DAILY PROJECT REPORT

Employee Name : Samuel Sihol Hutahaean


Date: Monday, 2019-03-25
No. Project Target Completion Remarks
Task Date Status

I. Project: Edo Residence

1 Progress Meeting w/ Owners 25/3/2019 Done Post meeting to be followed-up:


9.00 AM to 12.30 PM - Rugs
- Façade's Travertine Stone
- Blue Calacatta Stone
- Metal Inlay for Wooden Door
- Swimming Pool Waterfall
- Bathroom glass cubicles
- Glass Railing for balconies
- TOTO Kitchen
- Master area work stages
- HKA Lighting
- Soft Finishings
- Wet Kitchen
- Ceiling design for terrace area
- Landscape tree request
- Interni additional work loose furniture
- 3D visualisation update
2 Swimming pool & waterfall revision 26/3/2019 on progress 65%
3 Request to Eschol: front garden tree needs 25/3/2019 Done Informed to Mr. Doddy (Eschol)
more "tidy" type

II. Project: Zahir Residence


1 Site meeting Mushola w/ Owner, Rudy, 25/3/2019 Done Post meeting to be followed-up:
General Contractor, Wina Metalworks, Gym - Metalworks drawing: clarified
Door - Gym Bathroom Door (D-03) drawings
12.30 PM to 15.00 PM - Ceiling Revision
- Carpet
2 Gym Bathroom Door (D-03) drawings 26/3/2019 on progress 70%

1
DAILY PROJECT REPORT
Employee Name : Samuel Sihol Hutahaean
Date: Monday, 2019-03-25
No. Project Target Completion Remarks
Task Date Status

I. Project: Edo Residence