Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Ph: 250-562-6861 Fax: 250-562-6826

DAILY CONSTRUCTION REPORT


1820 3rd Ave., Prince George, BC, V2M 1G4

OWNER: District of Wells REPORT NO.: 07

PROJECT: Lowhee Creek 2023 Dike Repairs SHEET: 1 OF 3

LOCATION: District of Wells, BC PROJECT NO.: 954-012-04

CONTRACTOR: Fresno Const. & EA Works Construction FILE NO.:

CONTRACT: Time & Materials Works (assigned rates) DATE: 2023-11-29

Low
CONTRACT NO.: TEMPERATURE: High: -4*C : -11*C

WEATHER: Cooling temperatures and snow removed from site work areas

List the LABOUR FORCE (by trade) and the CONTRACTOR’S EQUIPMENT, followed by the REPORT.

Labour Force:

1- Eric Andersen & Anthony Harris (EA Works Const.)


2- David Entwistle (RRA Engineering)
3- EX300 Excavator Darren Joly EX200 Excavator Luke-Operator –7 Tri & Tandem trucks (Fresno Const.)
4- Ron & Roger – Laborers (light plant set-up & site works) – Fresno Const.
5- Dave Wilkins – Site Safety Officer (District of Wells)

Contractor’s Equipment:
1- D6T Cat Dozer (lowbed in today)
2- EX330 Excavator (AE Works Const.)
3- 4 Triaxle and Tandem Gravel trucks (3 with pup wagons)
4- EX320 & EX330 Cat Excavator with Hoe-Pac
5- 7 Tri-drive & Tandem Tricks hauling pit run & rock as well as two tandems at
site hauling materials up channel to the two Fresno excavators.
6- Site Safety Vehicle & RRA Field truck (Survey crew)
7- 2-Portable Toilets (vac once a week)-All-Haul
8- 1-1,000lb Packer & Insulated tarps (Fresno Const.)
9- 1-SoilTec staff on-site running densities on pit run placements.

Report:
• Site safety meeting (Dave Wilkins & contractor staff). Emergency First Aid plan posted at Muster Station.
• Compaction testing to be ran and tested tomorrow during pit run hoe-pac and/or 1,000lb plate tamper work.
• SoilTec ran testing on pit run placement at larger fill area along east bank (work to reach >95% determined
and hoe-pac is much more time effective with current soils moisture and any frost).
• Design details reviewed for bank sharp corner at upper channel and new cut and riprap being incorporated in
design today and tomorrow (survey crew to attend site with updates on best hydrology flow fit for upper
channel).

Items to Note:

• Pit Run and Armor Rock delivered and stockpiled for channel work on dike banks.
• Channel work started and bank trilling with excavator (EX300 Hitachi).
• EX200 Cat excavator with hoe-pac compact test section of pit run
• Design Drawings detailed for upper channel reviewed, and work plan revised to accommodate best flow
condition, updated cross-sections by RRA and additional drawings to be provided (IFC).

Radloff & Associates Representative: Randy Brown [Radloff rep]


Ph: 250-562-6861 Fax: 250-562-6826
DAILY CONSTRUCTION REPORT
1820 3rd Ave., Prince George, BC, V2M 1G4

Figure 1: Muster station ands laydown area set up with first aid arrangements (Dave Wilkins has all set up).

Figure 2: Channel riprap commenced with excavators (RRA review compaction of pit run work for hoe-pac and/or
plate tamper). Density testing ran by SoilTec.

Radloff & Associates Representative: Randy Brown [Radloff rep]


Ph: 250-562-6861 Fax: 250-562-6826
DAILY CONSTRUCTION REPORT
1820 3rd Ave., Prince George, BC, V2M 1G4

Figure 3: Lowhee channel trimmed for riprap material (SoilTec ran density testing with RRA review).

EX200 Cat Excavator with hoe-pac and 1,000lb plate tamper tested for best compaction rates and effective compaction.

Radloff & Associates Representative: Randy Brown [Radloff rep]