Method of Statement For Structural Steel Manufacturing and Erection

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7

Title: Manufacturing of Structural Steel

Scope: This method statement outlines the procedures to be followed for the
manufacturing of structural steel products, including cutting, grinding, drilling,
and finishing of steel members to ensure compliance with design specifications and
quality standards.

Responsibilities:
Quality Control: Ensure that all steel products meet the required specifications and
standards.

Production: Ensure that all steel products are manufactured in accordance with the
approved design drawings and specifications.

Health and Safety: Ensure that all workers involved in the manufacturing process
follow safety guidelines and protocols to prevent accidents and injuries.
Procedure:
Receive and inspect raw materials: Verify that the raw materials meet the required
specifications and standards.

Cutting: Cut the steel members to the required lengths using a plasma cutter or
oxy-acetylene torch.

Grinding: Grind the cut edges to remove any sharp edges or burrs using an angle
grinder or belt sander.

Drilling: Drill holes for bolt holes, rivets, or other fixings as required using a drill
press or handheld drill.

Finishing: Clean and deburr all surfaces using a wire brush or sandpaper.

Painting and coating: Apply paint or coating as required to protect the steel from
corrosion and weathering.

Inspection: Inspect all manufactured steel products for defects or damage before
dispatch.

Testing: Conduct tests on random samples to ensure compliance with design


specifications and standards.

Packaging and dispatch: Package and dispatch the manufactured steel products in
accordance with transportation regulations.
Quality Control Checks:
Visual inspection of all manufactured steel products

Measurement of dimensions

Testing of mechanical properties (tensile strength, yield strength, etc.)

Chemical composition analysis

Paint coating thickness measurement


Safety Precautions:
Wear personal protective equipment (PPE) such as gloves, safety glasses, and
earplugs when operating machinery or performing tasks that may generate dust or
debris.

Ensure proper ventilation in work areas to prevent inhaling fumes or particles.

Keep long hair tied back and avoid loose clothing that may get caught in
machinery.

Use proper lifting techniques to avoid injury.


Title: Erecting of Structural Steel

The purpose of this Method of Statement is to outline the procedures for the
structural steel erection at [Tubas YDRC and Tulkarem YDRC], located at [Tubas
and Tulkarem]. The scope of work includes the fabrication, transportation, and
assembly of structural steel members, including beams, columns, girders, and
bracing, as per the approved drawings and specifications. The following is the
step-by-step procedure to be followed for the structural steel erection:
Pre-Erection Preparation: Prior to commencing the steel erection, the site
shall be cleared of any debris, obstructions, and hazardous materials. All necessary
permits and approvals shall be obtained from relevant authorities.

Steel Fabrication: The structural steel members shall be fabricated off-site in


accordance with the approved drawings and specifications.

Site Preparation: The site shall be prepared by laying down a level and
compacted base course to ensure a stable foundation for the steel erection.

Steel Transportation: The fabricated steel members shall be transported to the


site using [mode of transportation] and unloaded in a safe and controlled manner.

Steel Erection: The steel members shall be erected in accordance with the
approved sequence and tolerances as per the drawings. All connections shall be
made in accordance with the approved specifications and manufacturer's
instructions.

Bracing and Clamping: Temporary bracing and clamping systems shall be


installed to ensure stability and prevent damage to the structure during
construction.

Quality Control: The structural steel erection process shall be monitored


regularly to ensure compliance with the approved specifications and quality
standards.
Final Inspection and Testing: A thorough final inspection and testing of the
completed structure shall be conducted prior to handover to the client.

By following this Method of Statement, we are committed to delivering a safe,


high-quality, and timely completion of the structural steel erection works at [Tubas
YDRC and Tulkarem YDRC].