BILL OF ENGENEERING MEASUREMENT AND EVALUATION FOR THE

CONSTRUCTION OF UMUCHICHI BY COUNCIL UHURU, MALTING


COMPANY ROAD, ABA ABIA STATE (Length 1,650m, Width 7.3m)

S/N DESCRIPTION QTY UNIT RATE AMOUNT

1.00 GENERAL AND PRELIMINARIES

1.01 Allow for laboratory tests of soil and 5,000,000


other materials on the site.

1.02 Allow for services to the engineer 40,000,000


and maintenance of project vehicles.

1.03 Allow for survey works and design 5,000,000


of the project

1.04 Allow for the provision of furniture 5,000,000


for the living accommodation of the
Engineer's representative.

1.05 Allow for the cost of stationery and 5,000,000


equipment required by the engineer.

1.06 Allow for the cost of progress 4,000,000


photographs

1.07 Allow for payment of wages to daily 4,000,000


rated staff for the Engineer's
representatives.

1.08 Allow for service to the Engineer's 4,000,000


representative

1.09 Allow for provision of security on the 4,000,000


site to provide the contractor a safe
working environment

1.10 Allow for the provision and erection 4,000,000


of road signs

1.11 Allow for the provision for relocation 30,000,000


of electricity relocation

1.12 Allow for provision for installation of 30,000,000


solar light

BILL NO 1 CARRIED TO 140,000,000


SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT

2.00 SITE CLEARANCE AND


EARTHWORKS

2.01 Clear both sides of the existing road 19,800 M2 1,000 19,800,000
to the required width of all bush,
shrubs, and grass including
removal/disposal of topsoil to a
depth not less than 150mm

2.02 Excavate all unsuitable materials 9,900 M3 4,500 44,550,000


within carriageway and dispose of
as directed.

2.03 Shape and compact to formation 12,045 M2 750 9,033,750


level as specified and elsewhere as
directed to 100% B.S.

2.04 Excavate approved borrow pit


laterite material, haul excavated
material any distance, deposit,
spread in 150mm layers and
compact to 100% B.S compaction as
filling to embankment and margins.
4,818 M3 14,000 67,452,000
Shape formation and trim slopes to
require cross section. All measured
as completed work in final situ.
Rate inclusive of haulage. As a
replacement for item before haul up
to 5,000M distance.

2.05 Provide, place, spread, shape and


compact with naturally occurring
laterite material to the sub-base 14,000
3,613.5 M3 50,589,000
course and not exceeding 300mm
thick to road carriage way and
shoulder (haulage inclusive)

BILL NO 2 CARRIED TO 191,424,750


SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT

3.00 DRAINS AND CULVERTS

3.01 Excavate for concrete side drains


and culverts to any depth 3,300 M 4,000 13,200,000
including backfilling to 100%
MDD/WASC and dispose of
surplus materials as directed.

3.02 Provide for 750mm X 750mm


concrete line drains including 3,300 M 150,000 495,000,000
concrete grade 25 (150mm thick
walls). Rates to include
reinforcement and shuttering
using standard 10mm
reinforcement

3.03 Provide and place reinforced


precast slab across drains with 800 M 32,000 25,600,000
grade 25 concrete for vehicular
access as directed with manhole.

3.04 Provide for the construction of 1.0


x 1.0m box culvert (walls
200mm). rate includes 40 M 180,000 7,200,000
excavation, shuttering, backfilling
and carting away of excess
excavated materials, concreting
the surrounding. Using 12mm
double reinforcement

3.05 Provide for desilting of newly 3,300 M 1,200 3,960,000


constructed drains

BILL NO 3 CARRIED TO 544,960,000


SUMMARY
S/N DESCRIPTION QTY UNIT RATE AMOUNT

4.00 PAVEMENT AND SURFACING

4.01 Shape and compact to formation 12,045 M2 750 9,033,750


level as specified and elsewhere
as directed to 100% B.S.

4.02 Provide, spread, shape and 1,806.75 M3 70,000 126,472,500


compact to 100% WASC
approved granite crushed rock
base to compacted thickness of
150mm (haulage inclusive) for
carriage way and shoulder

4.03 Provide and lay prime coat using 12,045 M2 1,100 13,249,500
MC-1 cutback bitumen and blind
with sharp sand.

4.04 Provide and spray bituminous 12,045 M2 900 10,840,500


tack coat using colas 'A'.

4.05 Provide, lay and compact 12,045 M2 20,000 240,900,000


asphaltic concrete binder course
to a compacted thickness of
40mm on carriageway.

4.06 Provide and spray bituminous 12,045 M2 900 10,840,500


tack coat using colas 'A'.

4.07 Provide, lay and compact 12,045 M2 22,000 264,990,000


asphaltic concrete wearing
course to a compacted thickness
of 40mm on carriageway.

4.06 Allow for thermoplastic road 5,000 M 1,400 7,000,000


marking

BILL NO 4 CARRIED TO 683,326,750


SUMMARY
SUMMARY

S/N DESCRIPTION AMOUNT

1.00 GENERAL AND PRELIMINARIES 140,000,000

2.00 SITE CLEARANCE AND EARTHWORKS 191,424,750

3.00 DRAINS AND CULVERTS 544,960,000

4.00 PAVEMENT AND SURFACING 683,326,750

SUBTOTAL 1 1,559,710,750

ADD 5% CONTINGENCIES 77,985,537.50

SUBTOTAL 2 1,637,696,287.20

ADD 7.5% VAT 122,827,221.54

ADD 5% ADMIN COST 81,884,814.36

ADD 3% SECURITY FUND 49,130,888.62

ADD 2.5% WITHHOLDING TAX 40,942,407.18

GRAND TOTAL 1,932,481,618.90