METHOD STATEMENT
TITLE
HOSSAM
04 13-05-2023 KARIM MAHMOUED
HAMOUAD
HSE SUPERVIOR PROJECT MANGER
Sub - Contractor:
SEAWORLD ABU DHABI MS Ref no:
METHOD STATEMENT FOR CAR PARK SHED Date:
INVERTER INSTALLATION Page 2 of 15
CONTENTS
1. PURPOSE:....................................................................................................................................................
2. SCOPE OF WORK:.....................................................................................................................................
3. REFERENCES:............................................................................................................................................
4. ABBREVIATIONS:.....................................................................................................................................
5. ROLE AND RESPONSIBILITIES..............................................................................................................
6. MATERIALS:..............................................................................................................................................
7. WORK SEQUENCE:...................................................................................................................................
7.1 Preliminary Activities:.............................................................................................................................7
7.2 Pre-Construction Activities:.....................................................................................................................7
7.3 Methodology _ Construction Activities............................................................................................8
7.4 Carpark shade Inverter Installation………………………………………………………………………
7.5 Drawings for Inverters Installation on Car Park
Sub - Contractor:
SEAWORLD ABU DHABI MS Ref no:
METHOD STATEMENT FOR CAR PARK SHED Date:
INVERTER INSTALLATION Page 3 of 15
1. PURPOSE:
Purpose of this Method Statement For Car Park Shade Inverters Installation in accordance with the standards &
specifications -
2. SCOPE OF WORK:
This method statement explains the procedure for Car Park Shade Inverters Installation in SeaWorld guest
car park and staff car park areas
3. REFERENCES:
4. ABBREVIATIONS:
Client MIRAL
Project Manager ELLISDON
Engineer AECOM
Contractor ALEC Engineering and Contracting L.L.C
Sub-Contractor CES/GFTS
PE Project Engineer
QCM QA/QC Manager
SE Site Engineer
QCE Quality Control Engineer
CRM Safety Manager
ITP Inspection and Test Plan
MSS Method Statement Submittal
QCP Quality Control Plan
TS Technical submittal Request
NCR Non-Conformance Report
SD Shop Drawing
CD Contract Drawing Issued for Construction
CL Check List
RA Risk Assessment
MS Material Submittal
MRS Material Reference Schedule
IR Inspection Request
PSSP Project safety security plan
HSE Health, Safety & Environment
ADM Abu Dhabi Municipality
OSHAD Abu Dhabi Occupational Safety and Health Center (OSHAD)
Brief details of role and responsibilities of key personals involved in the activity are given below.
Project Manager
Overall responsible for the implementation of this method statement with detail activities as delegated to
the Construction. Which includes but not limited to approving safety programs and ensuring that all aspects
of the program are implemented and adhered to.
He also ensures managerial staff of the Project team is aware of the HSE requirements and are
implementing the same during the Project execution.
To ensure that all reasonably practicable measures are taken to protect and promote the Health, safety and
welfare of the workforce and to protect the environment
Shall provide full support to HSEMS to ensure that all site managers and supervision staffs take
responsibility of HSE
Construction Manager
Responsible for the coordination with Project Engineers, Site Engineer, Foremen, and Surveyors will ensure
that the installation of activities as carried out according to the drawings and specifications.
Promote a culture in which HSE are the prime concern that shall never be compromised.
Shall monitor and review the overall project HSE performance and implement timely mitigation and
corrective action(s).
To ensure that the installation of activities as carried out according to the approved drawings and
specifications.
Make sure HSE are the prime concern that shall never be compromised through constant training and
supervision by HSE team.
Ensure that safe systems of work are defined and documented, and that hazard analysis and risk control
methods have been incorporated during the preparation
QA/QC Engineer
To ensure that site personnel are aware of requirements and that works are carried out as per project’s
requirements. They are responsible for the implementation of related QA/QC activities as detailed in
relevant QCP’s and ITP’s. They will also coordinate with site team and store if the materials are delivered to
site as per approved material.
Promote a culture in which health, safety and the environment are the prime concern and shall never be
compromised
HSE Supervisor/Engineer
Are delegated supporting roles to assist managers and supervisors to fulfil their accountabilities.
To ensure implementation of all safety procedures and precautions, safety measures related to the nature
of works being carried out and in accordance to the HSE Plan.
Promote a culture in which health, safety and the environment are the prime concern and shall never be
compromised
Co-ordinate in House Safety Trainings and Safety toolbox talks with all levels of the work force
Promote the involvement of all employees in improving safety and the environment.
Conduct daily site inspection along with site HSE team to monitor the HSE operation status.
Report to the Project Manager or his designate on all matters relating to health, safety and the
environment.
Co-ordinate with the action of contractors CRM during any Emergency Situations.
6. MATERIALS:
SL
Material Description Submittal No. Submittal Status
No.
Drawings of Inverters shed installation on car
1.
park structure.
7. WORK SEQUENCE:
Reference/
Responsible
DESCRIPTION Verifying
person
Document
Reference/
Responsible
DESCRIPTION Verifying
person
Document
7.3 Methodology
As per the approved layout fix the mounting bracket in the car park
shade for the inverter
All the inverters are fixed as per manufacturer installation manual
Unpack the inverter release the sealing screws on the mounting ears
with a flat-head screwdriver and store them properly. Anchor the four
supplied screw-in handles to the mounting ears and base of the
inverter.
Lift and move the inverter to the destination by using the side and
bottom handles as well as the four installed handles.
Release the sealing screws on the mounting ears and store them
properly Anchor two M12 thread lifting rings to the hangers of the
inverter.
Lead the sling through the two lifting rings and fasten the tie-down
strap.
Hoist the inverter, and stop to check for safety when the inverter is
100mm above the ground, Continue hoisting the device to the
destination after ensuring the safety.
Assemble the mounting-bracket by using the connecting bar.
Level the assembled mounting-bracket by using the level, and mark
the positions for drilling holes on the PV bracket. Drill the holes by
using a hammer drill. Secure the mounting-bracket with bolts.
Insert the expansion bolts into the holes and secure them with a
rubber hammer. Fasten the nut with a wrench to expand the bolt.
Remove the nut, spring washer, and flat washer, and store them
properly and Fix the mounting-bracket with the expansion bolts.
Hoist the inverter to the installation position when necessary If the
installation position is not high enough, skip performing this step.
Hang the inverter to the mounting-bracket and ensure that the
mounting ears perfectly engage with the mounting-bracket.
Fix the screws.
Reference/
Responsible
DESCRIPTION Verifying
person
Document
i. Hazards / Risks
The hazards and risks are detailed in attached Risk assessment. Refer to the attached Risk Assessment
The access / egress for the construction vehicles for the installation of activities shall be as per the
project logistic Plan.
Ensure proper coordination with all interfacing contractors for logistics and access prior to
commencement of all activities.
All Access routes through the site to be properly maintained to minimize interference with adjoining
roads. Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used
facilities during operations.
Flagman will be provided at critical locations when applicable.
11. LIGHTING:
i. Safety Lighting:
The minimum safety lighting as per general requirements
i. General:
Construction equipment shall comply with the requirements of relevant authorities, industrial
agreements and acceptable industry practice.
Appropriate plants and equipment shall be used for the execution of the activity. The plant, tools
and equipment shall be checked visually prior to use.
All Operators shall be trained and certified by the 3 rd party where required. The testing agency used
for lifting equipment must be certified by the ADM/OSHAD Approval.
No defective plant and equipment shall be allowed to use on site
All operatives involved in the activity shall be provided with Job specific Personal Protective equipment
which are and but not limited as mentioned below
Polycarbonate Safety Helmet
Safety boots with steel toe and Sole
Coverall with high visibility strips
Hand Gloves
Full body Harness (When applicable)
Eye protection / Goggles (When applicable)
iv. Power:
The Power supply used on site for power tools shall be 110V only. 230v or higher voltage power supply
shall be provide to site welfare areas and another site establishment. The 110V and 230V tools will be
verified with colour code blue for 220V and Yellow for 110V.
Non
The work areas shall be clean and tidy. No debris from construction activities is allowed to accumulate
in the work area.
Work areas shall be cleaned on daily basis at the end of the shift or on completion of the activity
Sufficient Waste collection bins shall be provided at each working zone
Waste segregation area (where recyclable / landfill materials are segregated, usually as Steel, Wood,
Plastic, Concrete and debris) shall be established to control the waste generated on site due to
construction.
Fire extinguishers shall be put in place in each working zone and a clear access shall be provided to
the location
All the operatives shall be trained for fire precautions on site
A fire warden is appointed and trained from each team of operatives
iii. Communication
The communication for site emergencies shall be in accordance with the communication protocol given
in the project Emergency Plan & ADMM H&S induction information.
19. ATTACHMENTS
1. Rik Assessment