关丹隧道南侧出口拱顶下沉观测数据表(KUANTAN TUNNEL SOUTH

PORTAL RELATIVE CROWN SETTLEMENT DATA RECORD)


测点里程(CHAINAGE): CH312+895 初测时间(INITIAL TIME): 7/21/2019 点号(POINT No.): 1
时间(date&time) 时间间隔 累积下沉
本次下沉量( 下沉速率 等级管理 备注
总天数 (time 标高 (total
difference) (rate)(mm/ (managemen (remark
(days) 年月日 时 interval) (level(m) difference)
(mm) d) t level) )
(d) (mm)
138 12/6/2019 9 1 34.0279 0 0.0000 60.7 Ⅱ
139 12/7/2019 10 1 34.0279 0 0.0000 60.7 Ⅱ
140 12/8/2019 15 1 34.0278 0.1 0.1000 60.8 Ⅱ
141 12/9/2019 16 1 34.0277 0.1 0.1000 60.9 Ⅱ
142 12/10/2019 11 1 34.0277 0 0.0000 60.9 Ⅱ
143 12/11/2019 10 1 34.0276 0.1 0.1000 61 Ⅱ
144 12/12/2019 15 1 34.0275 0.1 0.1000 61.1 Ⅱ
145 12/13/2019 10 1 34.0275 0 0.0000 61.1 Ⅱ

management
classification countermeasures 对策
Ⅲ the normal construction正常施工
undertake comprehensive assessment on design and construction measures,enchance the
Ⅱ monitoring and measurement,take relevant engineening countermasures if necessity.对设计和
施工措施进行综合评价,进行监测和测量,必要时采取相应的工程措施

suspend construction and take relevant engineering countermeasures暂停施工并采取相应的工



程措施

拱顶累积沉降 (data chart) ( mm )


160 Ⅰdisplacement limit value 极限位移
140 值 U0

120 Ⅱ 、Ⅲ boundary value line 级分


累积沉降量 (total difference)

界值线 2U0/3(mm)
100
80 Ⅲ level threshold 级上限值
( mm)U0/3
60
Column H
40
20
0
12/6/2019

12/7/2019

12/8/2019

12/9/2019

12/10/2019

12/11/2019

12/12/2019

12/13/2019

测量(surveyed by): 检核(witnessed by):


Settlement Gauge - Monitoring Report

Chainage: CH 2200 Inital Date: 5/30/2024

Date & Time Value of


Level Ground Level Fill Total Settlement
Days Time(d) Settlement Remark
(YYYY /MM (m) (m) Thickness (m) amount(mm)
Time (mm)
/DD)
0 2024/05/30 10:00 0 34.7700 33.2560 0.00 0.0 0.0 Base Reading
7 2024/06/06 9:35 7 34.7680 34.7000 1.44 2.0 2.0
14 2024/06/13 9:40 14 35.9600 35.8760 2.62 0.0 2.0 Extended 1st pipe
21 2024/06/20 9:00 21 35.9590 35.8760 2.62 1.0 3.0

Settlement Gauge Monitoring Report

10.0

8.0
Fill Thickness(m)

6.0

4.0

2.0

0.0
0 7 14 21 10

Time (Days)

60

110

Fill Thickness (m) Total Settlement amount ( mm )

Surveyed by: Checked by:


Settlement Gauge - Monitoring Report

Chainage: CH 2620 Inital Date: 6/13/2024

Date & Time Value of


Level Ground Level Fill Total Settlement
Days Time(d) Settlement Remark
(YYYY /MM (m) (m) Thickness (m) amount(mm)
Time (mm)
/DD)
0 2024/06/13 9:50 0 34.6410 33.3000 0.00 0.0 0.0 Base Reading
7 2024/06/20 9:15 7 34.6390 33.6110 0.31 2.0 2.0

Settlement Gauge Monitoring Report

10.0

8.0
Fill Thickness(m)

6.0

4.0

2.0

0.0
0 7 10

Time (Days)

60

110

Fill Thickness (m) Total Settlement amount ( mm )

Surveyed by: Checked by: