Project Page No

Project Summary
IJAP24 1

Open Coring Rig Move Consumeable


Date Total
No Borehole Unit Rig Hole < 90% > 90% Total DistanceCorebox Fuel Casing Polymer Bentonite Stand by
From To
From To Meter (meter) (meter) (meter) (meter) (meter) (Pcs) (Pcs) (Pcs) (Liter) (Kg)

1 IS_05 RIG-02 06-May-202411-May-2024 110 0 0 0 110 IS_05 0 0 80 0 0 0 54:45:00


2 IS_07 RIG-01 06-May-202411-May-2024 100.3 0 0 0 100.3 IS_07 0 0 120 0 0 0 58:55:00
3 IS_05C RIG-02 12-May-202419-May-2024 73.1 0 15.3 15.3 88.4 IS_05 IS_05C 301.5 0 160 0 1 25 76:30:00
4 IS_07C RIG-01 12-May-202413-May-2024 21.8 0 6.6 6.6 28.4 IS_07 IS_07C 350 0 40 0 0 0 19:00:00
5 IS_06 RIG-01 14-May-202420-May-2024 110.6 0 0 0 110.6 IS_07C IS_06 0 0 125 19 2 55 58:45:00
6 IS_04 RIG-02 19-May-2024 100 0 0 0 100 IS_05C IS_04 400 0 90 0 1 95 54:00:00
7 IS_06C RIG-01 20-May-2024 59.6 0 10.7 10.7 70.3 IS_06 IS_06C 0 0 120 18 21 102 58:30:00
8 IS_04C RIG-02 25-May-2024 23.9 0 0 0 23.9 IS_04 IS_04C 1.5 4:00:00

Total 599.3 32.6 631.9 1053 0 735 37 25 277 384:25:00