View

306
306
0

SPL2
2 ~Ø 14 2 ~Ø 14
32

62 60 63 60
0

62

122

184

244
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'LADDER SPLICE JOINT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
SPL2 RSA65*65*4 S275. 306 0.1 1.2 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LADDER SPLICE JOINT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 612 0.2 2.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
2 required for 2 'LADDER SPLICE JOINT' marked SPL2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [SPL.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 3

122

184

244
62
62 60 63 60

0
26
2 ~Ø 14 2 ~Ø 14

Top View

30

216

276
90
30 60 126 60
0

2 ~Ø 14
SPL1
26

306
0

306
2 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 3 parts named 'LADDER SPLICE JOINT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
SPL1 RSA50*50*4 S275. 306 0.1 0.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LADDER SPLICE JOINT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 3 parts 918 0.2 2.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
3 required for 3 'LADDER SPLICE JOINT' marked SPL1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [SPL.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 16

1 375

SB2

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 16 parts named 'Seconary Beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
SB2 RHS100*50*4.0 S275. 1375 0.4 11.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Seconary Beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 16 parts 22000 6.3 189.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
16 required for 16 'Seconary Beam' marked SB2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [SB.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 20

3 100

SB1

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 20 parts named 'Seconary Beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
SB1 RHS100*50*4.0 S275. 3100 0.9 26.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Seconary Beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 20 parts 62000 17.7 532.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
20 required for 20 'Seconary Beam' marked SB1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [SB.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

2 029
2 000
29

57.8

100
30
°
Top View

2 029

R1

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 3 parts named 'Rafter' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
R1 SHS50*50*3.0 S275. 2029 0.4 8.5 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Rafter


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 3 parts 6087 1.2 25.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
6 required for 3 'Rafter' marked R1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [R.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 12

6
Top View

150

130
20
20 110
0

PLT6

4 ~Ø 14
120

70
25

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
Material list for 12 parts named 'Cap Plate' 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Mark Profile Grade Length Paint Area Mass PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
PLT6 PLT6*120 S275. 150 0.0 0.8 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
Total for 12 parts 1800 0.5 10.2 BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Cap Plate


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.

The part shown is required for the following assemblies:- Issued:


6 required for 6 'COLUMN' marked C3 Scale: 1:1 Workshop Drawing Rev
Revised:
6 required for 3 'Rafter' marked R1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [PLT.6] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 12

8
Top View

212

300
87
87 88

0
PLT5

150

300

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 12 parts named 'Side Plate' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PLT5 PLT8*150 S275. 300 0.1 2.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Side Plate


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 12 parts 3600 0.8 33.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
12 required for 6 'COLUMN' marked C1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [PLT.5] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

6
Top View

50

PLT1

50

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'PLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PLT1 PLT6*50 43A 50 0.0 0.1 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE PLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 100 0.0 0.2
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 2 'ANCHOR ROD' marked HD3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [PLT.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 24

6
Top View

50

PL1

50

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 24 parts named 'PLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PL1 PLT6*50 43A 50 0.0 0.1 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE PLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 24 parts 1200 0.1 2.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
24 required for 24 'PLATE' marked PL1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [PL.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 12

3 600

P1

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 12 parts named 'Purlin' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
P1 SHS50*50*2 S275. 3600 0.7 10.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Purlin


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 12 parts 43200 8.6 130.2
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
12 required for 12 'Purlin' marked P1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [P.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 12

2 875

MB3

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 12 parts named 'Main Beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
MB3 RHS150*100*6.0 S275. 2875 1.4 62.4 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Main Beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 12 parts 34500 16.5 748.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
12 required for 12 'Main Beam' marked MB3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [MB.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 16

1 375

MB2

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 16 parts named 'Main Beam' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
MB2 RHS150*100*6.0 S275. 1375 0.7 29.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Main Beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 16 parts 22000 10.5 477.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
16 required for 16 'Main Beam' marked MB2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [MB.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

28

61 60 2 ~Ø 14
0

61

121

Top View

1 275

2 025

2 775

3 525
30

90

525

30 60 435 750 750 750 750


0

1 ~Ø 14
LD2
28

25
5 650
0

5 650
2 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
LD2 RSA50*50*6 S355JR 5650 1.1 25.4 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 5650 1.1 25.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:5 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [LD.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

0 13

13
2 ~Ø 14

28
26.8 9 692 60
15° 0

9 692
9 752
100

Top View

9 723
9 783
1 342

2 092

2 842

3 592

4 342

5 092

5 842

6 592

7 342

8 092

8 842

9 591
179

692

179 512 650 750 750 750 750 750 750 750 750 750 750 750 132 60
0

1 ~Ø 14

LD1
25

28
9 813
2 ~Ø 14
0

9 813
1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
LD1 RSA50*50*6 S355JR 9813 1.9 44.1 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 9813 1.9 44.1
Issued:
The part shown is required for the following assemblies:- Scale: 1:10 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [LD.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 9

HR10

1 375

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 9 parts named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR10 CHS42.8*2.0 S235JR 1375 0.2 2.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 9 parts 12371 1.7 24.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
9 required for 9 'GUARD RAIL SUPPORT' marked HR10 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.10] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

2 878

HR9

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR9 CHS42.8*2.0 S235JR 2878 0.4 5.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 2878 0.4 5.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
1 required for 1 'GUARD RAIL SUPPORT' marked HR9 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.9] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

HR8

493
921

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR8 CHS42.8*2.0 S235JR 1814 0.2 3.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 1814 0.2 3.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:6 Workshop Drawing Rev
Revised:
1 required for 1 'GUARD RAIL SUPPORT' marked HR8 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.8] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 3

HR7

1 425

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 3 parts named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR7 CHS42.8*2.0 S235JR 1425 0.2 2.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 3 parts 4275 0.6 8.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
3 required for 3 'GUARD RAIL SUPPORT' marked HR7 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.7] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

HR6

2 925

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR6 CHS42.8*2.0 S235JR 2925 0.4 5.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 5850 0.8 11.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 2 'GUARD RAIL SUPPORT' marked HR6 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.6] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 5

2 875

HR5

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 5 parts named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR5 CHS42.8*2.0 S235JR 2875 0.4 5.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 5 parts 14375 1.9 28.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
5 required for 5 'GUARD RAIL SUPPORT' marked HR5 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.5] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 3

HR3

479
479
913

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 3 parts named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HR3 CHS42.8*2.0 S235JR 1779 0.2 3.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 3 parts 5337 0.7 10.7
Issued:
The part shown is required for the following assemblies:- Scale: 1:6 Workshop Drawing Rev
Revised:
3 required for 3 'GUARD RAIL SUPPORT' marked HR3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HR.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

HD3

244

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'ANCHOR ROD' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HD3 ROD12 8.8 244 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE ANCHOR ROD


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 488 0.0 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 2 'ANCHOR ROD' marked HD3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HD.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

HD2

394

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'ANCHOR ROD' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HD2 ROD20 8.8 394 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE ANCHOR ROD


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 2364 0.1 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
6 required for 6 'ANCHOR ROD' marked HD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HD.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 18

HD1

394

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 18 parts named 'ANCHOR ROD' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
HD1 ROD20 8.8 394 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE ANCHOR ROD


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 18 parts 7092 0.4 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
18 required for 18 'ANCHOR ROD' marked HD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [HD.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

22
2 ~Ø 14
8 294 60
0

8 294

8 354
Top View

1 061

1 573

8 325

8 385
25

450

25 425 611 512 6 752 60


0

2 ~Ø 14
1 ~Ø 14 GS6

22
20

8 415
0

8 415
1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS6 L40*40*3 S355JR 8415 1.3 15.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 8415 1.3 15.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:3 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS6 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.6] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

1 ~Ø 14

20

22
1 ~Ø 14
25 1 036 512 1 ~Ø 14 2 ~Ø 14
0

25

1 061

1 573
Top View

8 325

8 385
8 325 60
0

2 ~Ø 14
GS5

22
8 294 60
0

8 294

8 354
8 415
0

8 415
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS5 L40*40*3 S355JR 8415 1.3 15.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 8415 1.3 15.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:2.5 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS5 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.5] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

22
5 708 60 2 ~Ø 14
0

5 708

5 768
Top View

5 830
1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14
5 830
0

1 ~Ø 14 GS4 2 ~Ø 14
20

22
25 750 750 750 750 750 750 1 215 60
0
25

775

1 525

2 275

3 025

3 775

4 525

5 740

5 800
1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS4 L40*40*3 S355JR 5830 0.9 10.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 5830 0.9 10.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:5 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS4 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.4] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

22

2 ~Ø 14
61 60
0

61

121

Top View

1 305

2 055

2 805

3 555

4 305

5 055

5 805
30

90

555
0

30 60 465 750 750 750 750 750 750 750


2 ~Ø 14 1 ~Ø 14
GS3
22

20
5 830
0

5 830
1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS3 L40*40*3 S355JR 5830 0.9 10.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 5830 0.9 10.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:7 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

2 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

20
22

555 750 750 750 750 750 750 750


0

555

1 305

2 055

2 805

3 555

4 305

5 055

5 805
Top View
30

90

30 60
0

GS2
22

2 ~Ø 14
61 60
0

61

121

5 830
0

5 830
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS2 L40*40*3 S355JR 5830 0.9 10.8 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 5830 0.9 10.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:6 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

22

2 ~Ø 14
62 60
0
62
122

Top View

8 415
1 ~Ø 14 1 ~Ø 14
8 415
0

2 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14
GS1
22

20
30 102 750 750 750 750 750 750 750 750 650 512 611 425
60
0

192

942

1 692

2 442

3 192

3 942

4 692

5 442

6 192

6 842

7 354

7 965

8 390
30
90

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAGE STRAP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
GS1 L40*40*3 S355JR 8415 1.3 15.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAGE STRAP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 8415 1.3 15.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:9 Workshop Drawing Rev
Revised:
1 required for 1 'CAGE STRAP' marked GS1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [GS.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

100
°
45
100
45

100
°

100

1 820
52 52 1 768
0

25
1 ~Ø 10 1 ~Ø 10

50 50
0

50

1 816

1 866
Top View

CTT6

1 866

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT6 RSA50*50*4 S355JR 1866 0.4 5.7 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 3732 0.7 11.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
2 required for 2 'CASTING TEMPLATE' marked CTT6 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.6] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

100
45
°

100
°
45
100

1 814
100

46
46 1 768
0
25

1 ~Ø 10 1 ~Ø 10

50 50
0

50

1 816

1 866
Top View

CTT5

1 866

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT5 RSA50*50*4 S355JR 1866 0.4 5.7 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 3732 0.7 11.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
2 required for 2 'CASTING TEMPLATE' marked CTT5 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.5] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

25
1 ~Ø 10 1 ~Ø 10

70 2 800
0

70

2 870
Top View

CTT4

2 940
0

2 940
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT4 RSA50*50*4 S355JR 2940 0.6 9.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 2940 0.6 9.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
1 required for 1 'CASTING TEMPLATE' marked CTT4 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.4] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

1 220

1 370

1 570

1 720

2 870

3 070
70

570

70 500 650 150 200 150 1 150 200


0
25

1 ~Ø 10 1 ~Ø 10 1 ~Ø 10 2 ~Ø 10 1 ~Ø 10 2 ~Ø 10

Top View

3 470
3 470
0

CTT3

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT3 RSA50*50*4 S355JR 3470 0.7 10.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 3470 0.7 10.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:5 Workshop Drawing Rev
Revised:
1 required for 1 'CASTING TEMPLATE' marked CTT3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

1 ~Ø 10 1 ~Ø 10 2 ~Ø 10 1 ~Ø 10
25

2 ~Ø 10
70 1 150 150 200 150 1 150 200
0

70

1 220

1 370

1 570

1 720

2 870

3 070
Top View

CTT2

3 470
0

3 470
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT2 RSA50*50*4 S355JR 3470 0.7 10.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 3470 0.7 10.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:4 Workshop Drawing Rev
Revised:
1 required for 1 'CASTING TEMPLATE' marked CTT2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

1 220

1 720

2 870

3 070
70

70 1 150 500 1 150 200


0
25

1 ~Ø 10 1 ~Ø 10 1 ~Ø 10 2 ~Ø 10

Top View

3 470
3 470
0

CTT1

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'CASTING TEMPLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CTT1 RSA50*50*4 S355JR 3470 0.7 10.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING TEMPLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 6940 1.3 21.2
Issued:
The part shown is required for the following assemblies:- Scale: 1:4 Workshop Drawing Rev
Revised:
2 required for 2 'CASTING TEMPLATE' marked CTT1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CTT.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 4

85 2880 85

85

2965
3050
3096 3100

110
108
2988 2990

1380

1380
CQP1
1608 1610

10
120

120
1488 1490

3 050

Front View
1380

1380

108 110
108

110

Rev Mark Revision Description Date


3050

GENERAL NOTE:
85

2963

1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE


CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
85 2878 87 ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 4 parts named 'CHEQ'D PL2.1' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Top View Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CQP1 CHEQ'D PLATE S275. 3050 19.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CHEQ'D PL2.1


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 4 parts 12200 76.1 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:5 Workshop Drawing Rev
Revised:
4 required for 4 'CHEQ'D PL2.1' marked CQP1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CQP.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

Top View

CPL1

4 ~Ø 22
100
280

2 ~Ø 10
100

1 ~Ø 10
40

40 100 100
0

40

140

240

280

Front View Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named ' CASTING PLATE' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CPL1 PLT4*280 43A 280 0.2 2.5 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CASTING PLATE


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 1680 1.0 14.8
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
6 required for 6 ' CASTING PLATE' marked CPL1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CPL.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

100
15°
26.8

13

727
740
Top View

CLT21

740

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT21 RSA50*50*6 S355JR 740 0.1 3.3 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 740 0.1 3.3
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.21] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

192

192
179
100
15°
13

26.8 CLT20

13
0

13

26.8

100
15°
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT20 RSA50*50*6 S355JR 192 0.0 0.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 192 0.0 0.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.20] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1
100
15°

26.8

13
0

13

Top View

740

CLT19

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT19 RSA50*50*6 S355JR 740 0.1 3.3 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 740 0.1 3.3
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.19] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

100
15°
192 26.8

13
13

0
CLT18

13

179
192
26.8
100
15°

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT18 RSA50*50*6 S355JR 192 0.0 0.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 192 0.0 0.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.18] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

28
2 ~Ø 14
5 529 60
0

5 529

5 589
Top View

5 650
5 650
0

5 620
5 560
5 560 60
0

CLT17 2 ~Ø 14

28
25

1 ~Ø 14
2 125 750 750 750 750
0

2 125

2 875

3 625

4 375

5 125
1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT17 RSA50*50*6 S355JR 5650 1.1 25.4 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 5650 1.1 25.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:4 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.17] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 50

CLT16

458
0

458
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
Material list for 50 parts named 'LADDER RUNGS' 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Mark Profile Grade Length Paint Area Mass PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
CLT16 RSA40*40*4 S355JR 458 0.1 0.8 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
Total for 50 parts 22900 3.5 42.4 BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LADDER RUNGS


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.

The part shown is required for the following assemblies:- Issued:


32 required for 1 'CAT LADDER' marked LD1 Scale: 1:1 Workshop Drawing Rev
Revised:
18 required for 1 'CAT LADDER' marked LD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.16] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

25
25

0
CLT15

1 ~Ø 14

25
50
0

50
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT15 RSA50*50*6 S355JR 50 0.0 0.2 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 100 0.0 0.4
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 1 'CAT LADDER' marked LD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.15] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

9 800 9 813
13
28

2 ~Ø 14
61 60 26.8
0
61
121

100
15°
Top View
30
90
0

30 1 ~Ø 14
60
1 ~Ø 14
2 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14 1 ~Ø 14
CLT14
28

25
1 ~Ø 14
222 750 750 750 750 750 750 750 750 750 750 750 650 512
0

222

972

1 722

2 472

3 222

3 972

4 722

5 472

6 222

6 972

7 722

8 472

9 122

9 634
9 813

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'CAT LADDER' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT14 RSA50*50*6 S355JR 9813 1.9 44.1 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE CAT LADDER


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 9813 1.9 44.1
Issued:
The part shown is required for the following assemblies:- Scale: 1:10 Workshop Drawing Rev
Revised:
1 required for 1 'CAT LADDER' marked LD1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.14] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

CLT13

10

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'NUT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT13 M12_NUT 8.8 10 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE NUT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 20 0.0 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 2 'ANCHOR ROD' marked HD3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.13] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 1

CLT10

479

500
19

RD 19 459 21

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 1 part named 'GUARD RAIL SUPPORT' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CLT10 CHS42.8*2.0 S235JR 500 0.1 1.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 1 part 500 0.1 1.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
1 required for 1 'GUARD RAIL SUPPORT' marked HR8 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.10] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

391

438
46

2
17
Top View

438
438
0

391
380

438
380 10 47
0

CLT9

6
2
Front View

19
2
391 1 46
0

392 391

438
Bottom View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.

Material list for 6 parts named 'GUARD RAIL SUPPORT' 2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
Mark Profile Grade Length Paint Area Mass 4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE

CLT9 CHS42.8*2.0 S235JR 438 0.1 0.9 PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Total for 6 parts 2625 0.4 5.3 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

The part shown is required for the following assemblies:- 7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE
ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
GUARD RAIL SUPPORT

2 required for 2 'GUARD RAIL SUPPORT' marked HR6 Issued:


3 required for 3 'GUARD RAIL SUPPORT' marked HR7 Scale: 1:2 Workshop Drawing Rev
Revised:
1 required for 1 'GUARD RAIL SUPPORT' marked HR8 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.9] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 5

17
2
47

391

438
Top View

438
438
0

391
380

438
380 11 46
0

CLT8

6
2
Front View

391

438
46

2
19
Bottom View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
Material list for 5 parts named 'GUARD RAIL SUPPORT' 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Mark Profile Grade Length Paint Area Mass PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
CLT8 CHS42.8*2.0 S235JR 438 0.1 0.9 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
Total for 5 parts 2188 0.3 4.4 BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE GUARD RAIL SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.

The part shown is required for the following assemblies:- Issued:


2 required for 2 'GUARD RAIL SUPPORT' marked HR6 Scale: 1:2 Workshop Drawing Rev
Revised:
3 required for 3 'GUARD RAIL SUPPORT' marked HR7 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.8] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 47

479

500
21

21 457 21
0

CLT7

Front View

Rev Mark Revision Description Date


Material list for 47 parts named 'GUARD RAIL SUPPORT'
Mark Profile Grade Length Paint Area Mass GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CLT7 CHS42.8*2.0 S235JR 500 0.1 1.0 CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH

Total for 47 parts 23500 3.2 47.2 ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
The part shown is required for the following assemblies:- PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
3 required for 3 'GUARD RAIL SUPPORT' marked HR3 PLATE

20 required for 5 'GUARD RAIL SUPPORT' marked HR5 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

8 required for 2 'GUARD RAIL SUPPORT' marked HR6 7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE
ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
GUARD RAIL SUPPORT

3 required for 3 'GUARD RAIL SUPPORT' marked HR7 Issued:


4 required for 1 'GUARD RAIL SUPPORT' marked HR9 Scale: 1:1 Workshop Drawing Rev
Revised:
9 required for 9 'GUARD RAIL SUPPORT' marked HR10 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.7] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 33

438
21

21 416
0

CLT6

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
Material list for 33 parts named 'GUARD RAIL SUPPORT' 1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
Mark Profile Grade Length Paint Area Mass ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
CLT6 CHS42.8*2.0 S235JR 438 0.1 0.9 4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE

Total for 33 parts 14439 1.9 29.0


PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE

The part shown is required for the following assemblies:- 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

3 required for 3 'GUARD RAIL SUPPORT' marked HR3 7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE
ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
GUARD RAIL SUPPORT

10 required for 5 'GUARD RAIL SUPPORT' marked HR5 Issued:


2 required for 1 'GUARD RAIL SUPPORT' marked HR9 Scale: 1:1 Workshop Drawing Rev
Revised:
18 required for 9 'GUARD RAIL SUPPORT' marked HR10 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.6] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 68

CLT5

879 21

Front View

Material list for 68 parts named 'GUARD RAIL SUPPORT' Rev Mark Revision Description Date
Mark Profile Grade Length Paint Area Mass
CLT5 CHS42.8*2.0 S235JR 900 0.1 1.8 GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
Total for 68 parts 61200 8.2 123.0 2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
The part shown is required for the following assemblies:- 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
3 required for 3 'GUARD RAIL SUPPORT' marked HR3 PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
25 required for 5 'GUARD RAIL SUPPORT' marked HR5 PLATE

10 required for 2 'GUARD RAIL SUPPORT' marked HR6 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

6 required for 3 'GUARD RAIL SUPPORT' marked HR7 7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE
ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
GUARD RAIL SUPPORT

1 required for 1 'GUARD RAIL SUPPORT' marked HR8 Issued:


5 required for 1 'GUARD RAIL SUPPORT' marked HR9 Scale: 1:1 Workshop Drawing Rev
Revised:
18 required for 9 'GUARD RAIL SUPPORT' marked HR10 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.5] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 56

168

571

705
0 168 134

CLT4
75

75
75

75
705

100 89.3
89.3

100
.

41
41

.8
°
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
Material list for 56 parts named 'Main Beam' 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Mark Profile Grade Length Paint Area Mass PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
CLT4 RHS150*100*6.0 S275. 705 0.3 15.3 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
Total for 56 parts 39497 18.9 857.1 BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE Main Beam


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.

The part shown is required for the following assemblies:- Issued:


32 required for 16 'Main Beam' marked MB2 Scale: 1:2 Workshop Drawing Rev
Revised:
24 required for 12 'Main Beam' marked MB3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CLT.4] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 2

1 ~Ø 14

313
0

313
1 ~Ø 14

R
R 324.5
327.5
655

Top View

639
313

313
0

CG2
50
25

1 ~Ø 14
Rev Mark Revision Description Date
Front View GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 2 parts named 'SAFETY HOOP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CG2 PLT3*50 43A 1649 0.2 1.9 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE SAFETY HOOP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 2 parts 3297 0.3 3.9
Issued:
The part shown is required for the following assemblies:- Scale: 1:5 Workshop Drawing Rev
Revised:
2 required for 2 'SAFETY HOOP' marked CG2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CG.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 19

1 ~Ø 14

1 ~Ø 14

25
0
25

1 ~Ø 14

R
R 324.5
327.5

655

Top View

640
25
0

25

1 ~Ø 14
CG1
50
25

1 ~Ø 14
313
0

313

Front View Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 19 parts named 'SAFETY HOOP' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
CG1 PLT3*50 43A 1699 0.2 2.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE SAFETY HOOP


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 19 parts 32286 3.4 38.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:6 Workshop Drawing Rev
Revised:
19 required for 19 'SAFETY HOOP' marked CG1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [CG.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

100
30
57.8

2 498

C3

38
38
43

2 454

2 498
Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'COLUMN' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
C3 SHS75*75*4.0 S275. 2498 0.7 22.4 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE COLUMN


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 14987 4.3 134.6
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
6 required for 6 'COLUMN' marked C3 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [C.3] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

5 980

C2

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'COLUMN' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
C2 SHS125*125*6.0 S275. 5980 2.7 122.6 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE COLUMN


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 35880 16.5 735.5
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
6 required for 6 'COLUMN' marked C2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [C.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

9 480

C1

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'COLUMN' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
C1 SHS125*125*6.0 S275. 9480 4.4 194.3 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE COLUMN


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 56880 26.1 1166.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:1 Workshop Drawing Rev
Revised:
6 required for 6 'COLUMN' marked C1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [C.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

228

6
6

0
A2

114

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'LINKS' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
A2 ROD6 8.8 888 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LINKS


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 5328 0.1 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
6 required for 6 'LINKS' marked A2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [A.2] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 6

228

6
6

0
A1

114

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Material list for 6 parts named 'LINKS' PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
Mark Profile Grade Length Paint Area Mass
6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
A1 ROD6 8.8 888 0.0 0.0 PO BOX 59401-000100
DIMENSIONS.
BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LINKS


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.
Total for 6 parts 5328 0.1 0.0
Issued:
The part shown is required for the following assemblies:- Scale: 1:2 Workshop Drawing Rev
Revised:
6 required for 6 'LINKS' marked A1 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [A.1] 0
Model :- 18M TOWER FOR 4NOs. 10m3 PLASTIC TANK
Phase name Qty
Phase 1 8

162

10

Front View

Rev Mark Revision Description Date

GENERAL NOTE:
1.) ALL DIMENSIONS AND LEVELS ARE TO BE VERIFIED ON SITE BY THE
CONTRACTOR BEFORE COMMENCING ANY WORK.
2.) THE STRUCTURAL DRAWINGS TO BE READ IN CONJUCTION WITH
ARCHITECTURAL & M.E DRAWINGS.
CLIENT/OWNER: PROJECT DESIGNATION:
Material list for 8 parts named 'LADDER SUPPORT' 3.) ALL STRUCTURAL TO BE GRADE S355
4.) ALL STEELWORK SHALL BE PRIMED WITH ONE COAT OF RED OXIDE
Mark Profile Grade Length Paint Area Mass PRIMER AT SHOP AND ONE COAT AFTER ERECTION.
CONSULTANT: PROPOSED ELEVATED H20 TANK SUPPORT FRAME
Cransfield Engineers
5.) ENDS OF HOLLOW SECTIONS SHALL BE BLANKED WITH 3MM THICK
PLATE
10 CHS42.8*3.0 S275. 162 0.0 0.5 6.) THE FABRICATOR SHALL CHECK ON SITE TO VERIFY ALL (Consulting Civil & Structural Engineers) ADDRESS/LOCATION: TITLE:
PO BOX 59401-000100
DIMENSIONS.
Total for 8 parts 1300 0.2 3.8 BOMET COUNTY
NAIROBI
Tekla structures

7.) APPROVAL OF SHOPDRAWINGS TO BE SOUGHT FROM THE LADDER SUPPORT


ENGINEER BEFORE COMMENCEMENT OF FABRICATION.

The part shown is required for the following assemblies:- Issued:


6 required for 1 'CAT LADDER' marked LD1 Scale: 1:1 Workshop Drawing Rev
Revised:
2 required for 1 'CAT LADDER' marked LD2 Drawn By: Date:28.08.2023 Checked by: Approved By: Project Number: 0719 W [10] 0