PIPELINE & FLOWLINE

TRENCH PREPARATION INSPECTION


RECORD
Report No.: 01 Date: 02.12. 2007

Client: DEZPC Project:TAB-110-F/L Contract No.: 05-24

Section No.: 01 From Joint No.: 3 To Joint No.: 7

Item Description Yes No

1) Depth of trench meets the specified depth in TOTAL Specifications √

2) Padding material meets the required thickness specified in Specifications in TOTAL √

3) Padding material is free from large stones, rocks and hard boulders √

4) Padding of sand river 15cm around the pipe. √

5) Trench is clean and free from timber, sticks, stones, hard clods and projecting rocks. √

Normal Ground

Comments:
Width of The Trench : 80 cm
Depth of The Trench : 150 cm

BUTEMAC Representative Client Representative