NORTH RUMAILA IBC

IRAQ SOUTH GAS PROJECT


Rehabilitation of Iraq South Gas Facilities Misc. Eng. Works for NR IBCs (UI-42859)

INSPECTION TEST PLAN For PRE-Fabrication, Fabrication


erection and testing of welded piping
Status
Status Code Description
Code
WORK MAY PROCEED.
 1
PROCEED, CHANGE AS NOTED AND RE-SUBMIT
 2
DO NOT PROCEED, REVISE AS PER COMMENTS AND RE-SUBMIT
 3
FOR INFORMATION ONLY, NO REVIEW REQUIRED
 4
VOID-TO BE CANCELLED / DELETED/REJECTED
 X
“Code A”, “Code B” and “Code I” endorsed on Subcontractor data by Contractor and/or Company shall not relieve
the Subcontractor from full responsibility for any errors or omissions, therein, or limit the Subcontractor obligations
for conformance to Specification to Contract requirements.
Reviewing Engineer’s Name (IN BLOCK LETTERS), Sign and Date

Name: Sign: Date:


st
Note: This sheet shall be the 1 cover page of all A3 & A4 documents. This block will also form
part of the A3 drawing template.

ALYAMAMA Eng. Co.


TITLE:

INSPECTION TEST PLAN For PRE-Fabrication,


Fabrication erection and testing of welded piping

Purpose of it: For Approval


Attached to it: INSPECTION TEST PLAN (ITP)

FOR
02A 28.09.2014 MA EM EM
APPROVAL
DOC SIZE: A4
FOR YAMA DOCS No:
01A 30.08.2014 MA EM EM
APPROVAL ALYAM-N001-00392-TX REV.
Doc. No.:
REV DESCRIPTION DATE PRPD CHKD APPD 02A
3000-ALYAM-N001-PR01-U10000-QA-5733-00010