QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 1 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
CONTRACT TITLE:
TITLE:
COMPANY
CONTRACTOR
SUBCONTRACTOR
Table of Contents
1. GENERAL........................................................................................................................4
1.1 PURPOSE....................................................................................................................4
1.2 SCOPE OF WORKS....................................................................................................4
1.3 LEGISLATION AND CODE OF PRACTICE................................................................6
1.4 DEFINITIONS...............................................................................................................6
1.5 ABBREVIATIONS........................................................................................................7
1.6 REFERENCES.............................................................................................................8
1.7 ROLES & RESPONSIBILITIES BY SUB-CONTRACTOR & HYDROSERV
(DEWATERING SPECIALIST).....................................................................................8
1.7.1 SHES (Coordinator)...................................................................................................8
1.7.2 SHES Team (SHES Officer).......................................................................................9
1.7.3 Site Management (Site Supervisor and Operations Manager)..............................9
1.7.4 Employees (Operators, Maintenance and Supervisors)........................................9
1.7.5 Foreman....................................................................................................................10
1.7.6 Flagman....................................................................................................................10
1.7.7 Rigger........................................................................................................................10
1.7.8 Electrician & Helpers...............................................................................................10
1.8 ROLES & RESPONSIBILITIES BY MAIN CONTRACTOR.......................................11
1.8.1 Construction Manager.............................................................................................11
1.8.2 SHES Officer.............................................................................................................11
1.8.3 Permit Control Coordinator....................................................................................11
1.8.4 Site Engineer............................................................................................................11
1.8.5 Site Supervisor.........................................................................................................12
1.8.6 Environmental Coordinator....................................................................................12
1.8.7 Lifting Supervisor....................................................................................................13
1.8.8 Scaffolders Supervisor............................................................................................13
2. RESOURCES.................................................................................................................14
2.1 PLANT & EQUIPMENTS...........................................................................................14
Note: 14
2.2 TOOLS MATERIALS AND MANPOWER..................................................................15
2.2.1 Light Tools................................................................................................................15
2.2.2 Materials....................................................................................................................15
2.2.3 Manpower.................................................................................................................15
3. SHES 16
4. POLLUTION CONTROL................................................................................................17
5. EMERGENCY RESPONSE PROCEDURE...................................................................18
5.1 EMERGENCY EVACUATION....................................................................................18
6. PROCEDURE / SEQUENCE OF WORK.......................................................................18
6.1 MOBILIZATION OF EQUIPMENT AND CONSTRUCTION MATERIALS.................19
6.2 DEWATERING SYSTEM...........................................................................................19
6.3 INSTALLATION OF SUMPS AND TRENCHES........................................................20
6.4 INSTALLATION OF DIESEL PUMPS........................................................................21
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 3 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
1. GENERAL
1.1 PURPOSE
The purpose of this method statement is to define the procedure to ensure that the
proposed materials, workmanship, roles, and possibilities to be used for complying with
the conditions/requirements as stipulated in project specifications for temporary
dewatering works using diesel pumps in CULVERTS, PIPE RACK FOUNDATIONS &
PIPE SLEEPERS (if required) in RLTO EXPANSION AND OFFPLOT FACILITIES OF
THE NORTH FIELD EXPANSION PROJECT.
The scope of this method statement details the methodology for the installation of the
temporary dewatering system required as part of the Site Excavation & Preparation for
CULVERT, PIPE RACK FOUNDATIONS & PIPE SLEEPERS (if required) in RLTO
EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD EXPANSION
PROJECT. Hydroserv shall install a temporary dewatering system under the supervision
of ELECO.
This document is a working document and shall be updated regularly according to site
conditions and the hydro geological conditions encountered. Separate Plan Drawings shall
be submitted for each Dewatering Location showing discharge point and all details prior
start for the activity. The scope of works covered in the table below is based on
information provided by Hydroserv and is as follows:
Total Estimated Inflow (l/s) 15.00 l/s 17.00 l/s 15.00 l/s 15.00l/s 15.00l/s
2 (1 duty & 2 (1 duty & 2 (1 duty & 2 (1 duty & 2 (1 duty &
Proposed no. of 6” Diesel Pump
1 standby) 1 standby) 1 standby) 1 standby) 1 standby)
900m 200m 900m 100m 200m
(Discharge (Discharge (Discharge (Discharge (Discharge
Distance to Discharge Point (m)
to existing to Existing to Existing to Existing to Existing
V Ditch) V Ditch) V Ditch) V Ditch) V Ditch)
Distance to Open Water (Approx.) 1000m 400m 1000m 1000m 1000m
1.4 DEFINITIONS
QC QUALITY CONTROL
QA QUALTIY ASSURANCE
Part of quality management focused on providing
QUALITY ASSURANCE
confidence that quality requirements will be fulfilled
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 7 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
1.5 ABBREVIATIONS
Abbreviations Definition
QG QATARGAS
MC Main Contractor
S/C Sub-Contractor
LE Lifting Equipment
1.6 REFERENCES
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 8 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Description Quantity
Construction Manager 1
Site Engineer 1
SHES Supervisor 1
SHES Coordinator 1
Operations Manager 1
Operators As Required
Site Supervisor As Required
Foreman As Required
Flagman As Required
Rigger As Required
1.7.1 SHES (Coordinator)
• Collaborate, monitor, and review and risk register in accordance with the project SHES
policies and procedures.
• Identify and evaluate significant health and safety risks and control improvement
programs by implementation of the Risk assessment process.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 9 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
• Conduct accident investigations for all accidents/incidents and significant near miss.
• Provide SHES assurance reports and scorecard submissions as determined by the SHES
manager including safety monthly report.
• Ensure SHES notice boards are populated and maintained with relevant SHES
information and correspondence.
• Coordinate all relevant permits and ensure they are current and up to date for the
duration of the activities.
• To take all reasonable measures to ensure the safety of the workforce, no damage to
equipment or materials and no damage to the environment.
• To observe and comply with all SHES rules and regulations.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 10 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
• To report all unsafe acts and conditions to the main contractor SHES personnel.
• To report all accidents, incidents, and report able cases to the MC’s SHES personnel.
• To report all equipment damage.
• To maintain a safe and clean work area.
• To wear required protective clothing.
1.7.5 Foreman
• Foreman shall supervise all the activities on site and has full control over the use of the
labour, plant, and equipment. He ensures that the work that is carried out in full
compliance with the specification, and in a manner that conforms to the safety
requirements and shall coordinate to the Site Engineer regarding permit to work and for
any work is complete and ready for inspection.
• To Give task instruction, and toolbox meeting to all workers.
1.7.6 Flagman
• Flagman will give a signal to clearly direct vehicles and mobile equipment at all-time
ensuring they are kept separate.
• He ensures to reduce the amount of reversing where possible and be aware of the
dangers caused when reversing. Using practical techniques and agreed on a system of
signalling and hand signals, flagman will assist drivers and operators in all manpower’s.
• Flagman shall keep traffic area free of pedestrians.
1.7.7 Rigger
• Inspecting and preparing loads that need to be moved. Setting, aligning, and levelling
heavy equipment machinery. Selecting the appropriate rigging gear.
• Preparing rigging equipment including beams, pulleys, clamps, and bolts. Inspecting
rigging before final use.
• Monitoring and maintaining rigging equipment.
• Manoeuvring loads using heavy equipment machinery and by hand.
• Ensuring compliance with state and company safety procedures. Communicating with the
rigging and construction team.
• Breaking down rigging equipment and conducting post-rigging inspections.
• It is their responsibility to use PPE and follow the safety procedures and to do the work as
described in the method statement.
• All electricians shall be competent and have a good general electrical knowledge and
workmanship trade craft.
The responsibilities among the Project related to Dewatering system works in Main
contractor are as follows.
• Supervise the site activities, especially in SHES compliance, to ensure that the site
activities are carried out safely and in environment friendly way.
• Correct non-compliance activities against project SHES regulations
• In consultation with the field staff, determine what SHES training is required for the
employees engaged in their area and ensure the facilities are organized to provide this
training.
• Supervise the recording, reporting and analysis of information on injuries, damage, and
losses, assess accident trends and review overall safety performances.
• To ensure that an adequate SHES training is delivered to all the workers prior to starting
of the activities.
• Improvements where necessary, in existing working methods to reduce SHES hazards.
• To comply the Legal and contractual requirements affecting environment, safety and
health of the employees.
• Carry out inspection in association with site management.
• To ensure that proper SHES information are posted onsite.
• Coordinate all relevant permits and ensure they are current and up to date for the
duration of the activities.
• Supervise the site activities, especially in SHES compliance, to ensure that the site
activities are carried out safely and in environment friendly way.
• Correct non-compliance activities against project SHES regulations
• Report relevant parties for improvement.
• In consultation with the field staff, determine what SHES training is required for the
employees engaged in their area and ensure the facilities are organized to provide this
training.
• Supervise the recording, reporting and analysis of information on injuries, damage, and
losses, assess accident trends and review overall safety performances.
• Preventing injury to personnel and damage to plant, equipment, and environment.
• Improvements where necessary, in existing working methods to reduce SHES hazards.
• Legal and contractual requirements affecting environment, safety, and health of the
employees.
• Provision and use of suitable PPE and equipment.
• Changes in legislation and safe codes of practice.
• Carry out inspection in association with site management to see that only safe plant,
equipment, and methods of working are in operation; that all laws and ordinances are
being observed, that all appropriate statutory notices have been posted; that washing
facilities and other amenities have been provided.
• Discuss with the SHES team what SHES information should be posted on safety bulletin
boards.
• To liaise with third party lab for the sample analysis and test report.
• To coordinate with MC’s Environmental focal point for the performance of monitoring,
reporting at any incident.
• Minimum secondary level educated, or Engineering diploma or Degree and a third party
certified, and approved supervisor shall Participate in crane lifting planning and crane
lifting process for lifts process equipment. Participate in the lift job safety analysis.
• Assist the crane operators with preparing the area where the lift will occur.
• Participate in Pre lifting meeting. Review and sign the lifting permit authorization that all
preparations and safeguards are in place prior to making the lift.
• Responsible to carry out all the assigned work delegated from the Site Engineer.
• Scaffolding supervisor must inspect the Scaffolding prior to RFI for inspection.
• After completion of scaffolding tower/plat form Supervisor must be installed the Scaff tag
as per project requirement/specification.
• TPI inspector must inspect the scaffolding plat form prior to use and signed on Scaff tag.
• Ensure the proper job scope and method of work delivered to the assigned skilled
workers and labours.
• Ensure that the JSA will be strictly observed and always enforced in the job site.
• Assist the crane operators with preparing the area where the scaffolding platform will
occur.
• Assist the construction superintendent with preparing the area where the scaffolding will
occur and participate in the scaffolding job safety analysis.
• SCAFFTAG’s allow an immediate visual indication of the condition of a scaffold structure.
The system comprises of:
• Insert for the holder, one side in GREEN on WHITE background to indicate, when
showing, that the scaffold is complete and certified for use and giving details.
• NOTE: The only person authorized to fix a green SCAFFTAG will be Scaffold Inspector.
• Anyone can pull a green SCAFFTAG if they believe the scaffold is unsafe.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 14 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
2. RESOURCES
1) 3rd Party Certification for Plant and Equipment will be available and checked to ensure validity prior
to commence work.
2) All machines shall follow Project standard and procedure and main contractor’s requirement if
required.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 15 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
2.2.3 Manpower
Surveyor
Scanning technicians Site Engineer
SHES Officer
Supervisor
Lifting Supervisor
Pump Operator
Scaffolders
Riggers
Electrician
HDPE Pipe welder
Heavy Equipment Operators
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 16 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
ELECO shall ensure full compliance to all RLIC and Project SHES instructions. All
activities shall be performed under eCPW, with daily Task Instruction, LMRA and tool-box
talks, prior to the start of activities. ELECO shall ensure that all requirements detailed in
the JSA (Refer to Appendix A) is fully complied with and implemented in the field:
The Supervisor shall ensure that the work party participates in the daily toolbox Talk
and carries out a task specific task instruction (TI) whereby the JSA is communicated
to the workers before the commencement of the activity.
Safety Warning signs and barricades shall be installed where required.
All plants and equipment shall be inspected and certified according to the Project
Plant and Equipment inspection procedure.
Dewatering pumps shall be equipped with suitable fire extinguishers and drip trays
and Subcontractor shall carry out a recorded daily inspection of the equipment.
Trained and competent people shall be involved in the activities including specialist’s
crafts such as riggers and operators during lifting and rigging.
All mandatory and task specific PPE shall be used in accordance with Project
requirements.
All personnel shall undergo relevant training including Site Safety induction and heat
stress training as a minimum.
In case of any emergency or incident in the Project emergency, an incident
management flow chart shall be followed.
Always maintain proper housekeeping on the site
Adequate lights should be provided at the workplace during night work.
All pumps at site have drip tray and anti-whip system attached both for suction and
discharge.
The Heat Stress Management Program (NFXP2-SSG-SH-PRC-00007) should be
applied during heat stress season.
All waste materials removed from the site shall be transported and dumped at
approved dumping skips located within the site.
Disposal of waste material shall be carried out as per the local legislation and
practices in force.
Standby diesel pumps shall be installed at site for emergency purposes like pump
breakdown.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 17 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
ELECO and Hydroserv shall ensure full compliance with RLIC dust control strategy and
support the requirement to control dust sources and improve the ambient air quality.
ELECO and Hydroserv shall implement the dust control hierarchy including prevention,
suppression, and containment of dust.
# PPE Description
1 Hard Hat
2 Safety Glasses
3 Dusty Mask
4 Safety Boots
5 Safety Gloves
6 Coveralls
7 Insulated Water Bottle
8 High Visibility Vest
9 Earmuffs
4. POLLUTION CONTROL
In addition to the above ELECO will ensure that all necessary measures are undertaken to
prevent the pollution of the environment by his plant and equipment for works:
To minimize the environmental impact of the pollution, ELECO shall satisfactorily address
and undertake in a timely and efficient manner to the following issues as a minimum:
Equipment which leaks any fuel, lubricant or hydraulic fluid shall not be used.
Equipment shall be maintained to ensure efficiency and to minimize emissions.
Equipment and vehicles shall be clean on arrival at site.
Equipment and vehicles shall be clean when entering the site with all necessary
measures to eliminate spillage or contamination of existing roads.
Fuel and oil shall be stored away from watercourses, fully bonded and containers
shall be maintained in a secure and clean manner.
Drip tray will be maintained for all the Duty and standby diesel pumps.
Drip trays must be used by the fueling crew during equipment fueling to prevent soil
contamination from minor fuel releases.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 18 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
ELECO shall ensure that all its worksite staff and personnel and subcontractors are fully
aware of the site emergency procedures and knowledgeable of the use and location of the
essential emergency equipment. Any emergencies on site shall follow NFXP Project
Emergency Response Procedure (NFXP3-TRSA-SH-PRC-00007). Key contacts list shall
be posted on site. Emergency eyewash and trained first aiders and standby vehicles shall
be available at all times.
The proposed dewatering methodology is trench & sump pumping system using diesel
pumps. Hydroserv has already performed different projects at the same Ras Laffan project
area. As a result, the pumping test is not required for this project conditions. If required in
future due to some unforeseen conditions during excavation, then pumping test will be
done at site after the mutual agreement with MC.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 19 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
The preparation and application procedure shall be in strict accordance with the
manufacturer recommendation and approved Dewatering Plan drawings as described
below. Steel ramp shall be used in case of any dewatering pipes crossing the service road
Please refer to Appendix E for the typical layout of the Road Crossing
All vehicles & equipment to be used in the work should be initially checked and approved
by the authorized personnel.
All Operators & drivers involved in operating equipment shall be licensed proof of
qualifications must be kept for review & would be competent for the tasks that they will be
carrying out.
Manufacturer’s specifications or owner’s manual for the equipment shall be on site and
reviewed for safety precautions or requirements. Incorporate the safety comments as
identified.
SHES manager, site superintendent will mobilize the Equipment as per approved TMP
(Traffic Management plan). Ensure travel routes & access to the jobsite is in good
condition and free from obstruction.
Access route for all equipment shall be provided and steel plates shall be provided to
cross the existing UG utilities/lines.
Once the trailer/Truck reached at site location, the equipment/materials shall be offloaded
from the vehicle using crane/boom truck and the materials shall be stored in approved
storage location.
Goal posts shall be installed if vehicles are required to pass under existing overhead
obstructions. Height of goal post to be determined by asset owner.
The proposed dewatering system is trench and sump pumping system using diesel pump.
Trenching and sumps shall be required during the stages of excavation up to the final
formation level to allow flexibility in dealing with hydrogeological features.
electrical sump pumps can be used instead of diesel pumps. The Maximum suction lift of
Diesel pump is just 3 - 5m.
The diesel pumps shall be connected to the main header line and the header main shall
be connected to the sedimentation tanks then to the booster station which shall be
discharged to the approved discharge location. Before discharging water to the discharge
location, water lab test needs to be done first, and if safe to discharge as per RLIC
Environmental requirement. The sample will be taken from the discharge tank, and it will
act as sampling point.
During the stages of the excavation, trenching and sumps shall be employed in order to
control any surface water or over bleed water which may be encountered. Trenches
approximately 1m length x 1m deep would be excavated along the perimeter and the
middle of the excavation if required. All trenches will be interconnected to the sump pits.
Any additional sump pits would be filled with crushed and washed aggregates to serve as
a filter for fine materials.
Since the excavation depth of this project is not extending below 3 - 5m depth, lowering of
platform is not required for this project.
All diesel pumps shall be installed near the excavation minimum 2 meters from the edge of
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 21 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
excavation, suitable for workers in doing maintenance and repair and not to cause hazard
of falling, position in assigned location and shall be installed low enough using constructed
platform to maintain suction power. It is required to use a crane or other suitable lifting
equipment for installation, maintenance, or relocation of diesel pumps. Those pumps shall
have a trained operator and maintenance work on both day and night shift. As per RLIC
requirements, the buddy system will be followed at Night shift. For every pump operator on
the night shift there will be a buddy in place.
No refueling of pumps while running and it shall be at full stop. The warning signs and
Device location signs will be posted on site. And this area shall be barricaded and tower
lights to provide lighting during night shift.
The discharge pipework shall be installed around the excavation perimeter with take offs
at each sump location. A check valve and automatic non-return valve shall be fitted at
each pump head works.
Once installed the header pipework shall be suitably protected and be visible at night by
S/C to ensure no damage can occur from site traffic or personnel.
Wherever the discharge pipework crosses haul roads / site access the pipe works shall
have additional protection measures in place suitable to each site-specific condition and it
should be visible during night work. The discharge pipework shall be laid to their specified
discharge location after the discharge tank, in this project the proposed discharge plan is
to the following network, whichever is the agreed location as per RLIC & QE
Environmental.
1) Discharge to Existing Ditch,
2) Discharge to Tanker
In case of any dewatering pipes crossing the road access, a steel ramp shall be used.
Please refer to Appendix E for the typical layout of the Road Crossing.
Lifting activity shall adhere to the Lifting & Rigging Procedure (NFXP3-TRSA-SH-PRC-
00021)
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 22 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
NOTE:
In case of any dewatering Pipes to cross any Existing culvert prior implantation
ELECO shall get concurrence from the Asset holder.
Upon the approval from RLIC, the actual track road and road crossing will be
specified in the layout.
The sequence of works shows the outline and procedure of activities that is required in the
dewatering works in CULVERT, PIPE RACK FOUNDATIONS & PIPE SLEEPERS in
RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD EXPANSION
PROJECT. The project includes supply and installation of HDPE Pipe. The preparation
and application procedure should be in strict accordance with the manufacturer
recommendation and approved shop drawings as described below. All the required
material and machinery will be mobilized to site from the Subcontractor & Hydroserv yard
or directly from the various suppliers.
The equipment used for the mobilization is noted in Table 3. The same type of equipment
would be used to demobilize the equipment from site.
Appropriate Permit to Work shall be in place before the start of work. Hot work permits
shall be taken to process the HDPE welding works. Necessary welding certificates shall
be submitted prior to welding activities.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 23 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
In Welding operation, the HDPE pipe will be welded one joint at a time inside the trench. In
this case, the Butt-welding machine will be retained in its position and HDPE pipe will be
laid on the rollers. As a result, the HDPE pipe will move along the trench and the process
will be seeded up. The process will continue until the target length is completed.
The HDPE pipe will be welded using heat fusion bonding. This is a combination of
temperature and force resulting in two mating surfaces flowing together to produce a joint.
Fusion bonding occurs when the joint cools below the melting temperature of the material.
There is a temperature range within which any particular material may be satisfactorily
joined. The specified temperature used requires consideration of the properties of the
specific material, the fusion equipment being used and the welding environment.
For HDPE pipe welding, the Mirror welding machine shall be heated by electricity since
electric heating plates can maintain consistent fusion temperatures when provided with an
adequate power source. Electric heating plates for general fusion use shall be controlled
thermostatically and capable of being adjusted over a temperature range from 150° to
300°C. For welding of HDPE, the temperature thermostat shall be set according to
manufacturer’s recommendation. The mirror (heating plate) shall be equipped with a
thermometer or other built‐in temperature measuring device and shall also have sufficient
area to adequately cover the ends of the pipe to be joined.
The alignment jig shall consist of two fixed and two movable clamping blocks for holding
the two parts to be fused in movable axial alignment. One shaver for simultaneously
preparing the ends to be joined. Appropriate adapters “inserts” for different pipe sizes.
Once the butt‐welding is done in several phases and by using several parameters. The
operations can be summarized as follows:
4) Cleaning of surfaces.
5) Heating of surfaces.
6) Fusion of surfaces.
The welding zone must be protected from unsuitable weather conditions (e.g., humidity
effects, wind and temperatures below 0°C). The surfaces to be joined must be undamaged
and free from impurities or loose particles.
The pipes must be aligned when they are clamped into the mirror welder in such a way
that the surfaces are in the same plane (parallel) to each other. The HDPE pipes can be
positioned directly into the welding machine. Install the correct adapter insert for the size
of pipe diameter to be used and tighten them to the machine.
Position the pipe in a way that approx. 40mm is protruding behind the last clamp. By doing
this, you will have approx. 10 to 15mm to shave from, and the remaining 25 to 30 mm
should be sufficient for welding.
Once the pipe has been placed in position, the top clamps can be closed. It is important to
tighten the top clamp nuts evenly in order to get a totally circular pipe, an even clamping
pressure must be achieved. Then, make the first dry matching (press the two pipes to
each other) and check the amount of shaving that will be required.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 25 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
After the dry matching is completed, open up the pipes and introduce the shaver. Turn the
shaver on and adjust to a suitable speed.
Press the two pipes together, and shave until a continuous strip of HDPE is peeling off on
both sides of the shaver. Once constant peeling off is observed, release the pressure on
the pipes and separate the pipes. Do not turn off the shaver until the pipes are apart. If the
shaver is stopped during shaving, the shaver will create an end cut-mark and the shaving
operation will have to be repeated.
Remove the shaver, match the pipes again, and check the pipe for proper alignment.
Sometimes, even when continuous peeling off is achieved on each side of the shaver, the
pipes do not match properly. This is normally due to the clamps, which are pressing on to
the pipe with different pressures. Re-tightening the nuts slightly on either side is one
solution. But, if this does not help, swimming normally does the job. Open one clamp and
insert a shim in between the jaws and the pipe. This shim will concentrate the pressure on
to the pipe and move the pipe into alignment. It is important to remember that, if the clamp
has been opened during operation, the shaving operation must be repeated.
Once the pipes are correctly aligned, separate the pipes again for cleaning. Remove chips
inside the pipes on both sides, all chips scattered under the pipes, and inside the machine.
Otherwise, they will stick to the mirror (heat plate) later while re-heating. Remove the chips
by using a brush or a small hook made of a thin steel wire. Never put any dirty gloves
inside the pipe or remove the chips with your hands. Do not touch the shaving pipe ends.
To be on the safe side, always clean the surface with a clean rag and mineral
spirits/alcohol before you introduce the mirror.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 26 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Before you introduce the mirror, you should have all parameters available for this
operation. Also check the mirror temperature. Normally, the mirror has a yellow or red
lamp, which tells you if the mirror has reached working temperature. To make sure there is
no cold air flowing through the pipe, place some plastic bags on each end of the pipe, this
will prevent the air from cooling the mirror on one side. You have now shaved the pipe into
a good fit and removed the shaver and introduced the mirror.
Push the pipes together against the mirror and raise the pressure to the Bead-up
pressure. This pressure needs to be maintained until the Bead-up height has been
reached. The bead up height is the height of the bead, which is pressing up against the
mirror.
As soon as the Bead up height has been reached, release the pressure down to the Heat
Soak pressure. Heat soak pressure is the pressure maintained during the Heat Soak time.
As soon as the heat soak time has elapsed, separate the pipes, remove the mirror, and
then press together.
This operation must be done quite fast since there is a time limit “Transfer time” from the
removal of the mirror until the two pipes are pressed together and reach the Fusion
pressure.
Fusion pressure is the pressure that shall reach during the Transfer time and maintained
during the Cooling time.
Cooling time is the time in which the pipe must be left undisturbed. Under no
circumstances shall the clamps be opened, or the pressure released until the cooling time
has elapsed.
The mirror-welding machine, if coupled to a data log, will give a print-out confirming the
parameters used during welding of a specific seam and approval/rejection of the welded
seam.
A well-formed bead that is within the Max / Min measurements as previously described.
(Bead size is a good measure of heating phase consistency, therefore the use of a digital
Vernier to measure the volume of material displaced at the completion of a butt-welded
joint is recommended) Faults as misalignment, porosity, and cracking.
Ensure the groove between the two beads does not continue into the pipe wall (usually
caused by extended changeover (dwell) times or when pressure is not maintained during
cool times).
Undersized bead size can be caused by extended changeover (dwell) time’s low heat,
short heat times, low pressure, and failure to maintain pressure during cool times or simply
the welder coming to the end of its travel without the operator noticing, these issues can
be checked by bead measurement.
Oversized beads can be caused by high heat, extended heating times, excessive
pressure, bringing pressure up to rapidly.
If poor quality of weld seam result was observed a corrective measure must be
undertaken before proceeding to the next joint.
Twist the beads at several positions. If the bead is seen to split at any point, then the joint
must be cut out from the pipeline and remade. If a similar defect re-occurs, cease all
further jointing until the equipment has been thoroughly cleaned, examined and new trial
joints have been made and shown to be satisfactory.
Discharge groundwater shall be monitored and tested in order to check the quality during
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 28 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
the dewatering works. All dewatering activities shall be in full compliance with RLIC and
QG requirements, in particular Environmental regulations.
If water is going to be discharged into existing drainage canals that are subjected to ocean
tidal flows that may get blocked by beach sand, the drainage canal shall be inspected
periodically and cleaned as necessary to maintain continuous flow. Direct discharging of
water into drains or trenches is not allowed. Water shall be collected in the sedimentation
tank and discharged to the following proposed discharge network. CONTRACTOR shall
consider the re-use of ground water encountered during activities associated with
excavations. The discharge of ground water (uncontaminated) for dust suppression is
authorized.
After the installation and commissioning of the system, all the dewatering works shall be
monitored both at day and night shift in charge on site. Hydroserv shall carry out daily
check on the dewatering system – that includes the following:
Flowrates
Pumps
Day and night shift in charge supervision shall be present on site, working with the
buddy system during night shift.
The Sludge waste materials or fine sand from the sedimentation tank will be
periodically removed once or twice a month. Safe access should be provided for
cleaning and for water quality monitoring.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 29 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Using the Shovel, Hydroserv will remove the sludge waste or sand settled at the
bottom of the tank and in its corners. Will ensure any blockages in the inlet and
outlet of the tank accordingly those blockages will be removed.
These collected sludge waste materials or sand will be stored in the proposed
laydown area. The RLIC approved location for the laydown area will be provided
by MC. Sludge waste should be properly segregated and disposed as per the QG
waste management procedures.
Dewatering Contractor develop a monitoring register for cleaning the tank and will
be submitted to the COMPANY on monthly basis.
Cleaning the concrete ditch and its path before discharging the ground
water.
Periodically clean the concrete ditches and remove the sludge wastes or
blockages from the ditches before uses, and during use to allow flow of
water to the beach and remove any blockages.
The dewatering works shall continue until a written notice is received from the main
contractor to demobilize. Subcontractor recovery tests shall be carried out to monitor the
water level as part of the process. This will allow the pumps to be re-energized should it
be required.
Scaffolding will be used for dewatering pipe to cross the existing berm. ( Refer to
Appendix F for Existing berm Crossing typical layout)
Responsible to carry out all the assigned work delegated from the Site Engineer.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 30 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Scaffolding supervisor must inspect the Scaffolding prior to RFI for inspection.
After completion of scaffolding tower/plat form Supervisor must be installed the Scaff tag
as per project requirement/specification.
TPI inspector must inspect the scaffolding plat form prior to use and signed on Scaff tag.
Ensure the proper job scope and method of work delivered to the assigned skilled
workers and labours.
Ensure that the JSA will be strictly observed and always enforced in the job site.
Assist the crane operators with preparing the area where the scaffolding platform will
occur.
Assist the construction superintendent with preparing the area where the scaffolding will
occur and participate in the scaffolding job safety analysis.
Following excessive rainfall that has caused flooding, the following will be implemented:
1) Visual inspection of formation and side slopes to be carried out by site personnel
under the supervision of site safety officer.
2) A detailed report on the rainfall event and its impact on all affected areas, including:
The diesel for the equipment will be supplied by diesel refueling, it shall be carried out
through approved Diesel tanker.
The diesel for the hand tools & generator, shall be filled by jerry cans brought using
pickup.
Ensure MSDS available for diesel supply during transportation & refueling.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 31 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Ensure jerry can is well secured with latching strap to avoid movement or fall.
Do not use mobile phone or any form of ignition source during fueling.
Suitable jerry can with UN class warning sign to be used for refueling.
Jerry can must be placed on the drip tray all the time.
Spill kit is available along with the inspection checklist for the protection of oil spillage.
Minor maintenance and refueling activities shall be done on the area designated for the
project including parking areas at the end of everyday work and any. Violators shall be
noted for fine/removal on the site premises.
Plant and Equipment minor maintenance shall be carried out as per COMPANY Plant &
Equipment Maintenance SHES Inspection Program (Ref: NFXP3-TRSA-SH-PR-00059)
Routine maintenance & inspections such as oil change, greasing & cleaning of the
equipment shall be carried out in the designated area with necessary precautionary
measures by the competent persons.
Waste generated out of maintenance activities shall be disposed to the designated area
within the RLIC premises as per the company (QG/RLIC) regulations and trained spill
response team shall be in place during these operations.
Minor maintenance shall be carried out with competent persons within the site premises.
In case of Major Breakdown, the machinery can be taken out of the COMPANY Premises,
unless physical restriction applies (E.g., Bulky & Tall Machinery, Machinery Must Travel
across sensitive areas)
During the execution of the work, approved Heat Stress Schedule Mitigation Plan (NFXP3-
TRSA-SH-PLN-00046) shall be implemented.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 32 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
All work will comply with the heat stress management program which includes Heat Stress
Assessment, workplace monitoring & personal monitoring.
All work sites shall comply with the ALT Heat stress Schedule Mitigation Plan for red and
black flag.
During hot weather, timing shall be adjusted to reduce exposure to direct sunlight.
The below method shall be implemented to on-site for Heat Stress Management.
a) Employee Rotation
Labor intensive work shall be rotated frequently as per the flag color.
Workers in additional clothing or suits must be rotated more frequently.
b) Training for heat stress
Workers shall be trained to avoid heat stress before starting work. Which includes
Knowledge of health hazard of heat stress
Recognition of factors, danger sign, and symptoms
Awareness of first-aid procedures
Worker responsibility in avoiding heat stress.
c) Fluid Replacement
Cooled water shall be readily available during warm weather or in hot work areas.
250ml of fluids shall be consumed every 10 minutes to prevent dehydration and reduce
the risk of illness.
d) Buddy System
When working during the hot season, working in pairs will be implemented, in which
person watching out each other for early warning sign of heat stress.
e) Shade and Shielding
A shaded area with a green net on all side including top will be provided at the working
site to prevent direct sunlight with seating arrangements to rest.
Cool drinking water will be provided with flasks (insulated bottles) to drink.
Misting fans shall be installed in the rest shelters.
f) Minimize Labor intensive work.
By using appropriate mechanical equipment to assist workers by reducing manual
labor and heat stress generated by the worker (such as JCB for digging instead of
manual digging, Bulk loading/unloading by crane …etc.)
g) Flagging System
A color-coded flagging system as per the Heat stress index will be implemented at all
workplace area.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 33 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Adequate lighting shall be provided in the access / egress and in the work area at night.
Lux readings taken before work commences to ensure minimum levels are achieved (30-
55 lux).
PTW revalidation shall be signed and approved for night shift activities.
Extended Work Overtime and Nightshift plan must be approved from CPY before any
nightshift work can commence.
All Risks are evaluated prior to any works commencing utilizing the matrix to determine
the level of significance in terms of likelihood of occurrence and severity of hazard based
on the allocated numerical values.
The heat stress management program will be fully implemented when summer season
starts.
If any heat stress symptoms are observed, employees shall be attended by first aid /
medical team immediately and the JOC to be called on:44745888 / 800 8808 (TOLL
FREE).
All personnel, including subcontractors and third parties shall be provided with Safety
Induction prior to entry on site.
Site personnel shall always adhere to the site safety policies with emphasis on wearing
the correct PPE equipment relative to the type of operation being performed.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 34 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Basic PPE will be hard hat, safety boots, safety glasses and gloves, high-visible vest and
insulated water bottle as mandatory. Safety precautions shall be of paramount importance
to prevent any danger to the public and any operations carried out shall be closely
monitored by the Project Safety Advisor.
All the personnel's involved at site must undergo a SHES induction training and other
SHES relevant trainings (e.g., heat stress, working at height, confined space etc..)
depending to their activities.
All the equipment’s such as Crane, and boom trucks are subject to a COMPANY approved
Third-Party Inspections performed monthly for cranes and quarterly for boom trucks as per
Equipment Inspection Program NFXP3-TRSA-SH-PRC-00059 by a competent person.
Any structure made of scaffolding materials e.g., rest shelter and smoking shelter must be
inspected by the certified scaffolding inspector and provided with the inspection tag.
All the workers should undergo fitness to work screening validated by COMPANY
approved doctor prior to mobilization at site.
All tools and equipment's must be inspected by the competent personnel prior to use.
All lifting appliances and lifting gears will be tested and certified by approved (Third Party
Agencies) and a copy of these certificates will be made available at site for verification.
Lifting register will be maintained at the site showing details of lifting appliances and gears
available at site and their validity of current inspection status.
SUBCONTRACTOR shall develop traffic management plan within the construction areas it
shall be submitted to CONTRACTOR/COMPANY for approval.
Welfare facilities must be available and provided at site such as but not limited to; toilet,
drinking station and rest shelter.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 35 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK
FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Emergency evacuation route, emergency numbers, SHES & quality policy should be
display.
All personnel, including subcontractors and third parties shall follow the requirements
identified in the Project SHES Plan.
Supervisor to ensure the availability of the right JSA and PTW prior to commencing any
activity and toolbox talk shall be conducted on the activities planned for that day.
Rest shelter shall be provided near to the working location and water bottle for all
employees as mandatory PPE.
All attending parties and all involved in the activity shall sign the Toolbox Talk & TI log
sheet that they fully understand all safety precautionary measures and the execution of
work as per Method Statement.
Rest shelter and drinking water cooler provided as per Heat Stress Management Program
NFXP3-TRSA-SH-PRC-00046 within 3 minutes walking distance from work area.
Work Site supervisor & Safety Officer shall be present at site all the time while work is in
progress.
Separate doc should be Refer to Confined Space Rescue Plan No: TR-CSE-RP-001
15. APPENDICES
7 All outside activities Snakes & Scorpions - Train personnel on the snakes and scorpion hazard and preventive
measures.
- DO NOT attempt to approach, capture or handle the snake.
- Never leave your PPEs on site and double check the PPEs for any
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 41 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Damage of nearby existing - Obtain concurrence from all relevant asset owners prior to lift the
facilities / Overhead load over any existing live facilities.
Services
- Ensure CONTRACTOR approved lifting plan which has been
reviewed by COMPANY shall be in place before the critical lift
proceeds.
- Ensure the lifting equipment’s are positioned and maintained safe
distance away from any overhead services/ structures/power lines.
- Use two tag lines to control the swing of lifted load.
- Ensure the tag line is single length manila rope (Min Size 16mm)
and free of any splices, knots or loops and be of enough length.
Falling Load - Ensure the lifting equipment’s are inspected and appropriate
authorizations and approval obtained prior to commencement of
activities.
- Ensure Sponsor of Load check sheet has been completed.
- Ensure no one will stand under the suspended load.
- Ensure correct lifting warning signage is placed around the
barricaded area to prevent unauthorized access to the lifting area
where operation or maintenance activities are in progress.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 50 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Collisions
24 Connecting/Disconnecting of Improper/damage tools - All tools shall be inspected, and color coded prior to use.
hoses with pump/ tank etc.
- Tools that are damaged shall be quarantined immediately.
- Also refer to General Section - 14
Failure of hoses/couplings - Secure all fittings / connection with whip check.
- Check hose and fittings condition before use.
- Route the dewatering hoses properly
Manual Handling - Refer to General Steps Section - 11
Line of Fire, Pinch Point - Identify Line of fire & pinch point areas and stay away.
- Be aware about surroundings while shifting pipes manually.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 57 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Exposure to rotating parts - Signage and exclusion zones shall be set up. Around the pump area
and/or high noise
- Proper PPE Shall use at all times.
Noise - Refer to General Steps Section - 12
28 Discharge of water from Contaminated water - Only discharge non-contaminated ground water into SW drains after
sediment collection tank into assuring the water quality.
approved discharge location.
- De-watering samples shall be tested frequently as stated in
Environmental Monitoring and Reporting Plan by third party to
ensure that turbidity and contaminants levels are within acceptable
parameter.
Slip/Trip/fall - Refer with section .05
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 61 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Falling objects - Ensure the usage of suitable means to lift and lower material from
elevated areas such as gin-wheels, pulleys, ropes and rated lift
bags.
- Ensure toe boards are installed.
- Tool lanyards shall be used to secure tools for all working at height
activities.
- Loose materials shall be stored in designated containers to avoid
dropped objects.
- The drop zone shall be identified and barriered off to prevent access
and appropriate Stay Away signage placed
Manual handling injury - Refer with general section no.11
Slip, trip, fall - Refer with general section no.5
Asphyxiations in confined - Reference with the job step no.25
Space
Fire - Project Safety Regulation of Vehicle and Mobile Equipment
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 65 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Spillage & fire from standby - Provide adequate spill containment tray / spill kit.
COMPANY: Contract No.:
QATARGAS OPERATING COMPANY LIMITED LTC/C/NFE/3998/18
PROJECT: RLTO EXPANSION AND OFFPLOT FACILITIES OF THE NORTH FIELD Doc. No.:
EXPANSION PROJECT (EPC-3) NFXP3-ECC-CC-MST-00437
CONTRACTOR: TECNICAS REUNIDAS S.A. Rev. 0
SUBCONTRACTOR: CHINA ELEVENTH CHEMICAL CONSTRUCTION W.L.L PAGE 70 OF 74
Doc. Title: METHOD STATEMENT FOR DEWATERING WORKS FOR CULVERT (NFERC-306, 307, 308), PIPE RACK FOUNDATIONS & PIPE SLEEPERS AT HA-03 (EPC-3)
Section 4: Agreement
The Job had been analyzed for potential hazards, appropriate guidance had been obtained in identifying the hazards and the required controls
were discussed and agreed in the JSA Team Meeting.
JSA Team Leader Name CTR/Sub-CTR: CTR SHES Manager CTR Construction Manager
Date: Date: Date:
Signature: Signature: Signature:
All controls stated in the JSA are in place and the hazards and controls indicated in the JSA have been cascaded to the crew:
Job Supervisor Name CTR/Sub-CTR: Date: Signature:
Endorsed by QG Host if the Supervisor is a contractor.
Removal of the hazard by eliminating the process will also eliminate the risks associated with the hazard. Example: Offsite Welding, No
Elimination Working at Height etc.
If the process cannot be eliminated, consider substituting the substance or hazardous process with one known to be less harmful to health or
Substitution safety. Example: Using Man Lift instead of Ladder or Scaffolding Structure.
Engineering type controls include changing processes, equipment, or tools to reduce risk. For example: Reduction at source of noise or
Engineering
Controls
vibration through various known engineering controls. Providing air-movers for ventilation.
Administrative controls involve introducing and maintaining work practices that reduce risk by limiting the exposure of an employee to the
Administrati
ve Controls
hazard. For example: Reduce the time of exposure, Work Rest Cycle, Signages, Barriers, Procedures.
Additional / Special Personal Protective Equipment should be used when other measures have not been able to protect the employee
against the hazard or risk of exposure to the hazard. Where Additional PPE is used, the Job Supervisor should ensure that it fits the task
PPE
force correctly, training is provided: Double Hearing Protectors, Respirators, Breathing Apparatus, Safety Harness etc.
B MONITORING SHEETS