Sour Water Stripper Project Schedule Date: 06 May 2024

Work Completion
SN List of Remaining Work Start date End date Total days till date (%) Remarks

1 BOQ for Pipe, Fittings & structure 6 May 2024 7 May 2024 2 100
2 Ready for remaining 04 nos. pump 6 May 2024 15 May 2024 10
3 Fabrication of all vessels 6 May 2024 30 May 2024 25
4 Fabrication of Tower 10 May 2024 30 May 2024 21
5 Fabrication of 3 nos. Exchanger 15 May 2024 20 June 2024 37
6 Welding of all vessels with nozzle and other accessories 30 May 2024 25 June 2024 27
7 Welding of Tower with nozzle and other accessories 30 May 2024 25 June 2024 27
8 Welding of Exchanger 20 June 2024 10 July 2024 21
9 Installation of all pump on field 15 May 2024 30 June 2024 47
10 NDT of all vessel and tower 30 May 2024 30 June 2024 32 95
11 Hydrotest of all vessel 1 July 2024 5 July 2024 5 80
12 Hydrotest of Tower 6 July 2024 10 July 2024 5 85
13 Installation of all vessel, Tower, structure, and exchangers 5 June 2024 20 July 2024 46 80
14 Installation of internal tray 20 July 2024 30 July 2024 11 84
15 Pipe fabrication on shop 20 June 2024 20 July 2024 31
16 Pipe welding and erection on field 30 June 2024 20 August 2024 52
17 NDT of all pipe network 30 June 2024 25 August 2024 57
18 Hydrotest of pipe network 26 August 2024 31 August 2024 6
19 Flushing and leak test of pipe network 2 September 2024 5 September 2024 4
20 Surface cleaning and painting 15 August 2024 25 September 2024 42
21 Insulation work 10 September 2024 10 October 2024 31
Insulation work
Surface cleaning and painting
Flushing and leak test of pipe network
Hydrotest of pipe network
NDT of all pipe network
Pipe welding and erection on field
Pipe fabrication on shop
Installation of internal tray
Installation of all vessel, Tower, structure, and exchangers
Hydrotest of Tower
Hydrotest of all vessel
NDT of all vessel and tower
Installation of all pump on field
Welding of Exchanger
Welding of Tower with nozzle and other accessories
Welding of all vessels with nozzle and other accessories
Fabrication of 3 nos. Exchanger
Fabrication of Tower
Fabrication of all vessels
Ready for remaining 04 nos. pump
BOQ for Pipe, Fittings & structure
9 January 2024 28 February 2024 18 April 2024 7 June 2024 27 July 2024 15 September 2024 4 November 2024
Sour Water Stripper Project Schedule Date: 19 June 2024
Total Group
SN List of Remaining Work Start date End date Total days Group No. Remarks
Days
1 Fabrication and welding of all vessels 22 June 2024 15 July 2024 24 3 72
2 Fabrication and welding of Tower 22 June 2024 10 August 2024 50 2 100
3 Fabrication and welding of 3 nos. Exchanger 30 June 2024 5 August 2024 37 3 111
4 Installation of all pumps on field 5 July 2024 20 July 2024 16 2 32
5 NDT of all vessel and tower 28 June 2024 30 August 2024 64 0
6 Hydrotest of all vessel 16 July 2024 18 July 2024 3 1 3
7 Hydrotest of Tower 11 August 2024 14 August 2024 4 1 4
8 Installation of all vessel, Tower, structure, and exchangers 15 August 2024 20 August 2024 6 2 12
9 Installation of internal tray 21 August 2024 5 September 2024 16 2 32
10 Pipe welding and erection on field 21 August 2024 19 September 2024 30 2 60
11 Tie-in Pipe network and structural work 10 September 2024 15 October 2024 36 3 108
12 NDT of all pipe network 10 September 2024 20 October 2024 41 0
13 Hydrotest of pipe network 20 October 2024 23 October 2024 4 2 8
14 Flushing and leak test of pipe network 23 October 2024 25 October 2024 3 2 6
15 Surface cleaning and painting 15 September 2024 10 November 2024 57 0
16 Insulation work 11 November 2024 20 November 2024 10 0
Total 25 548
Insulation work
Surface cleaning and painting
Flushing and leak test of pipe network
Hydrotest of pipe network
NDT of all pipe network
Tie-in Pipe network and structural work
Pipe welding and erection on field
Installation of internal tray
Installation of all vessel, Tower, structure, and exchangers
Hydrotest of Tower
Hydrotest of all vessel
NDT of all vessel and tower
Installation of all pumps on field
Fabrication and welding of 3 nos. Exchanger
Fabrication and welding of Tower
Fabrication and welding of all vessels
28 February 2024 18 April 2024 7 June 2024 27 July 2024 15 September 2024 4 November 2024 24 December 2024