SCOPE OF WORK
PROJECT Asia Enclaves Sato 3 Unit 327H
CLIENT NAME Roan Kamille Gabinete
CONTRACTOR Styled Spaces – Jonathan Salialam
TIMELINE 8 weeks
ITEM REMARKS
CEILING WORKS
Construct and install dropped ceiling in living area and bedrooms Will observe appropriate clearance for
sprinklers and smoke detectors as prescribed by
admin
PAINTING WORKS
Painting of ceiling and retouching of several areas as needed
Repaint all walls
CARPENTRY WORKS
Living Area / Kitchen Area
Re-laminate existing kitchen upper cabinets ***Note for all fitouts:
Install T5 underlighting on kitchen upper cabinets ALL fabrication to be done off-site; for delivery
and install; Will observe no drilling/chipping on
structural component walls; will likewise
observe appropriate sprinkler clearance as
prescribed by admin if applicable
Install kitchen backsplash
Master’s Bedroom
Deliver and install dresser desk console
Relaminate WIC
Bathroom
Design, fabricate and install mirrored medicine cabinet Installation of medicine cabinet will be
coordinated with admin to ensure no existing
pipes might be damaged
Will coordinate installation with admin
GANTT CHART
WEEK
ACTIVITY
1 2 3 4 5 6 7 8
Ceiling works (including framing and painting)
Cove ceiling – living area and bedrooms
Bathroom works
Painting works
Carpentry works (offsite fabrication; for delivery and install)
Living Area
Bathrooms
Master’s Bedroom
Electrical works
Cleaning and finalizing
Furnishing and unit staging
_____________________________ _____________________________
Jonathan Salialam Roan Kamille Gabinete
Styled Spaces Unit owner